Committee of the Whole/Documents/Appendix: LEDCOR HIGH LEVEL SCHEDULE - New Public Safety Building
Appendix

Appendix: LEDCOR HIGH LEVEL SCHEDULE - New Public Safety Building

January 14, 2014Pages 29–301 section

Detailed construction schedule from Ledcor Construction Limited for the View Royal Fire Hall / Public Safety Building project.

Schedule update: January 8, 2013 (likely 2014 typo based on surrounding docs)Projected completion for View Royal Fire Hall: June 23, 2014Target for punch list completion: June 16, 2014

HIGH LEVEL SCHEDULE

New Public Safety Building

333 Island Highway, Victoria, BC, V9B 1G9

Construction Schedule

Gantt chart displaying the first page of the high-level construction schedule for the View Royal Fire Hall, including procurement, mobilization, demolition, civil works, and primary structural phases from July 2013 through July 2014.
Gantt chart displaying the first page of the high-level construction schedule for the View Royal Fire Hall, including procurement, mobilization, demolition, civil works, and primary structural phases from July 2013 through July 2014.
ID Task Name Start Finish
1 View Royal Fire Hall Thu 7/18/13 Mon 6/23/14
2 Tender Thu 7/18/13 Mon 7/29/13
3 Bid Closing Mon 7/29/13 Mon 7/29/13
4 Adjudication Mon 7/29/13 Mon 8/12/13
5 Contract award Mon 8/19/13 Mon 8/19/13
6 Construction Schedule/Duration Thu 7/18/13 Mon 6/23/14
7 Mobilize Tue 8/20/13 Thu 9/12/13
15 Structural Steel Shop Drawings Fri 8/30/13 Wed 1/29/14
29 Demolition Tue 8/20/13 Mon 9/9/13
33 Demolition Complete Mon 9/9/13 Mon 9/9/13
34 Civil Works Tue 9/3/13 Fri 1/3/14
43 Civil Works Complete Fri 1/3/14 Fri 1/3/14
44 Entry & Office Area (GL A-G/1-4) Thu 11/14/13 Mon 6/16/14
45 Foundations Thu 11/14/13 Wed 12/11/13
49 Structure Thu 12/5/13 Fri 4/25/14
76 Finishes Tue 4/22/14 Mon 6/16/14
117 Entry & Office Area (GL A-G/1-4) Envelope Mon 1/13/14 Fri 5/9/14
123 Entry & Office Area Complete Mon 6/16/14 Mon 6/16/14
124 Laundry/TO Gear/Shop/Mechanical Area (GL D-E/5-6) Mon 11/25/13 Fri 5/30/14
125 Foundations Mon 11/25/13 Mon 12/16/13
129 Structure Mon 12/16/13 Mon 4/21/14
130 Level 1 Mon 12/16/13 Mon 4/21/14
139 Level 2 Tue 1/21/14 Mon 4/21/14
Gantt chart displaying the second page of the construction schedule, detailing task schedules for the roof, finishes, hose tower, apparatus bays, exterior works, and final inspections.
Gantt chart displaying the second page of the construction schedule, detailing task schedules for the roof, finishes, hose tower, apparatus bays, exterior works, and final inspections.
ID Task Name Start Finish
152 Roof Mon 3/10/14 Fri 4/4/14
156 Finishes Wed 2/26/14 Fri 5/30/14
157 Level 1 Wed 2/26/14 Fri 5/30/14
172 Level 2 Wed 3/26/14 Wed 5/21/14
189 Laundry/TO Gear/Shop/Mechanical Area (GL D-E/5-6) Envelope Fri 2/21/14 Mon 4/21/14
193 Laundry/TO Gear/Shop/Mechanical Area Complete Fri 5/30/14 Fri 5/30/14
194 Hose Tower (GL E-G/5-6) Thu 11/21/13 Tue 4/15/14
195 Foundations Thu 11/21/13 Wed 12/18/13
199 Core Structure Wed 12/18/13 Fri 2/14/14
213 Core Steel Deck, Handrails, Guardrails & Stairs Fri 2/14/14 Mon 3/31/14
219 Hose Tower Roof Mon 3/31/14 Tue 4/15/14
225 Hose Tower (GL E-G/5-6) Envelope Fri 2/14/14 Wed 4/9/14
229 Hose Tower Complete Tue 4/15/14 Tue 4/15/14
230 Apparatus Bays (GL D-E/4-5) Fri 12/20/13 Mon 6/9/14
231 Foundations Fri 12/20/13 Mon 1/6/14
234 Structure Mon 1/6/14 Wed 6/4/14
235 Level 1 & 2 Mon 1/6/14 Wed 6/4/14
243 Roof Tue 2/18/14 Mon 4/7/14
250 Finishes Tue 3/11/14 Mon 6/9/14
270 Apparatus Bays Complete Mon 6/9/14 Mon 6/9/14
271 Exterior Works Thu 7/18/13 Fri 6/13/14
283 Punch list Tue 4/15/14 Mon 6/16/14
290 Inspections Fri 5/16/14 Mon 6/23/14
Page 29–30
Extracted from: 2014 01 14 Committee of the Whole Agenda