Staff Report
SITE REPORT No. 27 - 1122 VIEW ROYAL PUBLIC SAFETY BUILDING
April 8, 2014Pages 34–442 sections
Construction progress report for the new Public Safety Building, including site photos and financial budget status.
April 2, 2014Total revised budget: $7,402,160Projected expenditures to date: $2,788,481Construction activities include floor framing and concrete pouring for Level 2
SITE REPORT No. 27
TO: Ledcor Construction Ltd. Mike Forsyth / Jan Coetzee 203 - 830 Shamrock Street Victoria, BC V8X 2V1
FROM: Heather Spinney
CC: Paul Hurst / Kim Anema + Gary Faykes (Bldg Inspector) View Royal Adam Fawkes, Roger Hughes, HCMA Jonathan Reiter, RJC Tom Wilson, AME Iain Barnes, AES Jeff Ball / Gene Mazza, Associated Engineering Shane Moore, Ryzuk
PROJECT: 1122 VIEW ROYAL PUBLIC SAFETY BUILDING DATE: 2014.04.02
Date of visit: 2014.03.27 Weather: 12°C, Mix of Sun & Cloud Present: Heather Spinney
End of Site Report Number 27
Page 34–44
PUBLIC SAFETY BUILDING

| Budget after Tender | Revisions | Revised Budget | As at Mar. 31, 2014 | Committed | Total | Budget Variance | |
|---|---|---|---|---|---|---|---|
| Planning and Design | $ 527,025 | $ 2,300 | $ 529,325 | $ 423,656 | $ - | $ 423,656 | $ 105,669 |
| Tendered Price (note 1) | |||||||
| Base Tendered Price | 4,948,264 | - | 4,948,264 | 1,496,421 | - | 1,496,421 | 3,451,843 |
| Cash Allowances | 805,347 | - | 805,347 | 601,168 | - | 601,168 | 204,179 |
| 5,753,611 | - | 5,753,611 | 2,097,589 | - | 2,097,589 | 3,656,022 | |
| Reserves and Contingencies | 224,060 | (128,087) | 95,973 | - | - | - | 95,973 |
| Extras Approved | |||||||
| Remove Tree 880 & 725 | - | 1,964 | 1,964 | 1,964 | - | 1,964 | - |
| Remove Tree | - | 2,097 | 2,097 | 2,097 | - | 2,097 | - |
| Remove AC Pipe | - | 964 | 964 | 964 | - | 964 | - |
| Swimming Pool Removal | - | 1,244 | 1,244 | 1,244 | - | 1,244 | - |
| Revise Water Entry | - | 1,020 | 1,020 | - | 1,020 | 1,020 | - |
| Additional ACM unearthed | - | 420 | 420 | 420 | - | 420 | - |
| Modify Pavement Structure | - | (4,032) | (4,032) | (4,032) | - | (4,032) | - |
| Tree Removal #3 | - | 2,393 | 2,393 | 2,393 | - | 2,393 | - |
| Structural Steel Axial Loads | - | 6,132 | 6,132 | - | 6,132 | 6,132 | - |
| Embed & Anchor Details | - | 760 | 760 | - | 760 | 760 | - |
| Additional ACM | - | 400 | 400 | 400 | - | 400 | - |
| Revise Circuits & Panels | - | (4,487) | (4,487) | (4,487) | - | (4,487) | - |
| Water to Hydrant & Gas Trench | - | 5,660 | 5,660 | - | 5,660 | 5,660 | - |
| Add conduits to comm trench | - | 3,155 | 3,155 | 1,500 | 1,655 | 3,155 | - |
| Relocate grease interceptor | - | 2,311 | 2,311 | - | 2,311 | 2,311 | - |
| Hose tower - new door | - | 2,530 | 2,530 | 1,518 | 1,012 | 2,530 | - |
| Retaining Wall - type 1 - East PL OPT A | - | 47,949 | 47,949 | 43,154 | 4,795 | 47,949 | - |
| Revised embedded plate details | - | 2,391 | 2,391 | - | 2,391 | 2,391 | - |
| O/H door supports | - | 4,886 | 4,886 | - | 4,886 | 4,886 | - |
| Solid fill CMU cells | - | 1,191 | 1,191 | 1,191 | - | 1,191 | - |
| Damp proofing | - | (10,000) | (10,000) | - | (10,000) | (10,000) | - |
| Addl Lights in Training Area | - | 6,603 | 6,603 | - | 6,603 | 6,603 | - |
| Laundry repair venting | - | 2,816 | 2,816 | - | 2,816 | 2,816 | - |

