Appendix
2013 Capital Projects Summary Table
December 10, 2013Page 1061 section
Spreadsheet detailing expenditures, budgets, and projected completion dates for various infrastructure and service projects.
Craigflower Bridge Project budget: $5,512,500New Fire Engine budget: $100,000View Royal Park implementation budget: $140,000
2013 Capital Projects

| 2013 Capital Projects | G/L Account | Cost Centre # | 2013 YTD Nov. 30, 2013 | 2013 Budget | Additional Funds Approved | Variance | Projected Completion Date |
|---|---|---|---|---|---|---|---|
| Transportation | |||||||
| Structures | |||||||
| Craigflower Bridge Replacement Project - Construction (Grant) | 2-2-11109 | 1052 | 4,420,615 | 5,512,500 | 1,091,885 | End of May 2014 | |
| Craigflower Bridge Replacement Project - Construction (Not Grant) | 2-2-11109 | 1052 | 13,845 | 1,949,397 | 1,935,552 | End of May 2014 | |
| Craigflower Bridge Replacement Project - Land Acquisition | 2-2-11109 | 1013 | 2,360 | 60,058 | 57,698 | ||
| Bessborough Avenue at #314 Retaining Wall | 5-2-11106 | 1060 | 8,883 | 15,000 | 6,117 | December 2013 | |
| SUB-TOTAL | 4,445,703 | 7,521,955 | 15,000 | 3,091,252 | |||
| Drainage | |||||||
| Island Hwy (Atkins Road across to Price Road) | 2-2-11201 | 1016 | 4,334 | 6,000 | 1,666 | Complete | |
| SUB-TOTAL | 4,334 | 6,000 | 1,666 | ||||
| Sewer | |||||||
| Stewart Pump Station Upgrade | 5-2-11702 | 1017 | 246,534 | 230,000 | 25,000 | 8,466 | Complete |
| Glenairlie and Thetis Cove Pump Replacements | 5-2-11702 | 1055 | 19,500 | 19,500 | December 2013 | ||
| E&N Trail Installation (as per agreement with CRD Parks) | 5-2-11702 | 1056 | 108,472 | 95,000 | 25,000 | 11,528 | Complete |
| SUB-TOTAL | 355,006 | 344,500 | 50,000 | 39,494 | |||
| Parks | |||||||
| Improvements to Easements | |||||||
| Duffus Trail (Anya Court) Stairs | 2-2-11301 | 1021 | 20,603 | 22,000 | 1,397 | Complete | |
| Seabird Park - Part 1 | 2-2-11302 | 1025 | 6,333 | 5,000 | -1,333 | Complete | |
| Welland Park | 2-2-11302 | 1026 | 5,284 | 20,500 | 16,500 | 31,716 | February 2014 |
| Part Development | |||||||
| View Royal Park - Implementation of VR Park Plan | 2-2-11303 | 1028 | 154,228 | 140,000 | 15,000 | 772 | Complete |
| Park Vehicles | |||||||
| Dump Truck - 3 Ton with hydraulic lift | 2-2-11304 | 1029 | 100,000 | 100,000 | February 2014 | ||
| Vehicle Decals | 2-2-11304 | 1030 | 2,895 | 3,000 | 105 | Complete | |
| SUB-TOTAL | 189,342 | 290,500 | 31,500 | 132,658 | |||
| Fire Services | |||||||
| Buildings | |||||||
| Fire Hall - 2011 parking lot CF & building design / 2012 construction | 2-2-12101 | 1032 | 1,657,085 | 3,000,000 | 1,342,915 | End of Sept. 2014 | |
| Vehicles | |||||||
| Vehicle Replacement - Fire Engine | 2-2-12102 | 1033 | 97,461 | 100,000 | 2,539 | Complete | |
| Equipment | |||||||
| ESS Container | 2-2-12202 | 1057 | 6,281 | 7,000 | 719 | Mid Dec. 2013 | |
| Police Services | |||||||
| RCMP Equipment | 2-2-12301 | 1059 | 1,728 | 1,728 | End of Dec. if req. | ||
| SUB-TOTAL | 1,760,827 | 3,108,728 | 1,347,901 | ||||
| Administration / General Government | |||||||
| Software Upgrades | 2-2-13103 | 1039 | 1,780 | 15,000 | 13,220 | December 2013 | |
| Computer Replacements - 10 computers to be replaced + new switches | 2-2-13103 | 1043 | 12,068 | 13,500 | 1,432 | Complete | |
| Computer Server Replacement | 2-2-13103 | 1044 | 9,148 | 17,000 | 7,852 | Complete | |
| New interdepartmental vehicle (replaces 1991 Sprint) | 2-2-13104 | 1058 | 20,351 | 25,000 | 4,649 | Complete | |
| Land Acquisitions | |||||||
| Misc. Land Acquisition | 2-2-13201 | 1053/1054/10 | 21,983 | 130,000 | 108,017 | End of Dec. 2013 | |
| SUB-TOTAL | 65,331 | 200,500 | 135,169 | ||||
| TOTAL 2013 CAPITAL PROJECTS | 6,820,543 | 11,472,183 | 96,500 | 4,748,140 |
Page 106