Committee of the Whole/Documents/HIGH LEVEL SCHEDULE - New Public Safety Building
Appendix

HIGH LEVEL SCHEDULE - New Public Safety Building

February 11, 2014Pages 66–671 section

Gantt chart schedule for the Public Safety Building construction project.

Scheduled completion estimated for mid-2014

HIGH LEVEL SCHEDULE

New Public Safety Building

333 Island Highway, Victoria, BC, V9B 1G9

Construction Schedule

Schedule Date: August 15, 2013 Schedule Revision: H Schedule Update: January 8th, 2013

Gantt chart showing the high-level construction schedule from July 2013 to July 2014, including tender, mobilization, demolition, and structural work for the View Royal Fire Hall.
Gantt chart showing the high-level construction schedule from July 2013 to July 2014, including tender, mobilization, demolition, and structural work for the View Royal Fire Hall.
ID Task Name Start Finish
1 View Royal Fire Hall Thu 7/18/13 Mon 6/23/14
2 Tender Thu 7/18/13 Mon 7/29/13
3 Bid Closing Mon 7/29/13 Mon 7/29/13
4 Adjudication Mon 7/29/13 Mon 8/12/13
5 Contract award Mon 8/19/13 Mon 8/19/13
6 Construction Schedule/Duration Thu 7/18/13 Mon 6/23/14
7 Mobilize Tue 8/20/13 Thu 9/12/13
15 Structural Steel Shop Drawings Fri 8/30/13 Wed 1/29/14
29 Demolition Tue 8/20/13 Mon 9/9/13
33 Demolition Complete Mon 9/9/13 Mon 9/9/13
34 Civil Works Tue 9/3/13 Fri 1/3/14
43 Civil Works Complete Fri 1/3/14 Fri 1/3/14
44 Entry & Office Area (GL A-G/1-4) Thu 11/14/13 Mon 6/16/14
45 Foundations Thu 11/14/13 Wed 12/11/13
49 Structure Thu 12/5/13 Fri 4/25/14
76 Finishes Tue 4/22/14 Mon 6/16/14
117 Entry & Office Area (GL A-G/1-4) Envelope Mon 1/13/14 Fri 5/9/14
123 Entry & Office Area Complete Mon 6/16/14 Mon 6/16/14
124 Laundry/TO Gear/Shop/Mechanical Area (GL D-E/5-6) Mon 11/25/13 Fri 5/30/14
125 Foundations Mon 11/25/13 Mon 12/16/13
129 Structure Mon 12/16/13 Mon 4/21/14
130 Level 1 Mon 12/16/13 Mon 4/21/14
Continuation of the Gantt chart showing interior finishes, envelope work, hose tower construction, and final site works.
Continuation of the Gantt chart showing interior finishes, envelope work, hose tower construction, and final site works.
ID Task Name Start Finish
139 Level 2 Tue 1/21/14 Mon 4/21/14
152 Roof Mon 3/10/14 Fri 4/4/14
156 Finishes Wed 2/26/14 Fri 5/30/14
157 Level 1 Wed 2/26/14 Fri 5/30/14
172 Level 2 Wed 3/26/14 Wed 5/21/14
189 Laundry/TO Gear/Shop/Mechanical Area (GL D-E/5-6) Envelope Fri 2/21/14 Mon 4/21/14
193 Laundry/TO Gear/Shop/Mechanical Area Complete Fri 5/30/14 Fri 5/30/14
194 Hose Tower (GL E-G/5-6) Thu 11/21/13 Tue 4/15/14
195 Foundations Thu 11/21/13 Wed 12/18/13
199 Core Structure Wed 12/18/13 Fri 2/14/14
213 Core Steel Deck, Handrails, Guardrails & Stairs Fri 2/14/14 Mon 3/31/14
219 Hose Tower Roof Mon 3/31/14 Tue 4/15/14
225 Hose Tower (GL E-G/5-6) Envelope Fri 2/14/14 Wed 4/9/14
229 Hose Tower Complete Tue 4/15/14 Tue 4/15/14
230 Apparatus Bays (GL D-E/4-5) Fri 12/20/13 Mon 6/9/14
231: Foundations Fri 12/20/13 Mon 1/6/14
234 Structure Mon 1/6/14 Wed 6/4/14
250 Finishes Tue 3/11/14 Mon 6/9/14
270 Apparatus Bays Complete Mon 6/9/14 Mon 6/9/14
271 Exterior Works Thu 7/18/13 Fri 6/13/14
283 Punch list Tue 4/15/14 Mon 6/16/14
290 Inspections Fri 5/16/14 Mon 6/23/14
Page 66–67