Appendix
Project Scope and Timing – Alternative 1 (Appendix C)
May 7, 2024Page 1402 sections
Cost estimates breakdown for the fully accelerated project version using authorization loans.
$53.5 M high range estimateIncludes full 6.5 m widening
APPENDIX C
Page 140
Project Scope and Timing – Alternative 1
Accelerate Project with CRD Board Authorization Loans
Project Cost Estimates: Low Range/High Range (Class D + Contingency Estimates 2023)
| Project Component | Range | Estimate |
|---|---|---|
| Selkirk Trestle Rehabilitation 300 m (GGRT) | Low Range | $6.1 M |
| High Range | $8.3 M | |
| Section A: GGRT Selkirk Trestle to Switch Bridge 2 km | Low Range | $6.8 M |
| High Range | $8.9 M | |
| Section B: GGRT Switch Bridge to McKenzie 2 km | Low Range | $9.9 M |
| High Range | $13 M | |
| Section C: Lochside Trail Switch Bridge to McKenzie 2 km | Low Range | $7 M |
| High Range | $9.2 M | |
| Swan Lake Trestle Rehab 145 m (Lochside Trail) | Low Range | $8.6 M |
| High Range | $10.9 M | |
| Brett Ave Trestle Rehab 25 m (Lochside Trail) | Low Range | $2.2 M |
| High Range | $2.9 M | |
| Project Totals | Low Range | $40.8 M |
| High Range | $53.5 M |
INCLUDES CRITICAL INFRASTRUCTURE AND FULL 6.5 m WIDENING AND LIGHTING ENHANCEMENT
Page 140
Extracted from: 2024 05 07 Council Agenda - Agenda - Pdf