This site is in beta — data may be incomplete and features are still being added.
Committee of the Whole/Documents/Appendix B: Capital Project Update Report
Appendix

Appendix B: Capital Project Update Report

July 11, 2017Page 230 sections

Status update and budget variance for specific capital projects in transportation, drainage, sewer, parks, fire, and police services.

6.2.3(a) 2nd Quarter Budget Variance and Capital Project Update Report
Burnett Rd-Pheasant Ln reconstruction 96% completePrice Bay Pump Stn upgrade: $125,986 spent YTDFire Engine replacement ($750,000) deferred

No sections available for this document.