Committee of the Whole/Documents/Staff Report: View Royal Public Safety Building Monthly Report for March 2015
Staff Report

Staff Report: View Royal Public Safety Building Monthly Report for March 2015

April 14, 2015Pages 34–4010 sections

A project status report from the architects regarding the final stages of the Public Safety Building construction, including occupancy and change orders.

Occupancy Permit issued: March 12, 2015Building operational: March 12, 2015Change Order No. 47: Changes to East Property LineReport Date: April 9, 2015

View Royal Public Safety Building

Page 34–40

Monthly Report for March 2015

Photograph of the old fire station with a sign reading "VIEW ROYAL FIRE RESCUE WE HAVE MOVED 333 ISLAND HWY", dated 16 March 2015
Photograph of the old fire station with a sign reading "VIEW ROYAL FIRE RESCUE WE HAVE MOVED 333 ISLAND HWY", dated 16 March 2015

Date of report: 9 April 2015

Page 34–40

Monthly Report for March 2015

PREPARED FOR: Kim Anema, Chief Administrative Officer Town of View Royal

Paul Hurst, Fire Chief, Emergency Program Coordinator View Royal Fire Rescue

PREPARED BY: Heather Spinney, Architect AIBC Hughes Condon Marler Architects

CONTENTS:

Section Page
Introduction 3
Status of Project 3
Work Progress 3
Progress Photographs 4-6
Supplemental Instructions 7
Change Orders / Change Directives 7
Page 34–40

INTRODUCTION

This report summarizes the progress and status of the View Royal Public Safety Building up to the end of the month of March 2015.

Page 34–40

STATUS OF PROJECT

Construction Coordination Meetings have been concluded.

  • Occupancy Permit issued 12 March, 2015
  • Public Safety Building became operational 12 March, 2015.
Page 34–40

WORK PROGRESS

Key tasks started, in progress or completed this month include:

  • Deficiencies

Refer to the following pages for photographs illustrating the current progress of construction.

Page 34–40

Progress Photographs

Wide exterior view of the completed View Royal Public Safety Building, 5 March 2015
Wide exterior view of the completed View Royal Public Safety Building, 5 March 2015
Exterior view of the training tower and red shipping containers, 5 March 2015
Exterior view of the training tower and red shipping containers, 5 March 2015
Interior view of the empty apparatus bay with yellow floor markings, 5 March 2015
Interior view of the empty apparatus bay with yellow floor markings, 5 March 2015
Page 34–40

SUPPLEMENTAL INSTRUCTIONS

The following Supplemental Instructions have been issued up to March 31, 2015:

Page 34–40

CHANGE ORDERS

The following Change Orders have been issued up to March 31, 2015:

  • CO No. 47: PCN 47R – Changes to East Property Line -, Issued 31 March, 2015.
  • CO No. 108: PCN 108 – RFI 136 – Door Sill Details – 222-225 + Storefront 105 -, Issued 31 March, 2015.
  • CO No. 116: CD 18 – Alternate SK-1, Issued 31 March, 2015.
  • CO No. 117: - CR 920128 - Antenna Cables, Issued 31 March, 2015.
  • CO No. 118: CR 920127 - Fuel for Genset, Issued 31 March, 2015.
  • CO No. 119: CR 920126 - Core Hole for Owner Equipment, Issued 31 March, 2015.
Page 34–40

CHANGE DIRECTIVES

The following Change Directives have been issued up to March 31, 2015: