Presentation
Esquimalt Harbor Advisory Committee – Project Update Presentation
July 16, 2019Pages 158–1854 sections
A slide deck providing visual updates on various engineering and remediation projects in Esquimalt Harbour.
November 22, 2018A/B Jetty Recapitalization Project: New B-Jetty complete ~2023Remediation cost for C Jetty/ML Floats: $23.6MHistorical items found: 250lb training round, cannon ball, hand grenade
ESQUIMALT HARBOR ADVISORY COMMITTEE – PROJECT UPDATE
22 November 2018



Page 158–185
Small Boat Float Project

Small Boat Floats
- Pkg 1 Floats: awarded to BWS 7 June 2017; current CV=$13.1M. Delivery complete by mid November 2018
- Pkg 3 Metal + abutments: awarded to PIM 23 Nov 2017; current CV=$3.54M. CCD on Nov 13
- Metal fabricated items delivered
- Abutment work completed
- Pkg 2 (rock removal) and 4 (balance): funding approved 28 August; tender = Dec 2018
- Contract award: Feb or Mar 2018
- Construction start: Spring 2019
- Completion (BOD): Spring 2021
- Project Closeout: Spring 2022

Site overview

October 29 2018

Trestles and Piling
- Trestles (Jetty 2 + 3)
- Large diameter pipe for piles (Jetty 2 + 3)


Pile installation


November 13 2018

Village Rocks Blasting



Page 158–185
A/B Jetty Recapitalization Project

A/B Jetty
- Replacement of WWII era A & B-Jetties with modern structures
- Required to berth new ships being constructed for the Royal Canadian Navy
- Phase 1 – Utility Corridor – Complete
- Phase 2A –Replace B Jetty – Underway
- Old B-Jetty Demolished
- Dredging of contaminated sediments largely complete
- Underwater Rock Removal planned for this winter
- New B-Jetty complete ~2023
- Phase 2B – Replace A-Jetty – Planned for 2023-2026
- Phase 3 – Furnish new cranes

New Jetty Layout


B-Jetty Test Blast Areas
- Total Est. Volume = 8000 m³
- Cost Estimates:
- Rock Removal: $5.5M
- Bubble Curtain: $5M

B Jetty 3-D model: Rock for Removal

JIB Building


Utilities Corridor Extension


Retaining Wall 5

Page 158–185
Esquimalt Harbour Remediation Project

EHRP Scope
| Phase | Description |
|---|---|
| Phase I | A/B Jetty |
| Phase II | 3 Hotspots Remediated |
| Phase III | Risk Management Plan |

Dredging & Processing





UXO Found in Esquimalt Harbour
- 250lb Training Round
- Cannon Ball
- Hand Grenade
- Various Munitions




Historical Items found to-date






EHRP – C Jetty & ML Floats
- CJ/ML Tender Posted: 30 Jan 2018
- CJ/ML Tender Closed: 20 March 2018
- CJ/ML Contract Awarded: 5 April 2018 to Milestone Environmental ($23.6M)
- C Jetty/ML Floats Remediation: May, 2018 to May, 2019
- Timber pier & cradle demolished
- First Round of Dredging at C2/C3 complete
- Dredging around former Marine Railway complete 14 September 2018
- ML Floats #1 and #2 disconnected 29 September 2018 and moved to Colwood 21 October
- Dredging Underway around the ML Floats
EHRP – Y Jetty/Lang Cove
- Y Jetty/Lang Cove Remediation: Aug, 2018 to Mar, 2020
- Y-Jetty 100% Design Complete
- Contract Awarded by December 2018
- Remediation Start January 2019
- Remediation Complete March 2020
- Tender Posted 20 September 2018
- Tender Closed 31 October 2018
- Tender includes an Indigenous Benefits Plan
Questions???
Page 158–185
Document Images
(1)Extracted from: 2019 07 16 Council Agenda - Agenda - Pdf
