Attachment 5 - Construction Impact Assessment & Tree Management Plan
An arborist report evaluating the impact of the proposed development on existing trees and outlining retention and mitigation strategies.
1. INTRODUCTION
Talbot Mackenzie & Associates was asked to complete a tree inventory, subdivision impact assessment and management plan for the trees at the following proposed project:
- Site: 10 Erskine Lane
- Municipality: View Royal
- Client Name: Parsi Development Ltd.
- Dates of Site Visit: October 21, 2021
- Site Conditions: 1 urban lot interfacing with the Galloping Goose trail. 2 existing residences on the lot, no ongoing construction activity
The purpose of this report is to address the tree inventory and arborist report requirements of the Town of View Royal Bylaw No. 695. The construction impact assessment section of this report (section 8), is based on plans reviewed to date, including the architectural site, floor and elevation plans (prepared by Parsi Development Ltd.). At this time we have not reviewed a detailed landscape plan or a servicing or grading plan.
2. TREE INVENTORY METHODOLOGY
Numerated metal tags were used to identify bylaw protected onsite trees. Trees located on the neighbouring property to the West or municipal frontage were not tagged. Each tree was visually examined on a limited visual assessment basis (level 1), in accordance with Tree Risk Assessment Qualification (TRAQ) methods (Dunster et al. 2017) and ISA Best Management Practices.
3. EXECUTIVE SUMMARY
Based on review of the Architectural plans provided, it is anticipated that 27 bylaw protected onsite trees and 1 municipal tree will require removal to facilitate construction of the proposed underground parkade. 17 onsite trees, 4 municipal trees, 10 private offsite trees and 1 offsite hedge are located where they can be retained provided that their critical root zones can be adequately protected during construction. It is understood that a replanting plan will be prepared by others.
4. TREE INVENTORY DEFINITIONS
Tag: Tree identification number on a metal tag attached to tree with nail or wire, generally at eye level. Trees on municipal or neighboring properties are not tagged.
DBH: Diameter at breast height – diameter of trunk, measured in centimetres at 1.4m above ground level. For trees on a slope, it is taken at the average point between the high and low side of the slope.
- *Measured over ivy
- ~ Approximate due to inaccessibility or on neighbouring property
Dripline: Indicates the radius of the crown spread measured in metres to the dripline of the longest limbs.
Relative Tolerance Rating: Relative tolerance of the tree species to construction related impacts such as root pruning, crown pruning, soil compaction, hydrology changes, grade changes, and other soil disturbance. This rating does not take into account individual tree characteristics, such as health and vigour. Three ratings are assigned based on our knowledge and experience with the tree species: Poor (P), Moderate (M) or Good (G).
Critical Root Zone: A calculated radial measurement in metres from the trunk of the tree. It is the optimal size of tree protection zone and is calculated by multiplying the DBH of the tree by 10, 12 or 15 depending on the tree’s Relative Tolerance Rating. This methodology is based on the methodology used by Nelda Matheny and James R. Clark in their book “Trees and Development: A Technical Guide to Preservation of Trees During Land Development.”
- 15 x DBH = Poor Tolerance of Construction
- 12 x DBH = Moderate
- 10 x DBH = Good
To calculate the critical root zone, the DBH of multiple stems is considered the sum of 100% of the diameter of the largest stem and 60% of the diameter of the next two largest stems. It should be noted that these measures are solely mathematical calculations that do not consider factors such as restricted root growth, limited soil volumes, age, crown spread, health, or structure (such as lean).
Health Condition:
- Poor - significant signs of visible stress and/or decline that threaten the long-term survival of the specimen
- Fair - signs of stress
- Good - no visible signs of significant stress and/or only minor aesthetic issues
Structural Condition:
- Poor - Structural defects that have been in place for a long period of time to the point that mitigation measures are limited
- Fair - Structural concerns that are possible to mitigate through pruning
- Good - No visible or only minor structural flaws that require no to very little pruning
Suitability ratings are described as follows:
Rating: Suitable.
- A tree with no visible or minor health or structural defects, is tolerant to changes to the growing environment and is a possible candidate for retention provided that the critical root zone can be adequately protected.
Rating: Conditional.
- A tree with good health but is a species with a poor tolerance to changes to its growing environment or has a structural defect(s) that would require that certain measures be implemented, in order to consider it suitable for retention (ie. retain with other codominant tree(s), structural pruning, mulching, supplementary watering, etc.)
Rating: Unsuitable.
