View Royal Public Safety Building Monthly Report for February 2015
Progress report on the construction of the View Royal Public Safety Building, including status, work progress, and photographs.
View Royal Public Safety Building
Monthly Report for February 2015

Date of report: 4 March 2015
PREPARED FOR:
Kim Anema, Chief Administrative Officer Town of View Royal
Paul Hurst, Fire Chief, Emergency Program Coordinator View Royal Fire Rescue
PREPARED BY:
Heather Spinney, Architect AIBC Hughes Condon Marler Architects
CONTENTS:
| Section | Page |
|---|---|
| Introduction | 3 |
| Status of Project | 3 |
| Work Progress | 3 |
| Progress Photographs | 4-6 |
| Supplemental Instructions | 7 |
| Change Orders / Change Directives | 7 |
INTRODUCTION
This report summarizes the progress and status of the View Royal Public Safety Building up to the end of the month of February 2015.
STATUS OF PROJECT
Construction Coordination Meetings have been concluded.
- Contractor focusing on completing installation of systems + finishes + exterior works.
WORK PROGRESS
Key tasks started, in progress or completed this month include:
- Interior Finishing
- Concrete Floor Finish – Remediation
- Life Safety Demonstrations (remainder)
- Substantial Completion achieved
Refer to the following pages for photographs illustrating the current progress of construction.
Progress Photographs



SUPPLEMENTAL INSTRUCTIONS
The following Supplemental Instructions have been issued up to February 28, 2015:
- SI No. 130 – Door 102 – Film. Issued 17 February, 2015.
CHANGE ORDERS
The following Change Orders have been issued up to February 28, 2015:
- CO No. 115: Paint Speaker Baffles + Vent. Issued 27 February, 2015.
CHANGE DIRECTIVES
The following Change Directives have been issued up to February 28, 2015:
- CD No. 23: RFI 169 – Roof Rail. Issued 6 February, 2015.
- CD No. 24: RFI 168 + 170. Issued 6 February, 2015.