Staff Report
View Royal Public Safety Building Monthly Report for February 2014
March 11, 2014Pages 39–415 sections
Monthly status update on the construction of the new Public Safety Building.
Report date: March 5, 2014Construction coordination meetings moved to bi-weeklyGrading and concrete work ongoing
View Royal Public Safety Building
Town of View Royal
Page 39–41
Monthly Report for February 2014

Date of report: 5 March 2014
PREPARED FOR:
Kim Anema, Chief Administrative Officer Town of View Royal
Paul Hurst, Fire Chief, Emergency Program Coordinator View Royal Fire Rescue
PREPARED BY:
Heather Spinney, Architect AIBC Hughes Condon Marler Architects
CONTENTS:
| Subject | Page |
|---|---|
| Introduction | 3 |
| Status of Project | 3 |
| Work Progress | 3 |
| Progress Photographs | 4-6 |
| Supplemental Instructions | 7 |
| Change Orders / Change Directives | 7 |
| Appendix A Schedule |
Page 39–41
INTRODUCTION
This report summarizes the progress and status of the View Royal Public Safety Building up to the end of the month of February 2014.
Page 39–41
STATUS OF PROJECT
2 Construction Coordination Meetings have been conducted. (meetings have been changed to bi-weekly)
- Placement of concrete walls + slabs on grade in progress.
- Installation of civil, mechanical & electrical infrastructure in progress.
- Installation of waterproofing membrane in progress.
- Backfilling in progress.
- Construction of east retaining wall (Type 1) in progress.
- Installation of CMU in progress.
Page 39–41
WORK PROGRESS
Key tasks started, in progress or completed this month include:
- Clean Up / Rock Removal (ongoing)
- Grading
- Concrete (walls + slabs)
- Civil, Mechanical + Electrical Infrastructure
- Waterproofing
- Backfilling
Refer to the following pages for photographs illustrating the current progress of construction.
Page 39–41
Extracted from: 2014 03 11 Committee of the Whole Agenda