- A tree with poor health, a major structural defect (that cannot be mitigated using ANSI A300 standards), or a species with a poor tolerance to construction impacts, and unlikely to survive long term (in the context of the proposed land use changes).
Retention Status:
- Remove - Not possible to retain given proposed construction plans
- Retain - It is possible to retain this tree in the long-term given the proposed plans and information available. This is assuming our recommended mitigation measures are followed
- Retain * - See report for more information regarding potential impacts
Table 1. Tree Inventory
| Prev. Tag # | Tag or ID # | Surveyed? | Location | Bylaw Protected? | Common Name | Botanical Name | dbh (cm) | Ht (m) | Critical Root Zone Radius (m) | Dripline Diameter (m) | Health | Structural | Suitability (onsite trees) | Relative Tolerance | General Field Observations/Remarks | Tree Retention/Location Comments | Retention Status |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| M1 | Yes | Municipal | Municipal | Garry Oak | Quercus garryana | 59 below unions | 10 | 5.9 | 13 | Good | Fair | Good | Canopy weighted slightly south. | Project arborist to supervise all excavation required within the critical root zone. | Retain | ||
| M2 | No | Municipal | Municipal | Douglas-fir | Pseudotsuga menziesii | 41 | 10 | 4.9 | 8 | Fair | Fair | Moderate | Previous topping likely, suppressed. Surface rooted. | Project arborist to supervise all excavation required within the critical root zone. | Retain | ||
| M3 | No | Municipal | Municipal | Douglas-fir | Pseudotsuga menziesii | 43 | 15 | 5.2 | 9 | Fair | Fair | Moderate | Drought stress. | Project arborist to supervise all excavation required within the critical root zone. | Retain | ||
| OS1 | No | Shared off-site/municipal | Shared municipal | Western Red Cedar | Thuja plicata | 15avg. | 3 | 2.3 | 4 | Good | Fair | Poor | Hedge near west PL, appears to be shared municipal\neighbour (strata). | Will be impacted by excavation for the foundation of the proposed underground parkade. | Remove | ||
| 3546 | No | On | Yes | Bigleaf Maple | Acer macrophyllum | Multiple stems | 10 | 8 | 10 | Good | Poor | Suitable | Moderate | Multiple large epicormic shoots emerging from stump. | Located within the footprint of the proposed underground parkade. | Remove | |
| 3547 | No | On | Yes | Leyland Cypress | Cupressus x leylandii | 31 | 10 | 3.1 | 6 | Good | Fair | Suitable | Good | Part of hedge row (20 stems total). | Located within the footprint of the proposed underground parkade. | Remove | |
| 3548 | No | On | Yes | Leyland Cypress | Cupressus x leylandii | 31 | 10 | 3.1 | 6 | Good | Fair | Suitable | Good | Part of hedge row (20 stems total). Multiple leaders emerging at 3m. | Located within the footprint of the proposed underground parkade. | Remove | |
| 3549 | No | On | Yes | Bigleaf Maple | Acer macrophyllum | Multiple stems | 5 | 5 | 9 | Fair | Fair-poor | Suitable | Moderate | Cluster, hydro clearance pruning historically, decay main stem. | Will be impacted by excavation required for the foundation of the proposed underground parkade. | Remove | |
| 3550 | No | On | Yes | Douglas-fir | Pseudotsuga menziesii | 20 | 6 | 2.4 | 4 | Fair | Fair | Suitable | Moderate | Stunted form. | Will be impacted by excavation required for the foundation of the proposed underground parkade. | Remove | |
| 3551 | No | On | Yes | Douglas-fir | Pseudotsuga menziesii | 23 | 4 | 2.8 | 3 | Fair | Fair-poor | Suitable | Moderate | Previously topped at 2m. | Will be impacted by excavation required for the foundation of the proposed underground parkade. | Remove | |
| 3552 | No | On | Yes | Leyland Cypress | Cupressus x leylandii | ~30 | 10 | 3 | 7 | Good | Fair | Suitable | Good | Part of large hedge row (~22 stems). | Located within the footprint of the proposed underground parkade. | Remove | |
| 68 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 46 | 18 | 5.5 | 9 | Fair | Poor | Suitable | Moderate | Previously topped at 4m, large deflected leaders, pitch flow from unions. | Located within the footprint of the proposed underground parkade. | Remove | |
| 69 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 39 | 15 | 4.7 | 9 | Fair | Fair-poor | Suitable | Moderate | Previously topped at 4m, large deflected leaders. | Located within the footprint of the proposed underground parkade. | Remove | |
