C-224-08DevelopmentCompletedFollow Matter

Development Permit No. 08/08 (Thetis Cove)

First seen: September 16, 2008
Last seen: July 21, 2009

Lifecycle Timeline

July 21, 2009Council
Full Recording

Thetis Cove Phase 2 Form and Character Development Permits

Council rescinded the Development Permit previously issued for Thetis Cove Phase II.

Formal MotionPassed
"THAT resolution C-224-08 authorizing the issuance of Development Permit 08/08 for Phase II of Thetis Cove be rescinded."
Moved by: David Screech
Seconded by: John Rogers
Graham Hill
Heidi Rast
John Rogers
David Screech
September 16, 2008Council
Full Recording

Development Permit No. 08/08 (Thetis Cove)

Formal MotionPassed
"THAT Development Permit No. 08/08 be approved as presented."
Moved by: John Rogers
Seconded by: Nicholas Anderson
Graham Hill
Andrew Britton
Geri Anderson
John Rogers
David Screech