Committee of the Whole/Documents/View Royal Public Safety Building Construction Schedule (Appendix A)
Appendix

View Royal Public Safety Building Construction Schedule (Appendix A)

October 8, 2013Page 581 section

Gantt chart schedule for the Public Safety Building project by Ledcor Construction Limited.

6.1.3 c) Monthly RCMP Report for the month of September 2013
Completion of construction scheduled for April 7, 2014Structural steel shop drawings deadline November 13, 2013

View Royal Public Safety Building

333 Island Highway, Victoria, BC, V9B 1G9

Construction Schedule

Schedule Details:

  • Schedule Date: August 15, 2013
  • Schedule Revision: G
  • Schedule Update: October 3rd, 2013
ID Task Name Start Date Finish Date
1 View Royal Fire Hall 7/18 4/7
7 Construction Schedule/Duration 8/12 4/7
8 Mobilize 8/12 9/5
16 Structural Steel Shop Drawings 8/23 11/13
30 Demolition 8/19 8/23
35 Demolition Complete 8/23
36 Civil Works 8/23 10/29
44 Civil Works Complete 10/29
45 Entry & Office Area (GL A-G/1-4) 10/10 3/21
121 Entry & Office Area (GL A-G/1-4) Envelope 1/13 2/28
126 Entry & Office Area Complete 2/28
127 Laundry/TO Gear/Shop/Mechanical Area (GL D-E/5-6) 10/3 3/25
201 Laundry/TO Gear/Shop/Mechanical Area (GL D-E/5-6) Envelope 1/23 3/25
206 Laundry/TO Gear/Shop/Mechanical Area Complete 2/28
207 Hose Tower (GL E-G/5-6) 10/3 3/7
257 Hose Tower (GL E-G/5-6) Envelope 2/14 3/17
263 Hose Tower Complete 3/17
264 Apparatus Bays (GL D-E/4-5) 10/17 4/1
302 Apparatus Bays (GL D-E/4-5) Envelope 2/6 3/21
307 Apparatus Bays Complete 3/21
308 Exterior Works 2/12 4/4
319 Exterior Works Complete 4/4
320 Punch list 2/28 3/31
325 Punch list complete 3/31
326 Demobilize Site Offices 3/31 4/4
327 Inspections 2/27 4/7
332 Receive Occupancy Certificate 4/7
333 Turnover to Client (Including O&M Manuals) 4/7