Staff Report
View Royal Public Safety Building Monthly Report for April 2014
May 13, 2014Pages 48–505 sections
Architectural status report on the construction of the View Royal Public Safety Building.
May 8, 2014Tasks: Blasting, rock removal, concrete walls + slabs, structural steelFraming of building and concrete placement in progress
View Royal Public Safety Building
Town of View Royal
Page 48–50
Monthly Report for April 2014

Date of report: 8 May 2014
PREPARED FOR:
- Kim Anema, Chief Administrative Officer, Town of View Royal
- Paul Hurst, Fire Chief, Emergency Program Coordinator, View Royal Fire Rescue
PREPARED BY:
- Heather Spinney, Architect AIBC, Hughes Condon Marler Architects
CONTENTS:
| Section | Page |
|---|---|
| Introduction | 3 |
| Status of Project | 3 |
| Work Progress | 3 |
| Progress Photographs | 4-6 |
| Supplemental Instructions | 7 |
| Change Orders / Change Directives | 7 |
| Appendix A: Schedule |
Page 48–50
INTRODUCTION
This report summarizes the progress and status of the View Royal Public Safety Building up to the end of the month of April 2014.
Page 48–50
STATUS OF PROJECT
2 Construction Coordination Meetings have been conducted.
- Framing of building + placing of concrete in progress
- Installation of civil, mechanical & electrical infrastructure in progress.
- Preparation for installation of roofing membrane in progress
Page 48–50
WORK PROGRESS
Key tasks started, in progress or completed this month include:
- Additional blasting (upper parking + training ground)
- Clean Up / Rock Removal (ongoing)
- Grading
- Concrete (walls + slabs) + CMU
- Civil, Mechanical + Electrical Infrastructure
- Structural Steel
- TJI Framing + stud framing
- Installation of roofing membrane started
Refer to the following pages for photographs illustrating the current progress of construction.
Page 48–50
Extracted from: 2014 05 13 Committee of the Whole Agenda