Project Summary: Sewer SCADA Pack Upgrades

April 8, 2025Page 341 section

A project to supply and install new SCADA packs at all 17 sewer pump stations to improve data accuracy.

8.1.a) 2025 Draft Financial Plan
$106,000 capital budgetPriority: OptimalFunding from Sewer Capital Reserve

Project Summary

Priority: Optimal
Public Engagement: Not applicable
Financial Plan: 2025 – 2029 (C-200)

Project Name: Sewer SCADA Pack Upgrades (5-2-11703-950 CC1303)
Submitted by: Darryl Woodley
Director: Ivan Leung, Sewer

Overview of Project Summary form
Overview of Project Summary form
Project details and executive summary
Project details and executive summary

Executive Summary

As the community continues to urbanize in areas stipulated in the updated Official Community Plan (2026), data accuracy will become more important when assessing and analysis the health of the Town's sanitary sewer system.

This project recommends an upgrade to the SCADA system at all pump stations to support DNP3 polling which will increase the accuracy and usability of the flow data collected (aka "SCADA packs"). This will significantly improve accuracy when modeling sewer catchment flows and inflow and infiltration data: key metrics in measuring current and future sanitary sewer system health.

Recommended to be scheduled in 2025 so that more accurate readings and a 1 year period can be provided for the Sanitary Sewer Master Plan (scheduled 2026).

Business problem and opportunity

The current SCADA system at the Town's pump stations only support Modbus polling methods which result in poor data for flow meters, which results in poorer accuracy in hydraulic modelling exercises.

Proposed project objectives

To supply and install the new SCADA packs at all 17 sewer pump stations in View Royal.

Business risks

With the OCP expected to be updated in 2026, a preliminary sensitivity analysis indicated that the existing data may be less useful for future sanitary modelling purposes. In other words, less accurate data has a negative and incremental effect to the resilience and accuracy of the sanitary model, thus impacting project priorities.

Proposed sources of funding

Sewer Capital Reserve 5-1-00500-173

Costs, benefits, and recommendation
Costs, benefits, and recommendation

Costs and benefits

Costs FY1 FY2 FY3 FY4 FY5 5-year Total
Capital 106,000 0 0 0 0 106,000
Operational 0 0 0 0 0 0
Total 106,000 0 0 0 0 106,000

Benefits

  • Tangible: [Empty]
  • Intangible: [Empty]

Recommendation

THAT the Committee recommend the 2025-2029 Financial Plan include Sewer SCADA Pack Upgrades in 2025 to be funded by .