C109/C110GeneralActiveFollow Matter

Sewer Capacity Design

First seen: February 17, 2021
Last seen: February 17, 2021

Lifecycle Timeline

February 17, 2021Council
Full Recording

Fort Victoria Sewer Gravity Main Upgrade Design

Council approved $64,000 for design and capacity studies ($32k each) for two sections of the Fort Victoria sewer main, necessary to determine long-term capacity for future development.

"The studies are crucial for long-term planning, particularly concerning high-density areas like Lewis Properties. Council approved the design funding, noting that the larger construction costs (>$1.8 million) are estimates and can be deferred if the study shows sufficient existing capacity."