Committee of the Whole/Documents/View Royal Public Safety Building Monthly Report for December 2014
Staff Report

View Royal Public Safety Building Monthly Report for December 2014

February 10, 2015Page 244 sections

Brief update on project status and key tasks completed for the Public Safety Building construction as of the end of 2014.

6.1.3.c View Royal Public Safety Building Report for the month of January 2015
Construction coordination meetings conductedInfrastructure and finish installations in progress

View Royal Public Safety Building Town of View Royal

Page 24

INTRODUCTION

This report summarizes the progress and status of the View Royal Public Safety Building up to the end of the month of December 2014.

Page 24

STATUS OF PROJECT

2 Construction Coordination Meetings have been conducted.

  • Installation of civil, mechanical & electrical infrastructure in progress.
  • Installation of fenestration in progress
  • Installation of exterior finishes in progress
  • Installation of interior finishes / assemblies in progress
Page 24

WORK PROGRESS

Key tasks started, in progress or completed this month include:

  • Grading
  • Concrete Curbs + Exterior Concrete Slabs + Paving
  • Interior Concrete Slabs
  • Civil, Mechanical + Electrical Infrastructure
  • Installation of interior finishes / assemblies
  • GWB + Tile Remediation

Refer to the following pages for photographs illustrating the current progress of construction.

Page 24