Committee of the Whole/Documents/Appendix B: Capital Project Update
Appendix

Appendix B: Capital Project Update

July 11, 2017Page 232 sections

A status report for all 2017 capital projects including transportation, drainage, sewer, parks, and fire services.

2. APPROVAL OF AGENDA
$182,015 spent on Burnett Rd-Pheasant Ln road reconstruction$750,000 budget for new Fire Engine (deferred)Total 2017 Capital Projects Budget: $3,024,635

2nd Quarter Budget Variance and Capital Project Update Report

Page 23

Appendix B: Capital Project Update

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
Transportation
Road Reconstruction
11105 Road Projects 1109 Burnett Rd-Pheasant Ln (ld Isl Hwy) Cons 182,015 190,000 7,985 96% July
11105 Road Projects 1111 Island Hwy Stewart to Beaumont - Design 50,644 93,330 42,686 54% September
11105 Road Projects 1139 Stoneridge Development Sidewalk Replcmt - 45,000 45,000 0% August
11105 Road Projects 1140 Watkiss Way Median East of Talcott Road - 55,000 55,000 0% August
Miscellaneous
11106 Other Transportation Projects 1074 Watkiss Way Improved Ped Walkway & Light - 20,000 20,000 0% October
11106 Other Transportation Projects 1120 ECV - Park Trail to Little Rd N end ph 2 - 70,000 70,000 0% December
11106 Other Transportation Projects 1121 Kayak launch on Shoreline Drive 8,500 24,000 15,500 35% Deferred
11106 Other Transportation Projects 1122 Quincy St Pedestrian Access - 35,000 35,000 0% October
Annual Pavement Rehabilitation
11107 Repaving 1141 Westoby Road Seal Coating - 40,000 40,000 0% August
11107 Repaving 1142 Atkins Road East of Six Mile Road repair 62,806 70,000 7,194 90% Complete
11107 Repaving 1143 Hospital Way 36,737 37,500 763 98% Complete
Electrical
11108 Signals 1118 Isl Hwy at Heddle ped crosswalk 1,069 150,000 148,932 1% November
11108 Signals 1144 Isl Hwy Knollwood/Kislinbury ped heads - 30,000 30,000 0% October
11108 Signals 1145 Burnside Rd W at High St Flashing Ped X - 40,000 40,000 0% October
Structures
11109 Bridges 1013 Craigflower Bridge Construction - Land - 10,000 10,000 0% September
SUB-TOTAL 341,770 909,830 568,060 38%
Drainage
11201 Collection System (Drainage) 1124 VR Ave-Beaumont Ave to Stew. Ave design 4,525 14,000 9,475 32% September
SUB-TOTAL 4,525 14,000 9,475
Sewer
11702 Lift Stations 1125 Price Bay Pump Stn upgrade 125,986 378,500 252,514 33% July
11702 Lift Stations 1146 Stoneridge and Wilfert Pump Stn Pumps 29,293 35,000 5,707 84% September
SUB-TOTAL 155,279 413,500 258,221
Parks
Park Improvements
11302 Park Improvements 1129 Playgrounds - replacement program 29,626 52,000 22,374 57% July
Park Development
11303 Park Development 1028 View Royal Park - 150,000 150,000 0% October
11303 Park Development 1147 Chilco Trails Implementation Plan - 75,000 75,000 0% November
Park Vehicles
11304 Park Vehicles 1132 New 1/2 Ton Park Pick up and accessories 30,848 21,756 (9,092) 142% August
Improvement to Public Buildings
11401 Building Improvements 1133 Park Shop repair 12,060 - (12,060) 0% Complete
11401 Building Improvements 1136 Flag poles 2,774 5,000 2,226 55% July
11401 Building Improvements 1138 Council Chamber - renovation 2,347 27,000 24,653 9% September
SUB-TOTAL 77,654 330,756 253,102
Fire Services
Buildings
12101 Fire - Buildings 1149 Training Ground - 100,000 100,000 0% December
12101 Fire - Buildings 1032 Public Safety Building 52,784 - (52,784) 0% Complete
Vehicles
12102 Fire - Vehicles 1033 Fire Engine - 750,000 750,000 0% Deferred
Furniture & Equipment
12103 Fire - Furniture and Equipment 1150 Hose Replacement - 15,000 15,000 0% September
12103 Fire - Furniture and Equipment 1151 Tires - 15,000 15,000 0% September
SUB-TOTAL 52,784 880,000 827,216
Police Services
12301 Police Services 1152 RCMP 2017 capital projects - 47,400 47,400 0% TBD
SUB-TOTAL - 47,400 47,400
Administration / General Government
Information Technology
13103 Information Technology 1070 Annual IS Replacement Program - 51,000 51,000 0% December
13103 Information Technology 1135 IT strategic plan implementation 546 278,149 277,603 0% December
Land Acquisitions
13201 Land Acquisitions 1045 Misc Land Acquisitions - 100,000 100,000 0% Ongoing
SUB-TOTAL 546 429,149 428,603
Total 2017 Capital Projects 632,559 3,024,635 2,392,076