Sewer Capacity Design
First seen: February 17, 2021
Last seen: February 17, 2021
Lifecycle Timeline
February 17, 2021Council
Full RecordingFort Victoria Sewer Gravity Main Upgrade Design
Council approved $64,000 for design and capacity studies ($32k each) for two sections of the Fort Victoria sewer main, necessary to determine long-term capacity for future development.
"The studies are crucial for long-term planning, particularly concerning high-density areas like Lewis Properties. Council approved the design funding, noting that the larger construction costs (>$1.8 million) are estimates and can be deferred if the study shows sufficient existing capacity."