Council Meeting/Documents/Schedule 3.1 Capital Projects
Appendix

Schedule 3.1 Capital Projects

March 3, 2026Pages 26–271 sectionOriginal PDF

Detailed list of multi-year capital projects by division including transportation, parks, and environmental services.

Admirals Road active transportation improvements 5-year total: $4,638,000Six Mile Road improvements 5-year total: $1,150,000

Schedule 3.1 Capital Projects

General Government services

Priority Project Description Project Summary 2026 2027 2028 2029 2030 5-Year Total
2-Required Accessible entrance town hall C-189 18,000 - - - - 18,000
2-Required Ergonomic workstation replacement C-101 104,800 35,000 - - - 139,800
3-Strategic Council Chamber Accessibility Ramp C-188 - 15,000 - - - 15,000
3-Strategic IT infrastructure hardware replacements C-038 30,000 40,000 30,000 30,000 30,000 160,000
3-Strategic IT workstation ever-greening C-040 30,000 30,000 30,000 30,000 30,000 150,000
5-Discretionary Parks shed electrification C-191 25,000 100,000 - - 0 125,000
General Government Services Total 207,800 220,000 60,000 60,000 60,000 607,800

Protective Services

Priority Project Description Project Summary 2026 2027 2028 2029 2030 5-Year Total
1-Critical Bylaw office move C-190 24,100 - - - - 24,100
2-Required Emergency program storage C-193 24,000 - - - - 24,000
2-Required Fire services vehicle replacement-1992 Superior E-One C-113 134,200 - - - - 134,200
2-Required SCBA cylinder and battery replacements C-130 - - 38,600 - - 38,600
3-Strategic Community forest protection equipment C-177 50,000 25,000 25,000 - - 100,000
3-Strategic RCMP bldg capital projects C-010 100,000 - - - - 100,000
Protective Services Total 332,300 25,000 63,600 - - 420,900

Transportation Services

Priority Project Description Project Summary 2026 2027 2028 2029 2030 5-Year Total
2-Required Atkins Rd sidewalk-Anya Crt to La (Carry-forward) C-107 514,500 - - - - 514,500
2-Required Bridge Rehabilitation Program C-184 253,000 150,000 - - - 403,000
2-Required Island Hwy and Prince Robert Drive realignment C-175 - - - - - -
2-Required Island Hwy upgrades-Helmcken Rd to Beaumont Ave C-012 - - - - - -
2-Required Traffic signal renewal program C-186 138,000 70,000 70,000 70,000 70,000 418,000
2-Required Ready Step Roll Program C-203 40,000 - - - - 40,000
3-Strategic Admirals Road active transportation improvements C-180 3,000 300,000 4,335,000 - - 4,638,000
3-Strategic Curb and sidewalks-Burnside Rd W-Helmcken to Saanich border C-117 - - - - - -
3-Strategic LED lighting upgrades C-065 30,000 30,000 30,000 30,000 30,000 150,000
3-Strategic Six Mile Road improvements C-018 240,000 - - - 910,000 1,150,000
3-Strategic Six Mile Road improvements C-018 70,000 - - - - 70,000
3-Strategic Six Mile Road improvements C-018 10,000 - - - - 10,000
4-Optimal Intersection improvements-Helmcken Rd at Watkiss Way C-128 500,000 220,000 - - - 720,000
4-Optimal Isl Hwy-4 Mile Trestle to Shoreline C-020 - 140,000 - 1,400,000 - 1,540,000
4-Optimal North Burnside drainage improvements C-129 - 200,000 - - - 200,000
4-Optimal VR Ave drainage-Beaumont to Stewart/Beaumont to Plowright C-017 - - - - - -
4-Optimal Bus shelter installation C-139 130,000 - - - - 130,000
4-Optimal Glenairlie Drive sidewalk C-196 - - 15,000 220,000 - 235,000
4-Optimal Six Mile offramp noise mitigation wall C-197 - - 85,000 1,100,000 - 1,185,000
4-Optimal Pride and Veterans Memorial Decorative Crosswalks C-202 40,000 - - - 40,000 80,000
Transportation Services Total 1,968,500 1,110,000 4,535,000 2,820,000 1,050,000 11,483,500

Environmental Services

Priority Project Description Project Summary 2026 2027 2028 2029 2030 5-Year Total
2-Required Atkins pump station pump replacements C-030 100,000 - - - - 100,000
2-Required Hallowell pump stn pump repl - NEW C-183 - - 40,000 610,000 - 650,000
2-Required Norquay pump station upgrade C-089 5,000 35,000 500,000 - - 540,000
2-Required Sewer gravity main upgrade-Fort Victoria to Pheasant Lane C-109 - 300,000 1,540,000 - - 1,840,000
2-Required Glenairlie pump station upgrade C-087 637,000 - - - - 637,000
2-Required Helmcken Park pump staton upgrade C-204 - - - - 30,000 30,000
2-Required View Royal pump station upgrade C-205 - - - 30,000 700,000 730,000
4-Optimal SCADA Pack Upgrades C-200 - 106,000 - - - 106,000
Environmental Services Total 742,000 441,000 2,080,000 640,000 730,000 4,633,000

Parks Services

Priority Project Description Project Summary 2026 2027 2028 2029 2030 5-Year Total
2-Required Parks vehicle repl plan C-031 - 198,800 - 150,000 - 348,800
3-Strategic Development of road ends C-114 - - 40,000 40,000 40,000 120,000
3-Strategic Hart Road Lime Kiln heritage restoration C-111 - 217,900 - - - 217,900
3-Strategic Helmcken Centennial Park master plan implementation C-034 - - 125,000 125,000 - 250,000
3-Strategic Playground Repl Program C-032 300,000 110,000 185,000 100,000 - 695,000
3-Strategic View Royal Park development C-035 35,000 - - 30,000 - 65,000
4-Optimal Burside/Watkiss HandyDart site dv C-122 153,440 - - - - 153,440
4-Optimal Heddle Trail to Prince Robert Drive fencing C-019 - - - - 30,000 30,000
5-Discretionary Eagle Creek Trail-circular path C-052 - - - 70,000 - 70,000
5-Discretionary Nursery Hill to Brydon Road trail connector C-091 - - - - 40,000 40,000
5-Discretionary Pop Up Off Leash Dog Park C-198 - - - 20,000 - 20,000
Parks Services Total 488,440 526,700 350,000 535,000 110,000 2,010,140

Grand Totals

Description 2026 2027 2028 2029 2030 5-Year Total
5-Year Total 3,739,040 2,322,700 7,088,600 4,055,000 1,950,000 19,155,340
Page 26–27
Extracted from: 2026 03 03 Council Meeting - Agenda - Pdf(193 pages total)