Committee of the Whole/Documents/Attachment 3: 2025 Non-Core Projects & Attachment 4: 2025 Capital Projects
Appendix
Attachment 3: 2025 Non-Core Projects & Attachment 4: 2025 Capital Projects
February 10, 2026Pages 81–822 sections
Tracking tables for non-core and capital projects including status updates and budget remaining for 2025.
Official community plan: $195,555 YTD expenseFire services vehicle replacement: $1,442,343 YTD expenseAtkins Rd sidewalk: $900,000 budget
Attachment 3: 2025 Non-Core Projects
| Division / Project Name | Project # | CC | Budget | YTD | Variance | % Budget Remaining | Comments |
|---|---|---|---|---|---|---|---|
| General Government Services | |||||||
| Cyber security policies/process | N-088 | 160-11 | 10,000 | - | 10,000 | 100% | Carry forward to 2026 to align RIM project |
| Data mgmt plan & road map | N-088 | 160-12 | 20,000 | - | 20,000 | 100% | Carry forward to 2026 to align RIM project |
| IT asset inventory solution | N-088 | 160-09 | 8,500 | - | 8,500 | 100% | To be completed within existing operating resources |
| Multi-factor authentication | N-088 | 160-08 | 6,800 | - | 6,800 | 100% | Carry forward to 2026 as account security review |
| Accessibility plan development | N-101 | 140-15 | 1,500 | 1,411 | 89 | 6% | |
| Asset management program improvements | N-111 | 150-05 | 76,275 | 48,190 | 28,085 | 37% | Data audit project complete. LOS work is nearing completion |
| Truth and reconciliation awareness | N-068 | 140-11 | 7,650 | 975 | 6,675 | 87% | |
| Website refresh - NEW | N-047 | 140-06 | 19,500 | 2,960 | 16,540 | 85% | Carryover. Project is still progressing. |
| Cool it! Climate action leadership training | N-114 | 140-16 | 3,000 | 1,200 | 1,800 | 60% | |
| Volunteer community improvement grant program | N-110 | 120-05 | 2,500 | - | 2,500 | 100% | |
| General Government Services Total | 155,725 | 54,736 | |||||
| Protective Services | |||||||
| FireSmart program | N-113 | 210-06 | 200,000 | 171,962 | 28,038 | 14% | |
| Next Gen 911 preparedness | N-112 | 210-05 | 45,000 | 15,715 | 29,285 | 65% | |
| Emergency mgmt indigenous engagement - NEW | N-122 | 230-08 | 96,000 | 38,000 | 58,000 | 60% | |
| ESS Supplies Grant Program | N-119 | 230-05 | 40,000 | 5,469 | 34,531 | 86% | |
| Secondary suites online renewal - NEW | N-083 | 220-02 | 5,500 | - | 5,500 | 100% | |
| Protective Services Total | 386,500 | 231,146 | |||||
| Transportation Services | |||||||
| Speed limit reduction implement - NEW | N-125 | 310-16 | 20,000 | 4,000 | 16,000 | 80% | Signs have been purchased - not recorded in Vadim yet |
| Drainage master plan update | N-098 | 310-09 | 208,000 | 112,604 | 95,396 | 46% | Work in progress - carryforward required |
| Transportation master plan update | N-105 | 310-15 | 200,000 | 52,366 | 147,634 | 74% | In progress. Carryover required to 2026 (completion fall 2026) |
| Transportation Services Total | 428,000 | 168,970 | |||||
| Development Services | |||||||
| Coastal adaptation plan | N-089 | 510-28 | 75,000 | 45,577 | 29,423 | 39% | This project received a grant and it is anticipated to be completed in 2026. |
| Official community plan | N-025 | 510-02 | 155,000 | 195,555 | -40,555 | -26% | Council passed the following motion to add an additional $90,000 to the 2025 budget: THAT an additional $90,000 from the Growing Communities Fund be allocated to the 2025 budget for the Official Community Plan review and update (Non Core Project N-025) to enable staff to carry on with Phase 1 and begin substantial work on Phase 2 of the Official Community Plan update; AND THAT the 2025-2029 Financial Plan be amended accordingly. The additional funds allocated to the project will have to be carried over to 2026 to complete the project. |
| Zoning Bylaw updates | N-118 | 510-38 | 40,000 | - | 40,000 | 100% | Carry over to 2026. |
| Development Services Total | 270,000 | 241,132 | |||||
| Parks Services | |||||||
| Invasive Species Portage Park - NEW | N-123 | 300-03 | 10,000 | 1,278 | 8,722 | 87% | in progress. Within GVGT service agreement |
| Urban forestry strategy | N-074 | 310-14 | 65,874 | 67,789 | -1,915 | -3% | Expected to be fully completed in December |
| Parks Services Total | 75,874 | 69,067 | |||||
| TOTAL | 1,316,099 | 765,050 |
Page 81–82
Attachment 4: 2025 Capital Projects
| Division / Project Name | Project # | CC | Budget | YTD | Variance | % Budget Remaining | Comments |
|---|---|---|---|---|---|---|---|
| General Government Services | |||||||
| Bylaw office move - NEW | C-190 | 1287 | 55,000 | 39,261 | 15,739 | 29% | |
| Land acquisition - NEW | C-003 | 1045 | 175,000 | 39,009 | 135,991 | 78% | |
