Council Meeting/Documents/Project Scope and Timing – Alternative 2 (Appendix E)
Appendix

Project Scope and Timing – Alternative 2 (Appendix E)

May 7, 2024Page 1421 section

Cost estimates for a restricted project scope prioritizing only like-for-like critical infrastructure renewals.

1 CALL TO ORDER- Mayor Tobias called the meeting to order at 7:00 p.m.
$12.6 M project total (High Range)Zero cost for trail widening segments

Project Scope and Timing – Alternative 2

Advance Project by Prioritizing Critical Infrastructure Renewals (without CRD Board Authorization Loans)

Project Cost Estimates: Low Range/High Range (Class D + Contingency Estimates 2023)

Project Description Range Rehabilitation or Replace in-kind (same width, timber) With Widening 6.5 m With Widening & Lighting
Selkirk Trestle Rehabilitation 300 m (GGRT) Low Range $3.4 M $5.5 M $6.3 M
High Range $4.6 M $7.6 M $8.4 M
Swan Lake Trestle Rehab 145 m (Lochside Trail) Low Range $5.2 M $8.4 M $8.7 M
High Range $6.6 M $10.6 M $11 M
Brett Ave Trestle Rehab 25 m (Lochside Trail) Low Range $1.1 M $1.7 M $1.8 M
High Range $1.4 M $2.2 M $2.3 M
Section A: GGRT Selkirk Trestle to Switch Bridge 2 km Low Range $0 M $0 M $0 M
High Range $0 M $0 M $0 M
Section B: GGRT Switch Bridge to McKenzie 2 km Low Range $0 M $0 M $0 M
High Range $0 M $0 M $0 M
Section C: Lochside Trail Switch Bridge to McKenzie 2 km Low Range $0 M $0 M $0 M
High Range $0 M $0 M $0 M
Project Totals Low Range $9.7 M $15.6 M $16.8 M
High Range $12.6 M $20.4 M $21.7 M

LIKE FOR LIKE REPLACEMENT OF CRITICAL INFRASTRUCTURE ONLY

REPLACEMENT WITH ENHANCEMENT OPTIONS FOR CRITICAL INFRASTRUCTURE ONLY