Committee of the Whole Report - CAPITAL PROJECT UPDATE

January 14, 2014Pages 33–342 sections

Financial update providing Council with current expenditure status and projected completion dates for 2013 capital projects.

2. APPROVAL OF AGENDA
Date: January 9, 2014Total 2013 Capital Projects Budget: $11,472,183Actual expenditures to Dec 31, 2013: $8,697,692Craigflower Bridge Replacement projected completion: End of May 2014

TOWN OF VIEW ROYAL COMMITTEE OF THE WHOLE REPORT

TO: Committee of the Whole DATE: January 9, 2014 FROM: Jeannie Beauchamp, Director of Finance MEETING DATE: January 14, 2014

CAPITAL PROJECT UPDATE

RECOMMENDATION: THAT the Committee receive the January 9, 2014 Capital Project Update Report for information.

CHIEF ADMINISTRATIVE OFFICER’S COMMENTS:

I concur with the recommendation.

PURPOSE OF REPORT: To provide Council with information regarding capital project expenditures and projected completion dates.

INFORMATION:

For 2013, the Town has approved capital expenditures of $11,472,183. The attached report outlines expenditures to December 31, 2013 and current projected completion dates.

The actual expenditures presented are those received by the Town at the time of the report and are not final expenditures for the year.

RECOMMENDATION: THAT the Committee receive the January 9, 2014 Capital Project Update Report for information.

SUBMITTED BY: J. Beauchamp, Director of Finance

REVIEWED BY: S. Jones, Deputy Chief Administrative Officer for K. Anema, Chief Administrative Officer

Page 33–34

2013 Capital Projects

PRELIMINARY

Project G/L Account Cost Centre # 2013 YTD Dec. 31, 2013 2013 Budget Additional Funds Approved Variance Projected Completion Date
Transportation
Structures
Craigflower Bridge Replacement Project - Construction (Grant) 2-2-11109 1052 5,150,538 5,512,500 361,962 End of May 2014
Craigflower Bridge Replacement Project - Construction (Not Grant) 2-2-11109 1052 648,879 1,949,397 1,300,519 End of May 2014
Craigflower Bridge Replacement Project - Land Acquisition 2-2-11109 1013 3,959 60,058 56,099 End of May 2014
Bessborough Avenue at #314 Retaining Wall 2-2-11106 1060 14,232 15,000 15,000 768 Complete
SUB-TOTAL 5,817,608 7,521,955 15,000 1,719,347
Drainage
Island Hwy (Atkins Road across to Price Road) 2-2-11201 1016 4,334 6,000 1,666 Complete
SUB-TOTAL 4,334 6,000 1,666
Sewer
Stewart Pump Station Upgrade 5-2-11702 1017 249,145 230,000 25,000 5,855 Complete
Glenairlie and Thetis Cove Pump Replacements 5-2-11702 1055/1051 72 19,500 19,428 Complete
E&N Trail Installation (as per agreement with CRD Parks) 5-2-11702 1056 109,115 95,000 25,000 10,885 Complete
SUB-TOTAL 358,332 344,500 50,000 36,168
Parks
Improvements to Easements
Duffus Trail (Anya Court) Stairs 2-2-11301 1021 20,603 22,000 1,397 Complete
Seabird Park - Part 1 2-2-11302 1025 5,108 5,000 -108 Complete
Welland Park 2-2-11302 1026 11,509 20,500 16,500 25,491 February 2014
Park Development
View Royal Park - Implementation of VR Park Plan 2-2-11303 1028 154,228 140,000 15,000 772 Complete
Park Vehicles
Dump Truck - 3 Ton with hydraulic lift 2-2-11304 1029 100,000 100,000 February 2014
Vehicle Decals 2-2-11304 1030 2,895 3,000 105 Complete
SUB-TOTAL 194,342 290,500 31,500 127,658
Fire Services
Buildings
Fire Hall - 2011 parking lot CF & building design / 2012 construction 2-2-12101 1032 2,152,725 3,000,000 847,275 End of Sept. 2014
Vehicles
Vehicle Replacement - Fire Engine 2-2-12102 1033 97,461 100,000 2,539 Complete
Equipment
ESS Container 2-2-12202 1057 6,461 7,000 539 Complete
SUB-TOTAL 2,256,646 3,107,000 852,082
Police Services
RCMP Equipment 2-2-12301 1059 1,728 1,728 End of Dec. if req.
SUB-TOTAL 1,728 852,082
Administration / General Government
Software Upgrades 2-2-13103 1039 2,261 15,000 12,739 Complete
Computer Replacements - 10 computers to be replaced + new switches 2-2-13103 1043 12,068 13,500 1,432 Complete
Computer Server Replacement 2-2-13103 1044 9,148 17,000 7,852 Complete
New interdepartmental vehicle (replaces 1991 Sprint) 2-2-13104 1058 20,351 25,000 4,649 Complete
Land Acquisitions
Misc. Land Acquisition 2-2-13201 153/1054/10 22,602 130,000 107,398 Complete
SUB-TOTAL 66,430 200,500 134,070
TOTAL 2013 CAPITAL PROJECTS 8,697,692 11,472,183 96,500 2,870,991