Construction Schedule - View Royal Public Safety Building
May 13, 2014Pages 57–581 section
Detailed Gantt chart showing the project timeline from July 2013 through June 2014.
Scheduled completion of foundations: 12/13/13Projected finish: June 2014
CONSTRUCTION SCHEDULE
New Public Safety Building
333 Island Highway, Victoria, BC, V9B 1G9
Schedule Date: August 15, 2013 Schedule Revision: G Schedule Update: February 11, 2014

| ID | % Complete | Task Name | Duration | Start |
|---|---|---|---|---|
| 1 | 47% | View Royal Fire Hall | 272.94 days | Thu 7/18/13 |
| 2 | 100% | Tender | 9 days | Thu 7/18/13 |
| 3 | 100% | Bid Closing | 0 days | Mon 7/29/13 |
| 4 | 100% | Adjudication | 11 days | Mon 7/29/13 |
| 5 | 100% | Contract award | 0 days | Mon 8/19/13 |
| 6 | 47% | Construction Schedule/Duration | 246.88 days | Tue 8/20/13 |
| 7 | 100% | Mobilize | 20 days | Tue 8/20/13 |
| 15 | 99% | Structural Steel Shop Drawings | 150.88 days | Fri 8/30/13 |
| 18 | 100% | Demolition | 15 days | Tue 8/20/13 |
| 33 | 100% | Demolition Complete | 0 days | Mon 9/9/13 |
| 34 | 88% | Civil Works | 153 days | Tue 9/3/13 |
| 43 | 0% | Civil Works Complete | 0 days | Fri 3/14/14 |
| 44 | 40% | Entry & Office Area (GL A-G/1-4) | 174.88 days | Thu 11/14/13 |
| 45 | 100% | Foundations | 25.13 days | Thu 11/14/13 |
| 49 | 66% | Structure | 117.56 days | Mon 12/9/13 |
| 50 | 83% | Level 1 | 117.56 days | Mon 12/9/13 |
| 62 | 41% | Level 2 | 35 days | Fri 3/21/14 |
| 69 | 50% | Roof | 18 days | Fri 4/4/14 |
| 74 | 0% | Finishes | 43 days | Wed 4/30/14 |
| 75 | 0% | Level 1 Finishes | 41 days | Fri 5/2/14 |
| 96 | 0% | Level 2 Finishes | 42 days | Wed 4/30/14 |
| 115 | 24% | Entry & Office Area (GL A-G/1-4) Envelope | 104.75 days | Wed 1/15/14 |
| 121 | 0% | Entry & Office Area Complete | 0 days | Mon 6/23/14 |
| 122 | 38% | Laundry/TO Gear/Shop/Mechanical Area (GL D-E/5-6) | 163 days | Mon 11/25/13 |
| 123 | 100% | Foundations | 18 days | Mon 11/25/13 |
| 127 | 65% | Structure | 83 days | Tue 1/28/14 |
| 128 | 90% | Level 1 | 83 days | Tue 1/28/14 |
| 137 | 63% | Level 2 | 60 days | Tue 2/25/14 |
| 150 | 0% | Roof | 15 days | Fri 4/4/14 |
| 154 | 0% | Finishes | 53 days | Tue 4/15/14 |
| 155 | 0% | Level 1 | 48 days | Mon 4/21/14 |
| 170 | 0% | Level 2 | 45 days | Tue 4/15/14 |
| 187 | 0% | Laundry/TO Gear/Shop/Mechanical Area (GL D-E/5-6) Envelope | 47 days | Tue 4/2/14 |
| 191 | 0% | Laundry/TO Gear/Shop/Mechanical Area Complete | 0 days | Tue 6/17/14 |
| 192 | 64% | Hose Tower (GL E-G/5-6) | 134 days | Thu 11/21/13 |
| 193 | 100% | Foundations | 23 days | Thu 11/21/13 |
| 197 | 100% | Core Structure | 57 days | Thu 1/2/14 |
| 211 | 0% | Core Steel Deck, Handrails, Guardrails & Stairs | 35 days | Wed 3/12/14 |
| 217 | 0% | Hose Tower Roof | 13 days | Wed 4/23/14 |
| 223 | 0% | Hose Tower (GL E-G/5-6) Envelope | 44 days | Wed 3/12/14 |
| 227 | 0% | Hose Tower Complete | 0 days | Thu 5/8/14 |
| 228 | 11% | Apparatus Bays (GL D-E/4-5) | 88.88 days | Thu 2/27/14 |
| 268 | 0% | Apparatus Bays Complete | 0 days | Fri 6/13/14 |
| 269 | 5% | Exterior Works | 40 days | Mon 5/5/14 |
| 281 | 0% | Punch list | 34.88 days | Thu 5/8/14 |
| 288 | 0% | Inspections | 35 days | Mon 5/12/14 |