C-102-12GeneralActiveFollow Matter

Juan de Fuca Cable Project

First seen: July 17, 2012
Last seen: July 17, 2012

Lifecycle Timeline

July 17, 2012Council
Full Recording

S. van Mulligen, Sea Breeze Power Corp., Re: Juan de Fuca Cable Project Update

Formal MotionPassed
"THAT View Royal staff engage Sea Breeze Power Corporation in discussions about the Juan de Fuca Cable Project as soon as possible; AND THAT Seabreeze Power Corporation be requested to strike the Island Highway option from the routing plans."
Moved by: David Screech
Seconded by: John Rogers
Graham Hill
Heidi Rast
John Rogers
David Screech