Council Meeting/Documents/ATTACHMENT 1 – APPROXIMATE PROJECT COST BREAKDOWN
Appendix

ATTACHMENT 1 – APPROXIMATE PROJECT COST BREAKDOWN

November 4, 2025Page 2312 sections

Financial appendix providing a detailed cost breakdown for the Glenairlie Pumpstation upgrades project.

Subtotal Direct Construction Cost: $578,299.40Contingency (~11%): $58,000.00Total Requested Budget: $636,299.40Budget Increase Required: $118,799.40

Report to Council

Re: Glenairlie Pumpstation Upgrades Tender Award
Meeting Date: October 21, 2025

Page 231

ATTACHMENT 1 – APPROXIMATE PROJECT COST BREAKDOWN

Description Cost
Construction (Bid Price) $520,564.40
CRD Watermain Relocation $29,190.00
Engineering Inspection & Contract Administration $28,545.00
Subtotal (Direct Construction Cost) $578,299.40
Contingency (~11% Construction Cost) $58,000.00
TOTAL REQUESTED BUDGET $636,299.40
Existing Budget $517,500.00
Budget Increase Required $118,799.40

Table 1: Cost Breakdown and Budget Implications

Budget Allocation Budget Amount Increase Amount?
Community Works Fund $25,000 Possible
Sewer Capital Reserve Fund $442,000 Possible
DCC’s $50,500 Possible
Total $517,500

Table 2: Budget Allocations

Additional Budget Allocation Available Amount Additional Amount to be Used to Fund Project
DCC Allocation $15,500 $15,500
Community Works Fund $447K $104,500
Check: Feasible to fund from DCC’s and Community Works Fund? YES
Long term impacts to reserves? NO (Not Used)
Alternative Funding Stream: Growing Communities Fund $3.3M Not recommended

Table 3: Funding Impacts

Page 231