| Town Hall roof and gutter replace - NEW | C-192 | 1298 | 20,000 | 2,120 | 17,880 | 89% | carryforward required |
| Accessible entrance town hall - NEW | C-189 | 1286 | 18,000 | 180 | 17,820 | 99% | competitive bid process yielded no bids. Will look to single source but expectation is that it will not commence until 2026 as a result |
| Ergonomic workstation replacement | C-101 | 1226 | 55,000 | 25,219 | 29,781 | 54% | Carryover. Installation of soundproofing delayed due to supplier issues. |
| Electronic Records Mgmt System | C-004 | 1038 | 172,000 | - | 172,000 | 100% | Carryover. Project is ongoing. |
| IT infrastructure hardware replacements | C-038 | 1044 | 20,000 | 13,937 | 6,063 | 30% | Completed |
| IT workstation ever-greening | C-040 | 1070 | 47,500 | 36,701 | 10,799 | 23% | Completed |
| Town Hall energy conservation measures | C-172 | 1275 | 5,500 | - | 5,500 | 100% | no commenced due to short staffed and short resources. Would look to carry forward in 2026 (not a high priority though) |
| General Government Services Total | 568,000 | 156,427 | |||||
| Protective Services | |||||||
| Emergency program storage - NEW | C-193 | 1290 | 24,000 | - | 24,000 | 100% | |
| ESS Vehicle Replace 2002 Chev - NEW | C-199 | 1302 | 60,000 | 51,889 | 8,111 | 14% | |
| Fire services vehicle replacement-1992 Superior E-One | C-113 | 1240 | 1,572,500 | 1,442,343 | 130,157 | 8% | Complete |
| Rescue tool - NEW | C-194 | 1293 | 22,000 | 21,446 | 554 | 3% | |
| Community forest protection equipment | C-177 | 1280 | 25,000 | 22,236 | 2,764 | 11% | |
| RCMP bldg capital projects | C-010 | 1152 | 20,000 | 9,931 | 10,069 | 50% | |
| Protective Services Total | 1,723,500 | 1,547,844 | |||||
| Transportation Services | |||||||
| Atkins Rd sidewalk-Anya Crt to La | C-107 | 1234 | 900,000 | 16,996 | 883,004 | 98% | tender award Dec. 2. Carryforward required |
| Bridge Rehabilitation Program - NEW | C-184 | 1301 | 150,000 | 12,851 | 137,149 | 91% | works will be completed in 2026 per Council approval |
| Isl Hwy upgrades-Hart Rd to Wilf | C-066 | 1192 | 418,912 | 385,195 | 33,717 | 8% | complete |
| Traffic signal renewal program - NEW | C-186 | 1294 | 70,000 | 1,980 | 68,020 | 97% | works will be completed in 2026 per Council approval |
| Admirals Road active transportation improvements | C-180 | 1283 | 3,000 | - | 3,000 | 100% | |
| Curb and sidewalks-Burnside Rd W-Helmcken to Saanich border | C-117 | 1247 | 90,000 | - | 90,000 | 100% | deferred per Council direction |
| GPS replacement - NEW | C-195 | 1296 | 13,000 | 11,551 | 1,450 | 11% | complete |
| LED lighting upgrades | C-065 | 1194 | 30,000 | - | 30,000 | 100% | complete |
| Six Mile Road improvements | C-018 | 1168 | 306,911 | 2,202 | 304,709 | 99% | |
| Six Mile Rd crosswalks | C-018 | 1257 | 75,000 | - | 75,000 | 100% | |
| Isl Hwy-4 Mile Trestle to Shoreline | C-020 | 1154 | 15,000 | - | 15,000 | 100% | |
| Island Hwy-Helmcken to Colw desgn | C-076 | 1200 | 295,215 | 138,319 | 156,896 | 53% | complete |
| Jedburgh Rd sidewalk design/cons | C-080 | 1204 | 375,172 | 388,130 | -12,958 | -3% | complete |
| VR Ave drainage-Beaumont to Stewart/Beaumont to Plowright | C-017 | 1124 | 5,000 | - | 5,000 | 100% | DEFERRED PER COUNCIL APPROVAL |
| Transportation Services Total | 2,747,210 | 957,224 | |||||
| Environmental Services | |||||||
| Sewer Main Emerg Repair Watkiss Bridge - NEW | C-201 | 1304 | 127,000 | 106,762 | 20,238 | 16% | complete |
| Atkins pump station pump replacements | C-030 | 1170 | 100,000 | 7,213 | 92,787 | 93% | |
| Glenairlie pump station upgrade | C-087 | 1210 | 517,500 | 12,646 | 504,854 | 98% | construction in progress |
| SCADA Pack Upgrades - NEW | C-200 | 1303 | 106,000 | - | 106,000 | 100% | carryforward required |
| Environmental Services Total | 850,500 | 126,622 | |||||
| Parks Services | |||||||
| Parks vehicle repl plan | C-031 | 1167 | 38,000 | 22,510 | 15,490 | 41% | 2025 works complete |
| PSB truck canopy - NEW | C-187 | 1295 | 10,000 | 8,583 | 1,417 | 14% | |
| Development of road ends | C-114 | 1274 | 40,000 | - | 40,000 | 100% | |
| Playground Repl Program | C-032 | 1199 | 410,000 | 63,819 | 346,181 | 84% | Chancellor |
| View Royal Park development | C-035 | 1028 | 254,341 | - | 254,341 | 100% | deferred per council approval |
| Burside/Watkiss HandyDart site dv | C-122 | 1241 | 165,240 | 17,483 | 147,757 | 89% | works in progress |
| Parks Services Total | 917,581 | 112,395 | |||||
| TOTAL | 6,806,791 | 2,900,512 |
Page 81–82
Extracted from: 2026 02 10 Committee of the Whole Meeting - Agenda - Pdf