Project Scope and Timing – Alternative 1 (Appendix C)

May 7, 2024Page 1402 sections

Cost estimates breakdown for the fully accelerated project version using authorization loans.

1 CALL TO ORDER- Mayor Tobias called the meeting to order at 7:00 p.m.
$53.5 M high range estimateIncludes full 6.5 m widening

APPENDIX C

Page 140

Project Scope and Timing – Alternative 1

Accelerate Project with CRD Board Authorization Loans

Project Cost Estimates: Low Range/High Range (Class D + Contingency Estimates 2023)

Project Component Range Estimate
Selkirk Trestle Rehabilitation 300 m (GGRT) Low Range $6.1 M
High Range $8.3 M
Section A: GGRT Selkirk Trestle to Switch Bridge 2 km Low Range $6.8 M
High Range $8.9 M
Section B: GGRT Switch Bridge to McKenzie 2 km Low Range $9.9 M
High Range $13 M
Section C: Lochside Trail Switch Bridge to McKenzie 2 km Low Range $7 M
High Range $9.2 M
Swan Lake Trestle Rehab 145 m (Lochside Trail) Low Range $8.6 M
High Range $10.9 M
Brett Ave Trestle Rehab 25 m (Lochside Trail) Low Range $2.2 M
High Range $2.9 M
Project Totals Low Range $40.8 M
High Range $53.5 M

INCLUDES CRITICAL INFRASTRUCTURE AND FULL 6.5 m WIDENING AND LIGHTING ENHANCEMENT