C-17-13TransportationActiveFollow Matter

Craigflower Bridge Replacement Project Tender Award

First seen: March 12, 2013
Last seen: March 12, 2013

Lifecycle Timeline

March 12, 2013Council
Full Recording

Craigflower Bridge Replacement Project

Discussion and approval of the contract to replace the Craigflower Bridge despite a cost overrun.

Formal MotionPassed
"THAT the tender award to Don Mann Construction Ltd. upon the successful completion of a signed joint project agreement between View Royal and Saanich, a successful signed agreement with UBCM, as well as confirmation that the District of Saanich agreed to award the tender to Don Mann Construction Ltd. be endorsed."
Moved by: David Screech
Seconded by: Heidi Rast
Graham Hill
Ron Mattson
Heidi Rast
David Screech