Council Meeting/Documents/Project Summary N-105: Transportation master plan update
Staff Report

Project Summary N-105: Transportation master plan update

March 3, 2026Page 562 sectionsOriginal PDF

Update to transportation growth modeling based on the 2026 OCP and Active Transportation Network Plan.

$147,600 budget in 2026Funded by DCCs and Casino revenue
Page 56

Project Summary

Priority: Critical
Public Engagement: Involve
Project Name: Transportation master plan update
Project Number: 1-2-03100-615 CC310-15
Submitted by: Ivan Leung, Director of Engineering
Director: Ivan Leung, Transportation Services

Executive Summary

This project was included in the 2024-2028 Financial Plan. The purpose of this project is to update the Town’s Transportation Master Plan to (1) confirm Active Transportation Network Planning initiatives; and (2) calibrate growth modelling with the updated Official Community Plan (completion in 2025/2026).

Business problem and opportunity

The last Transportation Master Plan was competed in 2008, with a technical update in 2016. Given (1) the growth in View Royal since the latest update, (2) the completion of the Active Transportation Network Plan, and (3) the anticipated completion of the Official Community Plan in 2025-2026, an update to the transportation model will be beneficial to maintain an accurate representation of the long-term outlook for the Town’s transportation corridors.

Proposed project objectives

The objective of this project is to provide a long term, updated 10-year and 20-year outlook. This in turn would inform any updates that may be suggested for the Town’s bylaws including but not limited to the Subdivision and Development Servicing Bylaw 985 (2017) and the Development Cost Charges Bylaw 1011 (2019). The update would include:

  • Updated transportation network model to reflect the OCP and Active Transportation Network Planning;
  • Confirm and prioritize the long-term infrastructure improvements identified in the Active Transportation Network Plan and the OCP. This would include but is not limited to opportunities such as roundabouts, trail connectors, and cross section changes.

Business risks

This project was initially “place held” until the Active Transportation Network Plan (ATNP) and the Official Community Plan (OCP) is updated. While the ATNP has been completed, the OCP is scheduled for completion in 2025/2026. Staff recommend commencing the Transportation Master Plan during the same year as the OCP (2025), but giving the OCP a head start by approximately half a year.

Proposed sources of funding

DCC’s up to $98,900, Casino revenue $48,700

Costs and benefits

Costs FY1 FY2 FY3 FY4 FY5 5-year Total
Capital 0 0 0 0 0 0
Operational 147,600 0 0 0 0 147,600
Total 147,600 0 0 0 0 147,600
Benefits
Tangible Updated, long term transportation modelling to inform on future projects.
Intangible

Recommendation

This project was requested by Council.