| 70 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 40,30 | 15 | 7.0 | 10 | Fair | Fair-poor | Suitable | Moderate | Previously topped at 4m, large deflected leaders. | Located within the footprint of the proposed underground parkade. | Remove | |
| 71 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 44 | 18 | 5.3 | 9 | Fair | Fair | Suitable | Moderate | Deflected trunk. | Located within the footprint of the proposed underground parkade. | Remove | |
| 92 | 3553 | Yes | On | Yes | Bigleaf Maple | Acer macrophyllum | 42 | 15 | 5 | 12 | Good | Fair | Suitable | Moderate | Codominant at ~6m with active inclusion. | Will be impacted by excavation required to construct the proposed above-ground parking. | Remove |
| 93 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 57 | 20 | 6.8 | 9 | Fair | Fair | Suitable | Moderate | Corrected lean, stunted top, asymmetrical crown. | Located within the footprint of the proposed underground parkade. | Remove | |
| 3554 | No | On | Yes | Douglas-fir | Pseudotsuga menziesii | 13 | 5 | 1.6 | 3 | Fair-poor | Fair | Suitable | Moderate | Suppressed. | Located within the footprint of the proposed underground parkade. | Remove | |
| 91 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 61 | 30 | 7.3 | 9 | Fair | Fair | Suitable | Moderate | Asymmetrical crown. | Will be impacted by excavation required to construct the proposed above-ground parking. | Remove | |
| OS2 | No | Off | Yes | arbutus | Arbutus menziesii | ~35 | 10 | 5.3 | 10 | Good | Fair | Poor | Canopy weighted west. | *Above ground parking proposed within the critical root zone. Project arborist to supervise all excavation required within the critical root zone. | Retain* | ||
| 3555 | No | On | Yes | Douglas-fir | Pseudotsuga menziesii | 51 | 20 | 6.1 | 5 | Fair | Fair | Suitable | Moderate | Narrow crown, stunted top, epicormic growth on trunk. | Located within the footprint of the proposed above ground parking. | Remove | |
| 94 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 75 | 30 | 9.0 | 14 | Fair | Fair | Suitable | Moderate | Some epicormic growth on trunk, small deadwood lower crown. | Located within the footprint of the proposed above ground parking. | Remove | |
| 95 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 47 | 20 | 5.6 | 8 | Fair | Fair | Suitable | Moderate | Asymmetrical crown, suppressed top. | Located within the footprint of the proposed above ground parking. | Remove | |
| 96 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 35 | 15 | 4.2 | 7 | Fair | Fair-poor | Suitable | Moderate | Asymmetrical crown, suppressed deflected top, epicormic growth. | Located within the footprint of the proposed above ground parking. | Remove | |
| 97 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 41 | 18 | 4.9 | 5 | Fair | Fair-poor | Suitable | Moderate | Narrow crown, deflected leader, epicormic growth, deadwood. | Located within the footprint of the proposed above ground parking. | Remove | |
| 100 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 69 | 35 | 8.3 | 16 | Good | Fair | Suitable | Moderate | Small deadwood. | Located within the footprint of the proposed above ground parking. | Remove | |
| 99 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 63 | 25 | 7.6 | 10 | Fair | Fair-poor | Suitable | Moderate | Deflected/suppressed top, lower deadwood, hanger. | Located within the footprint of the proposed above ground parking. | Remove | |
| 98 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 36 | 15 | 4.3 | 8 | Fair | Fair-poor | Suitable | Moderate | Deflected/suppressed top, asymmetrical crown, epicormic growth. | Located within the footprint of the proposed above ground parking. | Remove | |
| 83 | Yes | On | Yes | Grand fir | Abies grandis | ~85 | 35 | N/A | N/A | Dead | Dead | Unsuitable | N/A | Dead. | Located within the footprint of the proposed above ground parking. | Remove | |
| 85 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 45 | 20 | 5.4 | 7 | Fair | Fair | Suitable | Moderate | Stunted top, epicormic growth. | Located within the footprint of the proposed above ground parking. | Remove | |
| 84 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 25 | 15 | 3.0 | 5 | Fair | Fair | Suitable | Moderate | Suppressed. | *Above ground parking proposed within the critical root zone. Project arborist to supervise all excavation required within the critical root zone. | Retain* | |
