Public Safety Building Budget Summary

January 13, 2015Pages 34–361 section

Detailed financial tables showing construction costs, contingencies, and variance for the Public Safety Building.

6.1.3 c) View Royal Public Safety Building Report for the month of December 2014
Tendered Price: $5,753,611Adjusted Construction Cost Total: $7,256,260 (Budget after tender)YTD Total as of Dec 31, 2014: $6,343,059

PUBLIC SAFETY BUILDING

Financial table for Public Safety Building project budget, part 1
Financial table for Public Safety Building project budget, part 1
Description Budget after Tender Revisions Revised Budget As at Dec 31, 2014 Committed Total Budget Variance
Planning and Design $ 527,025 $ 2,300 $ 529,325 $ 465,167 $ - $ 465,167 $ 64,158
Tendered Price (note 1)
Base Tendered Price 4,948,264 - 4,948,264 4,498,773 - 4,498,773 449,491
Cash Allowances 805,347 (9,118) 796,229 738,826 - 738,826 57,403
Subtotal 5,753,611 (9,118) 5,744,493 5,237,599 - 5,237,599 506,894
Reserves and Contingencies 224,060 (223,808) 252 - - - 252
Proceeds from Disposals - (50,000) (50,000) - (15,000) (15,000) (35,000)
Extras Approved
Site Conditions - 63,528 63,528 63,527 1 63,528 -
Design Corrections - 93,861 93,861 79,613 14,248 93,861 -
Owner Requests - 97,151 97,151 79,265 17,886 97,151 -
Opportunity Change - (32,706) (32,706) (32,706) - (32,706) -
Subtotal - 221,834 221,834 189,699 32,135 221,834 -
Extras Proposed
Site Conditions - 4,826 4,826 - - - 4,826
Design Corrections - 84,320 84,320 - - - 84,320
Owner Requests - - - - - - -
Opportunity Change - - - - - - -
Subtotal - 89,146 89,146 - - - 89,146
Owner Changes Contemplated
Site security fencing 12,000 - 12,000 - - - 12,000
Key FOB security system 22,854 - 22,854 - 22,854 22,854 0
IT backup town server and fire department server 32,000 - 32,000 13,541 18,459 32,000 -
Upper lot paving/infrastructure/landscaping 54,000 - 54,000 - - - 54,000
Training yard components 22,500 - 22,500 - - - 22,500
Finish volunteer rental suites 48,000 - 48,000 - 669 669 47,331
Continuation of the budget table, covering additional Owner Changes, Completion Costs, and Off Site Services
Continuation of the budget table, covering additional Owner Changes, Completion Costs, and Off Site Services
Description Budget after Tender Revisions Revised Budget As at Dec 31, 2014 Committed Total Budget Variance
LED community message board 40,000 - 40,000 - - - 40,000
Building maintenance equipment 6,000 - 6,000 - - - 6,000
Finish trailer enclosure 15,000 - 15,000 - - - 15,000
Mezzanine winch and beam 10,000 - 10,000 - - - 10,000
Amount available for overages 124,245 (102,000) 22,245 - - - 22,245
Subtotal 386,599 (102,000) 284,599 13,541 41,982 55,523 229,076
Completion Costs
Furniture & Equipment 150,000 - 150,000 67,411 - 67,411 82,589
DCC 41,760 - 41,760 41,760 - 41,760 0
Building Permit/Testing Structural and Geotech. 25,750 25,000 50,750 59,528 - 59,528 (8,778)
Connection Fees (BC Hydro Fee) 48,115 15,986 64,101 59,896 - 59,896 4,205
Administration Costs 10,000 - 10,000 1,041 - 1,041 8,959
Legal Costs 8,000 40,000 48,000 9,033 - 9,033 38,967
Insurance Costs 11,340 (11,340) - - - - -
Public Art 35,000 - 35,000 - - - 35,000
Operation/Startup Costs 35,000 - 35,000 819 - 819 34,181
Subtotal 364,965 69,646 434,611 239,488 - 239,488 195,123
Adjusted Construction Cost Total $ 7,256,260 $ (2,000) $ 7,254,260 $ 6,145,495 $ 59,117 $ 6,204,611 $ 1,049,649
Off Site Services
Off Site Design 30,000 2,000 32,000 44,652 - 44,652 (12,652)
Storm Drain 60,000 - 60,000 43,607 - 43,607 16,393
Traffic Control (fire warning flashers) 30,000 - 30,000 39,264 - 39,264 (9,264)
Traffic Islands / Painting 5,000 - 5,000 2,150 - 2,150 2,850
Fibre and Electrical Conduits Crossing 20,900 - 20,900 8,775 - 8,775 12,125
Subtotal $ 145,900 $ 2,000 $ 147,900 $ 138,447 $ - $ 138,447 $ 9,453
Final total for construction and off site services, and Note 1 breakdown
Final total for construction and off site services, and Note 1 breakdown
Description Budget after Tender Revisions Revised Budget As at Dec 31, 2014 Committed Total Budget Variance
Total Construction and Off Site Services $ 7,402,160 $ (0) $ 7,402,160 $ 6,283,942 $ 59,117 $ 6,343,059 $ 1,059,101

Note 1

Item Amount
Tendered price 5,753,611
Tax charged (rebatable) 287,681
Total including tax 6,041,292
Page 34–36