WestUrban Developments Ltd. Letter: Retaining Walls at 9 Erskine Lane
A technical justification letter from WestUrban Developments regarding variance requests for the height and design of retaining walls for Buildings A, C, and D at 9 Erskine Lane.
ERSKINE MULTIFAMILY
Site Sections (Sheet PR11)
Notes: CONTRACTOR TO VERIFY ALL LINES, LEVELS, SURVEYS, DIMENSIONS, LOCATION OF BUILDINGS ON SITE AND LOCATION OF ALL SERVICES PRIOR TO COMMENCING ANY WORK. ALL WORK TO BE DONE IN ACCORDANCE WITH THE B.C. BUILDING CODE CURRENT EDITION AND ALL LOCAL BY-LAWS.
COPYRIGHT RESERVED. THESE PLANS ARE THE PROPERTY OF THUJA ARCHITECTURE (STUDIO), TO BE USED ONLY FOR THE PROJECT SHOWN. REPRODUCING OR REPLICATING THEM IN ANY MANNER IS NOT PERMISSIBLE.
Drawings:

Key Plan showing site layout and section cut lines 
Site Section A - North-South section through the western portion of the site 
Site Section B - East-West section through the central courtyard and building blocks 
Site Section C - East-West section through the parking garage and lower building levels
Revision Schedule:
| Issue / Revision | Date |
|---|---|
| ISSUED FOR REVIEW | JUL 07 2019 |
| ISSUED FOR REVIEW | AUG 13 2019 |
| ISSUED FOR REVIEW | OCT 23 2019 |
| ISSUED FOR REVIEW | NOV 04 2019 |
| ISSUED FOR REZONE | JAN 23 2020 |
| ISSUED FOR REVIEW | MAR 09 2020 |
| REISSUED FOR REZONE | MAY 21 2020 |
| REISSUED FOR REZONE | AUG 05 2020 |
| UPDATED | NOV 23 2020 |
| PARKING REVISED | APR 30 2021 |
| ISSUED FOR DP | MAY 11 2021 |
Site Sections (Sheet PR12)
Drawings:
*
*
*
*
*
Revision Schedule:
| Issue / Revision | Date |
|---|---|
| ISSUED FOR REVIEW | JUL 07 2019 |
| ISSUED FOR REVIEW | AUG 13 2019 |
| ISSUED FOR REVIEW | OCT 23 2019 |
| ISSUED FOR REVIEW | NOV 04 2019 |
| ISSUED FOR REZONE | JAN 23 2020 |
| ISSUED FOR REVIEW | MAR 09 2020 |
| REISSUED FOR REZONE | MAY 21 2020 |
| REISSUED FOR REZONE | AUG 05 2020 |
| UPDATED | NOV 23 2020 |
| PARKING REVISED | APR 30 2021 |
| ISSUED FOR DP | MAY 11 2021 |
Proposed Materials (Sheet PR13)
Material Palette:
*
*
*
*
*
*
*
*
*
*
*
Revision Schedule:
| Issue / Revision | Date |
|---|---|
| ISSUED FOR REVIEW | JUL 07 2019 |
| ISSUED FOR REVIEW | AUG 13 2019 |
| ISSUED FOR REVIEW | OCT 23 2019 |
| ISSUED FOR REVIEW | NOV 04 2019 |
| ISSUED FOR REZONE | JAN 23 2020 |
| ISSUED FOR REVIEW | MAR 09 2020 |
| REISSUED FOR REZONE | MAY 21 2020 |
| REISSUED FOR REZONE | AUG 05 2020 |
| UPDATED | NOV 23 2020 |
| PARKING REVISED | APR 30 2021 |
| ISSUED FOR DP | MAY 11 2021 |
Proposed Renderings (Sheet PR14)
Visualizations:
*
*
*
Revision Schedule:
| Issue / Revision | Date |
|---|---|
| ISSUED FOR REVIEW | JUL 07 2019 |
| ISSUED FOR REVIEW | AUG 13 2019 |
| ISSUED FOR REVIEW | OCT 23 2019 |
| ISSUED FOR REVIEW | NOV 04 2019 |
| ISSUED FOR REZONE | JAN 23 2020 |
| ISSUED FOR REVIEW | MAR 09 2020 |
| REISSUED FOR REZONE | MAY 21 2020 |
| REISSUED FOR REZONE | AUG 05 2020 |
| UPDATED | NOV 23 2020 |
| PARKING REVISED | APR 30 2021 |
| ISSUED FOR DP | MAY 11 2021 |
Proposed Renderings (Sheet PR15)
Visualizations:
*
*
*
Revision Schedule:
| Issue / Revision | Date |
|---|---|
| ISSUED FOR REVIEW | JUL 07 2019 |
| ISSUED FOR REVIEW | AUG 13 2019 |
| ISSUED FOR REVIEW | OCT 23 2019 |
| ISSUED FOR REVIEW | NOV 04 2019 |
| ISSUED FOR REZONE | JAN 23 2020 |
| ISSUED FOR REVIEW | MAR 09 2020 |
| REISSUED FOR REZONE | MAY 21 2020 |
| REISSUED FOR REZONE | AUG 05 2020 |
| UPDATED | NOV 23 2020 |
| PARKING REVISED | APR 30 2021 |
| ISSUED FOR DP | MAY 11 2021 |
Proposed Renderings (Sheet PR16)
Visualization:
*
Revision Schedule:
| Issue / Revision | Date |
|---|---|
| ISSUED FOR REVIEW | JUL 07 2019 |
| ISSUED FOR REVIEW | AUG 13 2019 |
| ISSUED FOR REVIEW | OCT 23 2019 |
| ISSUED FOR REVIEW | NOV 04 2019 |
| ISSUED FOR REZONE | JAN 23 2020 |
| ISSUED FOR REVIEW | MAR 09 2020 |
| REISSUED FOR REZONE | MAY 21 2020 |
| REISSUED FOR REZONE | AUG 05 2020 |
| UPDATED | NOV 23 2020 |
| PARKING REVISED | APR 30 2021 |
| ISSUED FOR DP | MAY 11 2021 |