Pedestrian Street Lighting Improvement Project
First seen: July 12, 2022
Last seen: July 12, 2022
Lifecycle Timeline
July 12, 2022Council
Full RecordingPedestrian Street Lighting Project - Direct Award
Council approved the direct award of the Helmcken Road lighting upgrade and deferred the Chilco/Lund intersection to the following year due to budget constraints.
"Staff reported that construction quotes exceeded the $99,000 budget for the planned three locations. To proceed this year, staff recommended deferring the Chilco Road/Lund Road intersection improvements to 2023. This allowed the Helmcken Road roundabout improvements to move forward and be direct awarded to Victoria Contracting & Municipal Maintenance Corporation (VCMMC) for $99,575 plus GST, minimizing disturbance and aligning with other LED upgrades."
Formal MotionPassed
"THAT the Committee recommend to Council that staff move forward with the Pedestrian Street Lighting Improvement project for both roundabouts on Helmcken Road and defer the improvements at the Chilco Road/Lund Road intersection to 2023; AND THAT the 2022 Pedestrian Street Lighting Improvement project be awarded to Victoria Contracting & Municipal Maintenance Corporation (VCMMC) in the amount of $99,575 plus GST. (COW-19-22)"
Moved by: David Screech
Seconded by: John Rogers
David Screech
Damian Kowalewich
Ron Mattson
John Rogers