Update on the selection of playground equipment for Portage Park determined by the Parks and Recreation Advisory Committee.

2. APPROVAL OF AGENDA
Budget: $100,000Installation date: Fall 2014

TOWN OF VIEW ROYAL COMMITTEE OF THE WHOLE

TO: Committee of the Whole DATE: September 4, 2014 FROM: John Rosenberg MEETING DATE: September 9, 2014 FILE NO.: 5840-61

Page 76–77

Portage Park Playground Equipment

RECOMMENDATION:

THAT the Committee receives the report.

CHIEF ADMINISTRATIVE OFFICER’S COMMENTS:

I concur with the recommendation.

PURPOSE OF REPORT:

To inform the Committee on the layout and configuration of the proposed playground equipment to be installed in Portage Park.

BACKGROUND:

During the 2104 Financial plan $100,000 was allocated to install a playground in Portage Park. The Parks and Recreation Advisory Committee (PREAC) was tasked with determining the configuration and layout of the proposed playground. At the July 23 PREAC meeting the committee requested that one committee member and one Town staff member work together to choose a playground. Several options and quotes were submitted attached is the final choice that will be installed in the fall of 2014.

ALTERNATIVES TO STAFF RECOMMENDATION:

That the Committee directs staff to cancel the order.

RECOMMENDATION:

THAT the Committee receives the report.

SUBMITTED BY: John Rosenberg, Director of Engineering

REVIEWED BY: Kim Anema, Chief Administrative Officer

Page 76–77