| 86 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 32 | 20 | 3.8 | 6 | Fair | Fair | Suitable | Moderate | Stunted top. | Located within the footprint of the proposed above ground parking. | Remove | |
| 87 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 22 | 15 | 2.6 | 6 | Fair | Fair-poor | Suitable | Moderate | Deflected trunk, suppressed. | Located within the footprint of the proposed above ground parking. | Remove | |
| 88 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 65 | 30 | 7.8 | 9 | Fair | Fair | Suitable | Moderate | Pitch flow lower trunk. | *Above ground parking proposed within the critical root zone. Project arborist to supervise all excavation required within the critical root zone. | Retain* | |
| 89 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 60 | 30 | 7.2 | 10 | Fair | Fair | Suitable | Moderate | Leader deflects away from #90. | *Above ground parking proposed within the critical root zone. Project arborist to supervise all excavation required within the critical root zone. | Retain* | |
| 90 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 81 | 35 | 9.7 | 14 | Good | Fair | Suitable | Moderate | Small deadwood. | *Above ground parking proposed within the critical root zone. Project arborist to supervise all excavation required within the critical root zone. | Retain* | |
| 82 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 20 | 8 | 2.4 | 6 | Fair | Fair-poor | Suitable | Moderate | Previous top failure likely, new deflected leaders emerging. | Project arborist to supervise all excavation required within the critical root zone. | Retain | |
| 3556 | No | On | Yes | Douglas-fir | Pseudotsuga menziesii | 44 | 20 | 5.3 | 8 | Fair | Fair | Suitable | Moderate | Deflected leader, small deadwood. | *Above ground parking proposed within the critical root zone. Project arborist to supervise all excavation required within the critical root zone. | Retain* | |
| 3557 | No | On | Yes | Douglas-fir | Pseudotsuga menziesii | 17 | 15 | 2.0 | 3 | Fair-poor | Fair-poor | Suitable | Moderate | Dead top, epicormic growth | Project arborist to supervise all excavation required within the critical root zone. | Retain | |
| 3558 | No | On | Yes | Douglas-fir | Pseudotsuga menziesii | 19 | 15 | 2.3 | 2 | Fair-poor | Fair-poor | Suitable | Moderate | Low LCR. | Project arborist to supervise all excavation required within the critical root zone. | Retain | |
| 81 | Yes | Off (CRD) | Yes | Douglas-fir | Pseudotsuga menziesii | 107 | 15 | 12.8 | 10 | Poor | Poor | Moderate | Few live limbs, top 5m completely dead. | *Above ground parking proposed within the critical root zone. Project arborist to supervise all excavation required within the critical root zone. | Retain* | ||
| 80 | Yes | Off (CRD) | Yes | arbutus | Arbutus menziesii | 48 | 18 | 7.2 | 14 | Good | Fair | Poor | Canopy weighted south, small deadwood. | Project arborist to supervise all excavation required within the critical root zone. | Retain | ||
| 79 | Yes | Off (CRD) | Yes | Douglas-fir | Pseudotsuga menziesii | 79 | 35 | 9.5 | 14 | Good | Fair | Moderate | Deadwood lower crown. | Project arborist to supervise all excavation required within the critical root zone. | Retain | ||
| 3559 | No | On | Yes | Douglas-fir | Pseudotsuga menziesii | 15 | 12 | 1.8 | 3 | Fair-poor | Fair-poor | Moderate | Suppressed. | Project arborist to supervise all excavation required within the critical root zone. | Retain | ||
| 3560 | No | Off (CRD) | Yes | Grand fir | Abies grandis | 19 | 10 | 2.3 | 7 | Fair | Fair | Moderate | Top declining. | Project arborist to supervise all excavation required within the critical root zone. | Retain | ||
| 78 | Yes | On | Yes | arbutus | Arbutus menziesii | 30 | 13 | 4.5 | 10 | Good | Fair | Suitable | Poor | Leans northeast. Hanger from adjacent tree in canopy. | Project arborist to supervise all excavation required within the critical root zone. | Retain | |
| 77 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 70 | 35 | 8.4 | 10 | Fair | Fair | Suitable | Moderate | Trunk bends, epicormic growth on trunk, small deadwood. | Project arborist to supervise all excavation required within the critical root zone. | Retain | |
| 76 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 19 | 10 | 2.3 | N/A | Dead | Dead | Unsuitable | Moderate | Failed, supported by #75. | Project arborist to supervise all excavation required within the critical root zone. | Retain | |
