Committee of the Whole/Documents/Public Safety Building Budget Summary
Appendix

Public Safety Building Budget Summary

March 11, 2014Pages 50–521 section

Financial reconciliation of project costs, revisions, and variances.

$7,402,160 revised budget$2,824,405 total spent to Feb 28, 2014

PUBLIC SAFETY BUILDING

Public Safety Building budget report table - part 1
Public Safety Building budget report table - part 1
Budget after Tender Revisions Revised Budget As at Feb. 28, 2014 Committed Total Budget Variance
Planning and Design $ 527,025 $ 2,300 $ 529,325 $ 415,290 $ - $ 415,290 $ 114,035
Tendered Price (note 1)
Base Tendered Price 4,948,264 - 4,948,264 1,532,983 - 1,532,983 3,415,281
Cash Allowances 805,347 - 805,347 601,168 - 601,168 204,179
Subtotal Tendered Price 5,753,611 - 5,753,611 2,134,152 - 2,134,152 3,619,459
Reserves and Contingencies 224,060 (139,106) 84,954 - - - 84,954
Extras Approved
Remove Tree 880 & 725 - 1,964 1,964 1,964 - 1,964 -
Remove Tree - 2,097 2,097 2,097 - 2,097 -
Remove AC Pipe - 964 964 964 - 964 -
Swimming Pool Removal - 1,244 1,244 1,244 - 1,244 -
Revise Water Entry - 1,020 1,020 - 1,020 1,020 -
Additional ACM unearthed - 420 420 420 - 420 -
Modify Pavement Structure - (4,032) (4,032) (4,032) - (4,032) -
Tree Removal #3 - 2,393 2,393 2,393 - 2,393 -
Structural Steel Axial Loads - 6,132 6,132 - 6,132 6,132 -
Embed & Anchor Details - 760 760 - 760 760 -
Additional ACM - 400 400 400 - 400 -
Revise Circuits & Panels - (4,487) (4,487) (4,487) - (4,487) -
Water to Hydrant & Gas Trench - 5,660 5,660 - 5,660 5,660 -
Add conduits to comm trench - 3,155 3,155 1,500 1,655 3,155 -
Relocate grease interceptor - 2,311 2,311 - 2,311 2,311 -
Hose tower - new door - 2,530 2,530 2,000 530 2,530 -
Retaining Wall - type 1 - East PL OPT A - 47,949 47,949 45,000 2,949 47,949 -
Revised embedded plate details - 2,391 2,391 - 2,391 2,391 -
O/H door supports - 4,886 4,886 - 4,886 4,886 -
Solid fill CMU cells - 1,191 1,191 1,191 - 1,191 -
Damp proofing - (10,000) (10,000) - (10,000) (10,000) -
Subtotal Extras Approved - 68,947 68,947 50,652 18,295 68,947 -
Public Safety Building budget report table - part 2
Public Safety Building budget report table - part 2
Budget after Tender Revisions Revised Budget As at Feb. 28, 2014 Committed Total Budget Variance
Extras Proposed
Owner Changes Contemplated - 41,872 41,872 - - - 41,872
Completion Costs
Furniture & Equipment 150,000 - 150,000 - - - 150,000
DCC 41,760 - 41,760 41,760 - 41,760 0
Building Permit/Testing Structural and Geotech. 25,750 10,000 35,750 28,835 - 28,835 6,915
Connection Fees (BC Hydro Fee) 48,115 15,986 64,101 52,101 - 52,101 12,000
Administration Costs 10,000 - 10,000 - - - 10,000
Legal Costs 8,000 - 8,000 5,862 - 5,862 2,138
Insurance Costs 11,340 - 11,340 11,340 - 11,340 -
Public Art 35,000 - 35,000 - - - 35,000
Operation/Startup Costs 35,000 - 35,000 - - - 35,000
Subtotal Completion Costs 364,965 25,986 390,951 139,898 - 139,898 251,053
Adjusted Construction Cost Total $ 7,256,260 $ - $ 7,256,260 $ 2,739,992 $ 18,295 $ 2,758,287 $ 4,497,973
Off Site Services
Off Site Design 30,000 - 30,000 26,168 - 26,168 3,832
Storm Drain 60,000 - 60,000 39,301 - 39,301 20,699
Traffic Control (fire warning flashers) 30,000 - 30,000 650 - 650 29,350
Traffic Islands / Painting 5,000 - 5,000 - - - 5,000
Electrical Conduit Crossing 9,400 - 9,400 - - - 9,400
Fibre Conduit Crossing 11,500 - 11,500 - - - 11,500
Subtotal Off Site Services $ 145,900 $ - $ 145,900 $ 66,118 $ - $ 66,118 $ 79,782
Total Construction and Off Site Services $ 7,402,160 $ - $ 7,402,160 $ 2,806,110 $ 18,295 $ 2,824,405 $ 4,577,755
Note 1 table for tendered price calculation
Note 1 table for tendered price calculation

Note 1

Budget after Tender
Tendered price 5,753,611
Tax charged (rebatable) 287,681
Total including tax 6,041,292
Page 50–52
Extracted from: 2014 03 11 Committee of the Whole Agenda