Letter received July 8, 2024 from L. Pakos, Re: Sidewalk on Glenairlie Drive
First seen: July 16, 2024
Last seen: July 16, 2024
Lifecycle Timeline
July 16, 2024Council
Full RecordingLetter received July 8, 2024 from L. Pakos, Re: Sidewalk on Glenairlie Drive
"Councillor Lemon argued for a safe route for children walking to View Royal Elementary, stressing the need for a sidewalk extension to the schoolyard gate on Rudyard Road. Councillor Rogers noted that staff had recently cut back overgrown vegetation to improve safety in the short term, but cautioned that a full sidewalk would require a costly retaining wall due to the considerable drop-off. Council voted to refer the project for cost assessment during the 2025 budget deliberations."
Formal MotionPassed
"THAT a Project Summary to extend the Glenairlie Drive sidewalk to the View Royal Elementary School yard gate on Rudyard Road be brought forward to the 2025 budget deliberations."
Moved by: Gery Lemon
Seconded by: Ron Mattson
Sid Tobias
Don Brown
Damian Kowalewich
Gery Lemon
Ron Mattson
Alison MacKenzie
John Rogers