| 75 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 57 | 30 | 6.8 | 8 | Fair | Fair | Suitable | Moderate | Some health stress, epicormic growth on trunk, small deadwood. | Project arborist to supervise all excavation required within the critical root zone. | Retain | |
| 74 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 77 | 30 | 9.2 | 12 | Fair | Fair | Suitable | Moderate | Some health stress, epicormic growth on trunk, small deadwood. Pitch flow lower trunk. | Project arborist to supervise all excavation required within the critical root zone. | Retain | |
| 73 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 87 | 35 | 10.4 | 13 | Fair | Fair | Suitable | Moderate | Some health stress, epicormic growth on trunk, small deadwood, corrected lean. | Project arborist to supervise all excavation required within the critical root zone. | Retain | |
| 72 | Yes | On | Yes | Douglas-fir | Pseudotsuga menziesii | 56 | 25 | 6.7 | 8 | Fair | Fair-poor | Suitable | Moderate | Corrected lean away from #73, suppressed top, some epicormic growth, pitch flow lower trunk. | Project arborist to supervise all excavation required within the critical root zone. | Retain | |
| 3561 | No | On | Yes | Bigleaf maple | Acer macrophyllum | 15,5 | 8 | 2.2 | 9 | Good | Fair | Suitable | Moderate | Mechanical injury lower trunk. | Project arborist to supervise all excavation required within the critical root zone. | Retain | |
| 66 | Yes | Off (CRD) | Yes | Douglas-fir | Pseudotsuga menziesii | 68 | 30 | 8.2 | 11 | Fair | Fair | Moderate | Trunk bends. | Project arborist to supervise all excavation required within the critical root zone. | Retain | ||
| 3562 | No | Off (CRD) | Yes | Grand fir | Abies grandis | 31 | 15 | 3.7 | 8 | Good | Good | Moderate | Project arborist to supervise all excavation required within the critical root zone. | Retain | |||
| 3563 | No | Off (CRD) | Yes | Bigleaf maple | Acer macrophyllum | 34,30,23 | 15 | 7.9 | 15 | Good | Fair | Moderate | Tridominant, 30/23cm stems lean toward subject property ~9m. | *Above ground parking proposed within the critical root zone. Project arborist to supervise all excavation required within the critical root zone. | Retain* | ||
| 67 | 3564 | Yes | Off (CRD) | Yes | Red alder | Alnus rubra | 63,22 | 15 | 9.1 | 11 | Fair-poor | Poor | Moderate | Dead top primary stem (decay), secondary stem narrowly attached. | *Above ground parking proposed within the critical root zone. Project arborist to supervise all excavation required within the critical root zone. | Retain* | |
| 3565 | No | Off (CRD) | Yes | Bigleaf maple | Acer macrophyllum | 19 | 12 | 2.3 | 8 | Good | Fair | Moderate | Canopy weighted south away from 3564. | Project arborist to supervise all excavation required within the critical root zone. | Retain | ||
| M4 | No | Municipal | Municipal | arbutus | Arbutus menziesii | 27 | 8 | 4.1 | 5 | Good | Good | Poor | Crown raised historically. Pruning stub. Next to existing driveway. ~3m from east PL. | *Parkade entrance/exit road within the critical root zone. Project arborist to supervise all excavation required within the critical root zone. | Retain* | ||
| M5 | No | Municipal | Municipal | Native willow | Salix spp. | Multiple stems | 8 | 8 | 8 | Good | Fair-poor | Moderate | Tightly packed cluster. ~2m from east PL. | Will be impacted by excavation required for the parkade entrance/exit road. | Remove |
5. SITE INFORMATION & PROJECT UNDERSTANDING
The site is a single lot in View Royal, BC, which interfaces with the Galloping Goose Trail to the South. It is our understanding that the proposal is to remove the existing residences and construct a 5-story residential building with underground parking.
Below is a general observation of the tree resource, as it appeared at the time of our site visit:
6. FIELD OBSERVATIONS
The onsite tree resource consists of a mixture of native and nonnative species growing around the perimeter of the property. The site slopes down gradually from North to South.

7. CONSTRUCTION IMPACT ASSESSMENT
7.1. RETENTION AND REMOVAL OF MUNICIPAL TREES
The following municipal trees (indicated by ID #) are located where they are possible for retention providing that the critical root zone can be adequately protected during construction. The project arborist must be onsite to supervise all excavation or fill placement required within the critical root zone (shown on the tree management plan (T1) in appendix A):
Retain and protect 4 municipal trees
- M1, M2, M3, M4.