| Budget after Tender | Revisions | Revised Budget | As at Mar. 31, 2014 | Committed | Total | Budget Variance | |
|---|---|---|---|---|---|---|---|
| Flagpole lighting | - | 5,349 | 5,349 | - | 5,349 | 5,349 | - |
| Add clean out | - | 777 | 777 | - | 777 | 777 | - |
| Retain slope at Soil Valley | - | 3,838 | 3,838 | - | 3,838 | 3,838 | - |
| Alternate locker finish | - | (16,617) | (16,617) | - | (16,617) | (16,617) | - |
| - | 71,714 | 71,714 | 48,324 | 23,390 | 71,714 | - | |
| Extras Proposed | - | 28,087 | 28,087 | - | - | - | 28,087 |
| Owner Changes Contemplated | 386,599 | - | 386,599 | - | - | - | 386,599 |
| Completion Costs | |||||||
| Furniture & Equipment | 150,000 | - | 150,000 | - | - | - | 150,000 |
| DCC | 41,760 | - | 41,760 | 41,760 | - | 41,760 | 0 |
| Building Permit/Testing Structural and Geotech. | 25,750 | 10,000 | 35,750 | 32,785 | - | 32,785 | 2,965 |
| Connection Fees (BC Hydro Fee) | 48,115 | 15,986 | 64,101 | 52,101 | - | 52,101 | 12,000 |
| Administration Costs | 10,000 | - | 10,000 | - | - | - | 10,000 |
| Legal Costs | 8,000 | - | 8,000 | 5,862 | - | 5,862 | 2,138 |
| Insurance Costs | 11,340 | - | 11,340 | 11,340 | (11,340) | - | 11,340 |
| Public Art | 35,000 | - | 35,000 | - | - | - | 35,000 |
| Operation/Startup Costs | 35,000 | - | 35,000 | - | - | - | 35,000 |
| 364,965 | 25,986 | 390,951 | 143,848 | (11,340) | 132,508 | 258,443 | |
| Adjusted Construction Cost Total | $ 7,256,260 | $ - | $ 7,256,260 | $ 2,713,417 | $ 12,050 | $ 2,725,468 | $ 4,530,792 |
| Off Site Services | |||||||
| Off Site Design | 30,000 | - | 30,000 | 30,807 | - | 30,807 | (807) |
| Storm Drain | 60,000 | - | 60,000 | 43,607 | - | 43,607 | 16,393 |
| Traffic Control (fire warning flashers) | 30,000 | - | 30,000 | 650 | - | 650 | 29,350 |
| Traffic Islands / Painting | 5,000 | - | 5,000 | - | - | - | 5,000 |
| Electrical Conduit Crossing | 9,400 | - | 9,400 | - | - | - | 9,400 |
| Fibre Conduit Crossing | 11,500 | - | 11,500 | - | - | - | 11,500 |
| $ 145,900 | $ - | $ 145,900 | $ 75,063 | $ - | $ 75,063 | $ 70,837 |

| Budget after Tender | Revisions | Revised Budget | As at Mar. 31, 2014 | Committed | Total | Budget Variance | |
|---|---|---|---|---|---|---|---|
| Total Construction and Off Site Services | $ 7,402,160 | $ - | $ 7,402,160 | $ 2,788,481 | $ 12,050 | $ 2,800,531 | $ 4,601,629 |
Note 1 Tendered price: 5,753,611 Tax charged (rebatable): 287,681 Total including tax: 6,041,292
Page 34–44