Committee of the Whole/Documents/Staff Report: 2nd QUARTER BUDGET VARIANCE AND CAPITAL PROJECT UPDATE REPORT
Staff Report

Staff Report: 2nd QUARTER BUDGET VARIANCE AND CAPITAL PROJECT UPDATE REPORT

July 11, 2017Pages 20–212 sections

A report from the Director of Finance summarizing the town's financial operations and capital project progress to the end of Q2 2017.

2. APPROVAL OF AGENDA
July 5, 2017Dawn Christenson, Director of Finance$695,908 variance in Sales of services and other revenue due to property sale proceeds$765,500 in General capital projects deferred

TOWN OF VIEW ROYAL Finance & Administration Report

TO: Committee of the Whole DATE: July 5, 2017 FROM: Dawn Christenson, Director of Finance MEETING DATE: July 11, 2017

Page 20–21

2ND QUARTER BUDGET VARIANCE AND CAPITAL PROJECT UPDATE REPORT

RECOMMENDATION:

THAT the Committee receive the 2nd Quarter Budget Variance and Capital Project Update Report for information.

CHIEF ADMINISTRATIVE OFFICER COMMENTS:

I concur with the recommendation.

PURPOSE OF REPORT:

To provide Council with information regarding the financial results of operations and progress of capital projects to the end of second quarter 2017.

BACKGROUND:

In May, 2017 Council adopted a five-year financial plan (Bylaw 967) that identifies revenue and expense targets and authorizes capital projects to further its strategic objectives. The attached Appendix A – Consolidated Budget Variance and Appendix B – Capital Project Update are provided to inform Council of the financial results of delivering services and capital projects to the end of the second quarter this year.

DISCUSSION:

Analysis shows that revenues and expenses to date are within expected variances at the mid-point in the fiscal year with few exceptions, as noted below:

Category Variance amount Explanation
Sales of services and other revenue $695,908 Proceeds from sale of property; corresponding recognition of costs and transfers to reserves in accordance with new policy not yet completed
General capital $765,500 Projects deferred
General capital $73,936 2016 projects not completed by year end; 2017 financial plan amendment pending

Staff will continue to monitor financial results to ensure delivery of services and capital projects within the allocated budgets. Should corrective measures be necessary, staff will inform Council of the effect, if any, on service levels or project completion timelines.

RECOMMENDATION:

THAT the Committee receive the 2nd Quarter Budget Variance and Capital Project Update Report for information.

SUBMITTED BY:

Dawn Christenson, BAccS, CPA, CGA Director of Finance

REVIEWED BY:

Kim Anema, Chief Administrative Officer

Attachments: Appendix A: 2nd Quarter Consolidated Budget Variance Appendix B: Capital Project Update