Public Safety Building Construction Schedule

March 11, 2014Pages 48–491 section

Gantt chart depicting the project timeline from tender through completion.

June 23, 2014 targeted completion date

CONSTRUCTION SCHEDULE

New Public Safety Building

333 Island Highway, Victoria, BC, V9B 1G9

Schedule Date: August 15, 2013 Schedule Revision: G Schedule Update: February 11, 2014

ID % Complete Task Name Duration Start Finish
1 38% View Royal Fire Hall 272.94 days Thu 7/18/13 Mon 6/23/14
2 100% Tender 9 days Thu 7/18/13 Mon 7/29/13
3 100% Bid Closing 0 days Mon 7/29/13 Mon 7/29/13
4 100% Adjudication 11 days Mon 7/29/13 Mon 8/12/13
5 100% Contract award 0 days Mon 8/19/13 Mon 8/19/13
6 37% Construction Schedule/Duration 246.88 days Tue 8/20/13 Mon 6/23/14
7 100% Mobilize 20 days Tue 8/20/13 Thu 9/12/13
15 87% Structural Steel Shop Drawings 150.88 days Fri 8/30/13 Tue 3/11/14
29 100% Demolition 15 days Tue 8/20/13 Mon 9/9/13
33 100% Demolition Complete 0 days Mon 9/9/13 Mon 9/9/13
34 80% Civil Works 153 days Tue 9/3/13 Fri 3/14/14
43 0% Civil Works Complete 0 days Fri 3/14/14 Fri 3/14/14
44 25% Entry & Office Area (GL A-G/1-4) 174.88 days Thu 11/14/13 Mon 6/23/14
45 100% Foundations 25.13 days Thu 11/14/13 Fri 12/13/13
49 29% Structure 117.56 days Mon 12/9/13 Wed 5/7/14
50 51% Level 1 117.56 days Mon 12/9/13 Wed 5/7/14
62 0% Level 1 Structure Complete 0 days Fri 3/21/14 Fri 3/21/14
63 0% Level 2 35 days Fri 3/21/14 Mon 5/5/14
70 0% Level 2 Structure Complete 0 days Fri 4/4/14 Fri 4/4/14
71 0% Roof 18 days Fri 4/4/14 Fri 4/25/14
76 0% Finishes 43 days Wed 4/30/14 Mon 6/23/14
117 18% Entry & Office Area (GL A-G/1-4) Envelope 104.75 days Wed 1/15/14 Thu 5/22/14
123 0% Entry & Office Area Complete 0 days Mon 6/23/14 Mon 6/23/14
124 24% Laundry/TO Gear/Shop/Mechanical Area (GL D-E/5-6) 163 days Mon 11/25/13 Tue 6/17/14
Construction schedule table and Gantt chart showing the project timeline from July 2013 through June 2014, including milestones for mobilization, demolition, and foundational work for the Entry & Office Area.
Construction schedule table and Gantt chart showing the project timeline from July 2013 through June 2014, including milestones for mobilization, demolition, and foundational work for the Entry & Office Area.
ID % Complete Task Name Duration Start Finish
125 100% Foundations 18 days Mon 11/25/13 Mon 12/16/13
129 31% Structure 83 days Tue 1/28/14 Wed 5/7/14
130 64% Level 1 83 days Tue 1/28/14 Wed 5/7/14
140 13% Level 2 60 days Tue 2/25/14 Wed 5/7/14
153 0% Roof 15 days Fri 4/4/14 Wed 4/23/14
157 0% Finishes 53 days Tue 4/15/14 Tue 6/17/14
190 0% Laundry/TO Gear/Shop/Mechanical Area (GL D-E/5-6) Envelope 47 days Tue 4/1/14 Tue 5/27/14
194 0% Laundry/TO Gear/Shop/Mechanical Area Complete 0 days Tue 6/17/14 Tue 6/17/14
195 55% Hose Tower (GL E-G/5-6) 134 days Thu 11/21/13 Thu 5/8/14
196 100% Foundations 23 days Thu 11/21/13 Wed 12/18/13
200 82% Core Structure 57 days Thu 1/2/14 Wed 3/12/14
214 0% Core Steel Deck, Handrails, Guardrails & Stairs 35 days Wed 3/12/14 Wed 4/23/14
220 0% Hose Tower Roof 13 days Wed 4/23/14 Thu 5/8/14
228 0% Hose Tower (GL E-G/5-6) Envelope 44 days Wed 3/12/14 Mon 5/5/14
230 0% Hose Tower Complete 0 days Thu 5/8/14 Thu 5/8/14
231 0% Apparatus Bays (GL D-E/4-5) 88.88 days Thu 2/27/14 Fri 6/13/14
232 0% Foundations 5 days Thu 2/27/14 Wed 3/5/14
235 0% Structure 79.88 days Wed 3/5/14 Tue 6/10/14
251 0% Finishes 59 days Fri 4/4/14 Fri 6/13/14
271 0% Apparatus Bays Complete 0 days Fri 6/13/14 Fri 6/13/14
272 0% Exterior Works 40 days Mon 5/5/14 Mon 6/23/14
284 0% Punch list 34.88 days Thu 5/8/14 Fri 6/20/14
291 0% Inspections 35 days Mon 5/12/14 Mon 6/23/14
Construction schedule table and Gantt chart continuing the timeline, detailing structural work for Level 1, Level 2, the Hose Tower, and Apparatus Bays through project completion in June 2014.
Construction schedule table and Gantt chart continuing the timeline, detailing structural work for Level 1, Level 2, the Hose Tower, and Apparatus Bays through project completion in June 2014.

Legend:

  • Task
  • Critical Task
  • Progress
  • Milestone
  • Summary
  • Rolled Up Task
  • Rolled Up Critical Task
  • Rolled Up Milestone
  • Rolled Up Progress
  • Split
  • External Tasks
  • Project Summary
  • Group By Summary
  • Deadline
Page 48–49
Extracted from: 2014 03 11 Committee of the Whole Agenda