Appendix
Appendix: PUBLIC SAFETY BUILDING Budget
January 14, 2014Pages 31–321 section
Comprehensive budget breakdown for the Public Safety Building project, including tendered prices, revisions, and variances.
Base Tendered Price: $4,948,264Adjusted Construction Cost Total: $7,256,260Total Construction and Off Site Services Revised Budget: $7,402,160Total including tax estimate: $6,041,292
PUBLIC SAFETY BUILDING

| Item | Budget after Tender | Revisions | Revised Budget | As at Dec. 31, 2013 | Committed | Total | Budget Variance |
|---|---|---|---|---|---|---|---|
| Planning and Design | $ 527,025 | $ 2,300 | $ 529,325 | $ 396,230 | $ - | $ 396,230 | $ 133,095 |
| Tendered Price (note 1) | |||||||
| Base Tendered Price | 4,948,264 | - | 4,948,264 | 815,573 | 181,061 | 996,633 | 3,951,631 |
| Cash Allowances | 805,347 | - | 805,347 | 596,991 | 4,177 | 601,168 | 204,179 |
| 5,753,611 | - | 5,753,611 | 1,412,564 | 185,237 | 1,597,801 | 4,155,810 | |
| Reserves and Contingencies | 224,060 | (45,281) | 178,779 | - | - | - | 178,779 |
| Extras Approved | |||||||
| Remove Tree 880 & 725 | - | 1,964 | 1,964 | 1,964 | - | 1,964 | - |
| Remove Tree | - | 2,097 | 2,097 | 2,097 | - | 2,097 | - |
| Remove AC Pipe | - | 964 | 964 | 964 | - | 964 | - |
| Swimming Pool Removal | - | 1,244 | 1,244 | 1,244 | - | 1,244 | - |
| Revise Water Entry | - | 1,020 | 1,020 | - | 1,020 | 1,020 | - |
| Additional ACM unearthed | - | 420 | 420 | 420 | - | 420 | - |
| Modify Pavement Structure | - | (4,032) | (4,032) | (4,032) | - | (4,032) | - |
| Tree Removal #3 | - | 2,393 | 2,393 | 2,393 | - | 2,393 | - |
| Structural Steel Axial Loads | - | 6,132 | 6,132 | - | 6,132 | 6,132 | - |
| Embed & Anchor Details | - | 760 | 760 | - | 760 | 760 | - |
| Additional ACM | - | 400 | 400 | - | 400 | 400 | - |
| - | 13,361 | 13,361 | 5,049 | 8,313 | 13,361 | - | |
| Extras Proposed | - | 13,634 | 13,634 | - | - | - | 13,634 |
| Owner Changes Contemplated | 386,599 | - | 386,599 | - | - | - | 386,599 |
| Completion Costs | |||||||
| Furniture & Equipment | 150,000 | - | 150,000 | - | - | - | 150,000 |
| DCC | 41,760 | - | 41,760 | 41,760 | - | 41,760 | 0 |
| Building Permit/Testing Structural and Geotech. | 25,750 | - | 25,750 | 19,317 | - | 19,317 | 6,433 |
| Connection Fees (BC Hydro Fee) | 48,115 | 15,986 | 64,101 | 52,101 | - | 52,101 | 12,000 |
| Administration Costs | 10,000 | - | 10,000 | - | - | - | 10,000 |
| Legal Costs | 8,000 | - | 8,000 | 5,255 | - | 5,255 | 2,745 |
| Insurance Costs | 11,340 | - | 11,340 | 11,340 | - | 11,340 | - |
| Public Art | 35,000 | - | 35,000 | - | - | - | 35,000 |

| Item | Budget after Tender | Revisions | Revised Budget | As at Dec. 31, 2013 | Committed | Total | Budget Variance |
|---|---|---|---|---|---|---|---|
| Operation/Startup Costs | 35,000 | - | 35,000 | - | - | - | 35,000 |
| Adjusted Construction Cost Total | $ 7,256,260 | $ - | $ 7,256,260 | $ 1,943,615 | $ 193,550 | $ 2,137,165 | $ 5,119,095 |
| Off Site Services | |||||||
| Off Site Design | 30,000 | - | 30,000 | 22,451 | - | 22,451 | 7,549 |
| Storm Drain | 60,000 | - | 60,000 | - | - | - | 60,000 |
| Traffic Control | 30,000 | - | 30,000 | - | - | - | 30,000 |
| Traffic Islands / Painting | 5,000 | - | 5,000 | - | - | - | 5,000 |
| Street Light Conduit | 9,400 | - | 9,400 | - | - | - | 9,400 |
| Fibre Conduit Crossing | 11,500 | - | 11,500 | - | - | - | 11,500 |
| $ 145,900 | $ - | $ 145,900 | $ 22,451 | $ - | $ 22,451 | $ 123,449 | |
| Total Construction and Off Site Services | $ 7,402,160 | $ - | $ 7,402,160 | $ 1,966,067 | $ 193,550 | $ 2,159,617 | $ 5,242,543 |
Note 1
| Item | Amount |
|---|---|
| Tendered price | 5,753,611 |
| Tax charged (rebatable) | 287,681 |
| Total including tax | 6,041,292 |
Page 31–32
Extracted from: 2014 01 14 Committee of the Whole Agenda