Committee of the Whole/Documents/SITE REPORT No. 13 - 1122 VIEW ROYAL PUBLIC SAFETY BUILDING
Staff Report

SITE REPORT No. 13 - 1122 VIEW ROYAL PUBLIC SAFETY BUILDING

December 10, 2013Pages 23–261 section

Construction site report detailing progress on the new Public Safety Building, including foundations and site works.

1 CALL TO ORDER
Date of visit: 2013.11.211122 View Royal Public Safety BuildingStair footing + strip footings forming in progress

SITE REPORT No. 13

TO: Ledcor Construction Ltd. Mike Forsyth / Jan Coetzee 203 - 830 Shamrock Street Victoria, BC V8X 2V1

FROM: Heather Spinney

CC: Paul Hurst / Kim Anema, View Royal Adam Fawkes, Roger Hughes, HCMA Jonathan Reiter, RJC Tom Wilson, AME Iain Barnes, AES Jeff Ball / Gene Mazza, Associated Engineering Shane Moore, Ryzuk

PROJECT: 1122 VIEW ROYAL PUBLIC SAFETY BUILDING

DATE: 2013.11.25


Date of visit: 2013.11.21 Weather: 2°C, Sunny Present: Heather Spinney, Adam Fawkes, Paul Hurst, Kim Anema, Mike Forsyth, Paul Halverson

Item Work in Progress - Observations Action
SITE PANORAMAS – 2013.11.14
High view from west looking to east side of site.
High view from west looking to east side of site.

High view from west looking to east side of site.
High view from east looking towards west.
High view from east looking towards west.

High view from east looking towards west.
Low view from north looking towards south.
Low view from north looking towards south.

Low view from north looking towards south.
13.1
Stair footing and strip footing forming in progress
Stair footing and strip footing forming in progress


Stair footing + strip footings – forming in progress. GL 1 & C – footings already poured.
INFO
13.2

Excavation for footings in progress. (LEFT: Hose Tower; RIGHT: approx. GL F btwn 3&4)
INFO
13.3

Crane in place.
INFO
13.4

East property line - north of GL H (approx. location shown by red line + arrow) – rock & mortar retaining walls to be installed. During a discussion on site, contractor indicated that rock & mortar retaining walls could be installed in this location and existing trees in Heddle Park would not have to be removed. Some encroachment and reinstatement will be required to achieve cut slopes as indicated by Geotechnical Engineer in SI 007. All efforts are to be made to ensure the health and well being of existing trees. (circled in green) Encroachment on exist. root structures to be minimized, and cut roots are to be protected as soon as possible. PCN to be issued.
LED / HCMA
13.5

Toe of slope in Training Ground not yet fully exposed due to stored material. TBD how much Owner should be required to pay for relocation of stock-piled boulders which are to be used for retaining walls.
INFO
13.6

Upper Parking areas on west side of property – excavation in progress. Some rock is present in these areas. Refer to Geotechnical Field Review / Site Instruction dated 2013.10.29 issued as part of CD 01 for related comments.
LED
13.7

Upper Parking areas:
Void was observed – to be monitored by Geotechnical Engineer.
Abandoned water shut-off valve uncovered during excavation.
LED
13.8

CRD was on site to do boulevard work.
INFO
End of Site Report Number 13
Page 23–26