January 13, 2015Page 791 section

Financial status update on the Town's 2014 approved capital projects.

6.2.3 d) Capital Project Update
January 8, 2015Total approved 2014 capital expenditures: $8,239,888

TOWN OF VIEW ROYAL COMMITTEE OF THE WHOLE REPORT

TO: Committee of the Whole DATE: January 8th, 2015 FROM: Jennifer Lockhart, Senior Accountant MEETING DATE: January 13th, 2015

CAPITAL PROJECT UPDATE

RECOMMENDATION: THAT the Committee receive the January 8th, 2015 Capital Project Update Report for information.

CHIEF ADMINISTRATIVE OFFICER'S COMMENTS: I concur with the recommendation.

PURPOSE OF REPORT: To provide Council with information regarding capital project expenditures and projected completion dates.

INFORMATION: For 2014, the Town has approved capital expenditures of $8,239,888. The attached report outlines expenditures to December 31st, 2014 and current projected completion dates.

RECOMMENDATION: THAT the Committee receive the January 8th, 2015 Capital Project Update Report for information.

SUBMITTED BY: J. Lockhart, Senior Accountant

REVIEWED BY: K. Anema, Chief Administrative Officer