Committee of the Whole/Documents/Construction Schedule - View Royal Public Safety Building
Appendix

Construction Schedule - View Royal Public Safety Building

May 13, 2014Pages 57–581 section

Detailed Gantt chart showing the project timeline from July 2013 through June 2014.

Scheduled completion of foundations: 12/13/13Projected finish: June 2014

CONSTRUCTION SCHEDULE

New Public Safety Building

333 Island Highway, Victoria, BC, V9B 1G9

Schedule Date: August 15, 2013 Schedule Revision: G Schedule Update: February 11, 2014

Detailed construction Gantt chart for the New Public Safety Building project showing task timelines from July 2013 through June 2014.
Detailed construction Gantt chart for the New Public Safety Building project showing task timelines from July 2013 through June 2014.
ID % Complete Task Name Duration Start
1 47% View Royal Fire Hall 272.94 days Thu 7/18/13
2 100% Tender 9 days Thu 7/18/13
3 100% Bid Closing 0 days Mon 7/29/13
4 100% Adjudication 11 days Mon 7/29/13
5 100% Contract award 0 days Mon 8/19/13
6 47% Construction Schedule/Duration 246.88 days Tue 8/20/13
7 100% Mobilize 20 days Tue 8/20/13
15 99% Structural Steel Shop Drawings 150.88 days Fri 8/30/13
18 100% Demolition 15 days Tue 8/20/13
33 100% Demolition Complete 0 days Mon 9/9/13
34 88% Civil Works 153 days Tue 9/3/13
43 0% Civil Works Complete 0 days Fri 3/14/14
44 40% Entry & Office Area (GL A-G/1-4) 174.88 days Thu 11/14/13
45 100% Foundations 25.13 days Thu 11/14/13
49 66% Structure 117.56 days Mon 12/9/13
50 83% Level 1 117.56 days Mon 12/9/13
62 41% Level 2 35 days Fri 3/21/14
69 50% Roof 18 days Fri 4/4/14
74 0% Finishes 43 days Wed 4/30/14
75 0% Level 1 Finishes 41 days Fri 5/2/14
96 0% Level 2 Finishes 42 days Wed 4/30/14
115 24% Entry & Office Area (GL A-G/1-4) Envelope 104.75 days Wed 1/15/14
121 0% Entry & Office Area Complete 0 days Mon 6/23/14
122 38% Laundry/TO Gear/Shop/Mechanical Area (GL D-E/5-6) 163 days Mon 11/25/13
123 100% Foundations 18 days Mon 11/25/13
127 65% Structure 83 days Tue 1/28/14
128 90% Level 1 83 days Tue 1/28/14
137 63% Level 2 60 days Tue 2/25/14
150 0% Roof 15 days Fri 4/4/14
154 0% Finishes 53 days Tue 4/15/14
155 0% Level 1 48 days Mon 4/21/14
170 0% Level 2 45 days Tue 4/15/14
187 0% Laundry/TO Gear/Shop/Mechanical Area (GL D-E/5-6) Envelope 47 days Tue 4/2/14
191 0% Laundry/TO Gear/Shop/Mechanical Area Complete 0 days Tue 6/17/14
192 64% Hose Tower (GL E-G/5-6) 134 days Thu 11/21/13
193 100% Foundations 23 days Thu 11/21/13
197 100% Core Structure 57 days Thu 1/2/14
211 0% Core Steel Deck, Handrails, Guardrails & Stairs 35 days Wed 3/12/14
217 0% Hose Tower Roof 13 days Wed 4/23/14
223 0% Hose Tower (GL E-G/5-6) Envelope 44 days Wed 3/12/14
227 0% Hose Tower Complete 0 days Thu 5/8/14
228 11% Apparatus Bays (GL D-E/4-5) 88.88 days Thu 2/27/14
268 0% Apparatus Bays Complete 0 days Fri 6/13/14
269 5% Exterior Works 40 days Mon 5/5/14
281 0% Punch list 34.88 days Thu 5/8/14
288 0% Inspections 35 days Mon 5/12/14
A blank page in the document.
A blank page in the document.

THIS PAGE LEFT BLANK INTENTIONALLY

Page 57–58
Extracted from: 2014 05 13 Committee of the Whole Agenda