Meeting Overview

The Special Council meeting held on March 12, 2013, primarily focused on the Craigflower Bridge Replacement Project. Council discussed a budget overrun of $128,859 in the tender price and reviewed funding options with the CAO, including the use of reserve funds to be paid back over time. Council subsequently voted to endorse the tender award to Don Mann Construction Ltd., subject to joint project agreements with Saanich and UBCM.

Key Decisions

  • The Council voted to approve the meeting's agenda.
  • The Council endorsed awarding the bridge construction contract to Don Mann Construction, pending formal agreements with the District of Saanich and UBCM.
  • The meeting was officially closed at 3:30 p.m.