Supplemental Instructions and Change Orders List

March 11, 2014Page 454 sections

Log of formal technical changes and cost adjustments for the project.

CO No. 018: Revise Embedded Plate DetailsCO No. 033: CMU Solid Fill + Modify Bond Beam

View Royal Public Safety Building

Town of View Royal

27 February 2014

Page 45

SUPPLEMENTAL INSTRUCTIONS

27 February 2014

The following Supplemental Instructions have been issued up to February 28, 2014:

  • SI No. 022 — RFI 48 — CTRL Joints + Door Locations. Issued 7 February, 2014.
  • SI No. 023 — ESI-2 — Relocate LED Sign Connection + T.O Message Board. Issued 11 February, 2014
  • SI No. 024 — ESI-3 — RFI 051 — Generator Coordination. Issued 12 February, 2014.
  • SI No. 025 — SSI-4 — GL 3B — Oversized Base Plate. Issued 13 February, 2014.
  • SI No. 026 — SSI-5 — RFI 040 — Rappelling Anchors. Issued 14 February, 2014.
  • SI No. 027 — RFI 060 — GL 1-4 + A-H Dimensions. Issued 17 February, 2014.
  • SI No. 028 — Association Room Revisions. Issued 18 February, 2014.
  • SI No. 029 — RFI 059 — CTRL Joints. Issued 21 February, 2014.
  • SI No. 030 — SSI-6 — RFI 054 — Nederman Support. Issued 25 February, 2014.
  • SI No. 031 R — RFI 061 — Retaining Wall Type 1. Issued 26 February, 2014.
  • SI No. 032 — Kitchen Dishwasher Specification. Issued 26 February, 2014.
Page 45

CHANGE ORDERS

The following Change Orders have been issued up to February 28, 2013:

  • CO No. 018: PCN 018 — S-NOPC-4 Revise Embedded Plate Details. Issued 25 February, 2014.
  • CO No. 027: PCN 027 — S-NOPC-9 — RFI 036 — O/H Door Support. Issued 24 February, 2014.
  • CO No. 033: PCN 033 — S-NOPC-13 — CMU Solid Fill + Modify Bond Beam. Issued 25 February, 2014.
Page 45

CHANGE DIRECTIVES

Page 45

Document Images

(1)
Document image
Extracted from: 2014 03 11 Committee of the Whole Agenda