Committee of the Whole/Documents/PUBLIC SAFETY BUILDING TIMING OF FUNDING
Staff Report

PUBLIC SAFETY BUILDING TIMING OF FUNDING

March 4, 2013Pages 2–42 sections

A report from the Director of Finance outlining four options for the timing of tax increases to fund a new public safety building, including projections for interest costs and principal payments through 2017.

3a Public Safety Building Timing of Funding
Report date: February 8, 2013Estimated tax increase based on 2013 BC Assessment: 6.36%Projected completion: fall 2014Debenture term: 20 yearsTotal annual cost for View Royal by 2015: $350,593Option 2 proposes a steady 2.12% annual tax increase over three yearsOption 3 weighs the increase more heavily early on with 3.0% increases in 2013 and 2014
Page 2–4

TOWN OF VIEW ROYAL COMMITTEE OF THE WHOLE REPORT

TO: Committee of the Whole DATE: February 8, 2013 FROM: Jeannie Beauchamp, Director of Finance MEETING DATE: February 12, 2013

PUBLIC SAFETY BUILDING TIMING OF FUNDING

RECOMMENDATION: THAT the Committee receive the February 12, 2013 Public Safety Building Timing of Funding Report for information.

CHIEF ADMINISTRATIVE OFFICER'S COMMENTS: I concur with the recommendation.

FIRE CHIEF'S COMMENTS: I concur with the recommendation.

PURPOSE OF REPORT:

To provide Council with information regarding options for the timing of funding the new public safety building.

DISCUSSION:

In 2012, the public was informed that the estimated cost to the average resident would be a tax increase of 6.7%. This estimate was based on the 2012 BC Assessment Revised Roll. The figures in this report are based on the 2013 BC Assessment Completed Roll. The estimated tax increase based on this assessed value is 6.36%.

The public safety building is projected to be completed in the fall of 2014. It is currently anticipated that half the impact will be realized in 2014 and half in 2015. Interest costs will begin in 2013 as the debt amount will be temporarily borrowed before it is transitioned into long-term debt. The following budgeted costs are based on anticipated interest rates at the time of borrowing and a debenture term of 20 years.

2013 2014 2015 2016 2017
Interest Costs 30,000 125,000 192,150 192,150 192,150
Principal Payment - 92,182 184,364 184,364 184,364
Total Cost 30,000 217,182 376,514 376,514 376,514
Est Additional Contribution 2,065 14,952 25,921 25,921 25,921
View Royal $27,935 $202,230 $350,593 $350,593 $350,593
Annual % Increase to SF Home 0.51% 3.16% 2.69% 0% 0%

Council may choose to amend the timing of the tax increase to lessen the burden on taxpayers in any given year. This can be done by adjusting the contribution to the Fire Department Reserve, which will result in the desired tax increase in each year. The reserve contribution will be available to assist in funding the new public safety building, and could be used to reduce the amount of debt necessary for the project.

Option 1

Council may choose to leave the timing as currently presented.

Option 2

Council may choose to adjust the timing so that it impacts residents evenly over a three year period.

2013 2014 2015 2016 2017
Interest Costs 30,000 125,000 192,150 192,150 192,150
Principal Payment - 92,182 184,364 184,364 184,364
Trf to Reserve 95,505 33,828 - - -
Total Cost 125,505 251,010 376,514 376,514 376,514
Est Additional Contribution 8,640 17,280 25,921 25,921 25,921
View Royal $116,865 $233,730 $350,593 $350,593 $350,593
Annual % Increase to SF Home 2.12% 2.12% 2.12% 0% 0%

Option 3

Council may choose to weigh the increase more heavily early on.

2013 2014 2015 2016 2017
Interest Costs 30,000 125,000 192,150 192,150 192,150
Principal Payment - 92,182 184,364 184,364 184,364
Trf to Reserve 148,000 138,818 - - -
Total Cost 178,000 356,000 376,514 376,514 376,514
Est Additional Contribution 12,255 24,509 25,921 25,921 25,921
View Royal $165,745 $331,491 $350,593 $350,593 $350,593
Annual % Increase to SF Home 3.0% 3.0% .35% 0% 0%

Option 4

Council may choose to bring a portion of the increase on in 2013.

2013 2014 2015 2016 2017
Interest Costs 30,000 125,000 192,150 192,150 192,150
Principal Payment - 92,182 184,364 184,364 184,364
Trf to Reserve 59,000 - - - -
Total Cost 89,000 217,182 376,514 376,514 376,514
Est Additional Contribution 6,127 14,952 25,921 25,921 25,921
View Royal $82,873 $202,230 $350,593 $350,593 $350,593
Annual % Increase to SF Home 1.50% 2.16% 2.69% 0% 0%

RECOMMENDATION: THAT the Committee receive the February 12, 2013 Public Safety Building Timing of Funding Report for information.

SUBMITTED BY:

J. Beauchamp, Director of Finance

REVIEWED BY:

K. Anema, Chief Administrative Officer

Page 2–4
Extracted from: 2013 03 04 Committee of the Whole Budget Agenda