Committee of the Whole/Documents/View Royal Public Safety Building Monthly Report for December 2014
Staff Report

View Royal Public Safety Building Monthly Report for December 2014

January 13, 2015Pages 27–337 sections

Architect's progress report on the construction of the new Public Safety Building.

6.1.3 c) View Royal Public Safety Building Report for the month of December 2014
Date of report: 8 January 2015Progress tasks: Grading, Concrete Curbs, Interior Slabs11 Supplemental Instructions and 4 Change Orders issued up to December 31, 2014

View Royal Public Safety Building

Town of View Royal

Monthly Report for December 2014

Exterior photograph of the building construction site with red coverings on the door openings and a truck in the foreground, dated 4 December 2014
Exterior photograph of the building construction site with red coverings on the door openings and a truck in the foreground, dated 4 December 2014

Date of report: 8 January 2015


Page 27–33

Monthly Report for December 2014

PREPARED FOR: Kim Anema, Chief Administrative Officer Town of View Royal

Paul Hurst, Fire Chief, Emergency Program Coordinator View Royal Fire Rescue

PREPARED BY: Heather Spinney, Architect AIBC Hughes Condon Marler Architects

CONTENTS:

Section Page
Introduction 3
Status of Project 3
Work Progress 3
Progress Photographs 4-6
Supplemental Instructions 7
Change Orders / Change Directives 7
Appendix A Schedule

Page 27–33

INTRODUCTION

This report summarizes the progress and status of the View Royal Public Safety Building up to the end of the month of December 2014.

Page 27–33

STATUS OF PROJECT

2 Construction Coordination Meetings have been conducted.

  • Installation of civil, mechanical & electrical infrastructure in progress.
  • Installation of fenestration in progress
  • Installation of exterior finishes in progress
  • Installation of interior finishes / assemblies in progress
Page 27–33

WORK PROGRESS

Key tasks started, in progress or completed this month include:

  • Grading
  • Concrete Curbs + Exterior Concrete Slabs + Paving
  • Interior Concrete Slabs
  • Civil, Mechanical + Electrical Infrastructure
  • Installation of interior finishes / assemblies
  • GWB + Tile Remediation

Refer to the following pages for photographs illustrating the current progress of construction.


Wide panoramic view of the building construction site and surrounding terrain, dated 4 December 2014
Wide panoramic view of the building construction site and surrounding terrain, dated 4 December 2014
Interior construction view showing overhead mechanical systems and a large yellow ventilation duct, dated 4 December 2014
Interior construction view showing overhead mechanical systems and a large yellow ventilation duct, dated 4 December 2014
Wide view of the building exterior showing completed paving and glass bay doors, dated 18 December 2014
Wide view of the building exterior showing completed paving and glass bay doors, dated 18 December 2014



Page 27–33

SUPPLEMENTAL INSTRUCTIONS

The following Supplemental Instructions have been issued up to December 31, 2014:

  • SI No. 113 – RFI 990155 – Exterior Soffit + Entrance Paneling. Issued 2 December, 2014.
  • SI No. 114 – GL 4 Glazing – Mechanical Fastening. Issued 3 December, 2014.
  • SI No. 115 – GWB + Tile Remediation. Issued 3 December, 2014.
  • SI No. 116 – Door 222-225 Frames – Paint Colour. Issued 5 December, 2014.
  • SI No. 117 – Wash Down 127 – Curb Height. Issued 5 December, 2014.
  • SI No. 118 – Wood Ceiling Tile Orientation. Issued 5 December, 2014.
  • SI No. 119 – Hydro Seed Mixture. Issued 16 December, 2014.
  • SI No. 120 – Hose Tower Roof. Issued 17 December, 2014.
  • SI No. 121 – MSI-16 – Delete Return Air Grilles. Issued 19 December, 2014.
  • SI No. 122 – Delay Hydro Seed + Sod Installation. Issued 19 December, 2014.
  • SI No. 123 – Plant Substitution Request. Issued 19 December, 2014.
Page 27–33

CHANGE ORDERS

The following Change Orders have been issued up to December 31, 2014:

  • CO No. 106: Aluminum Tile Edge. Issued 08 December, 2014.
  • CO No. 107: CD 06 – Rock Slope Stability. Issued 3 December, 2014.
  • CO No. 109: Substitution Request 004R (Alternate Tile Grout). Issued 3 December, 2014.
  • CO No. 111: Relocate Landscape Bollards (Owner direction on site). Issued 19 December, 2014.
Page 27–33

Document Images

(3)
Document image
Document image
Document image
Extracted from: 2015 01 13 Committee of the Whole Agenda