The following municipal tree (indicated by ID #) is located where it is anticipated that it will be impacted by excavation required for the construction of the proposed entrance/exit ramp and will require removal.
Remove 1 municipal tree
- M5.
*Note that the municipality will need to provide consent, prior the removal of any trees that are located on Municipal property.
7.2. RETENTION AND REMOVAL OF ONSITE TREES
The following bylaw protected onsite trees (indicated by tag #) are located where they are possible for retention providing that their critical root zones are adequately protected during construction. The project arborist must be onsite to supervise all excavation or fill placement required within its critical root zone (shown on the tree management plan (T1) in appendix A):
Retain and protect 17 onsite trees
- 72, 73, 74, 75, 76, 77, 78, 82, 84, 88, 89, 90, 3556, 3557, 3558, 3559, 3561.
The following bylaw protected size onsite trees (indicated by tag #) are located where they will be heavily impacted by excavation required to construct the proposed underground and above parking and are proposed for removal.
Remove 27 onsite trees
- 3546, 3547, 3548, 3549, 3550, 3551, 3552, 68, 69, 70, 71, 3553, 93, 3554, 91(shared), 3555, 94, 95, 96, 97, 100, 99, 98, 83, 85, 86, 87.
*Note that trees with shared ownership will require written consent from the other owner prior to removal.
7.3. RETENTION AND REMOVAL OF PRIVATE OFFSITE TREES
The following bylaw protected private offsite trees (indicated by ID #) are located where they are possible for retention providing that their critical root zones are adequately protected during construction. The project arborist must be onsite to supervise all excavation or fill placement required within its critical root zone (shown on the tree management plan (T1) in appendix A):
Retain 10 private offsite trees and 1 offsite hedge
- OS1(hedge), OS2, 3560, 79, 80, 81, 3562, 66, 3563, 3564, 3565.
7.4. TREE REPLACEMENT
Pursuant to District of Town of View Royal bylaw No. 695, the tree replacement calculations are as follows:
| Category | Quantity of Existing Bylaw Protected Trees | # of Bylaw Protected Trees Retained | # of Trees Removed Inside of Building Envelope (exempt from replacement) | # of Trees Removed Outside of Building Envelope | Replacement Tree Ratio | Replacement Trees Required |
|---|---|---|---|---|---|---|
| Onsite (Bylaw protected size) | 44 | 17 | 22 | 5 | 2:1 | 10 |
| City owned trees | 5 | 4 | N/A | 1 | 2:1 | 2 |
| Private offsite trees | 10 trees and 1 hedge | 10 trees and 1 hedge | N/A | N/A | N/A | 0 |
| Total: | 12 |
Based on bylaw criteria, 12 trees are required to be planted in compensation for the proposed removal of 5 bylaw protected trees (outside of the building envelope). It is understood that a replanting plan will be prepared by others. If the site cannot accommodate the required quantity of replacement trees, the deficit will be provided via a cash in lieu payment by the owner.
8. IMPACT MITIGATION
Tree Protection Barrier: The areas, surrounding the trees to be retained should be isolated from the construction activity by erecting protective barrier fencing (see Appendix A for municipal barrier specifications). Where possible, the fencing should be erected at the perimeter of the critical root zone. The barrier fencing to be erected must be a minimum of 4 feet in height, of solid frame construction that is attached to wooden or metal posts. A solid board or rail must run between the posts at the top and the bottom of the fencing. This solid frame can then be covered with flexible snow fencing. The fencing must be erected prior to the start of any construction activity on site (i.e. demolition, excavation, construction), and remain in place through completion of the project. Signs should be posted around the protection zone to declare it off limits to all construction related activity. The project arborist must be consulted before this fencing is removed or moved for any purpose.
Arborist Supervision: All excavation occurring within the critical root zones of protected trees should be completed under supervision by the project arborist. Any severed or severely damaged roots must be pruned back to sound tissue to reduce wound surface area and encourage rapid compartmentalization of the wound. In particular, the following activities should be completed under the direction of the project arborist:
- All excavation required within the critical root zone of OS1 for the foundation of the proposed underground parking structure.
- All excavation required within the critical root zone of OS2, 84, 88, 89, 90, 81, 3563, 3564 for the footprint of the proposed above ground parking.
- All excavation required within the critical root zone of M4 for the footprint of the proposed entrance/exit ramp for the proposed underground parkade.
Methods to Avoid Soil Compaction: In areas where construction traffic must encroach into the critical root zones of trees to be retained, efforts must be made to reduce soil compaction where possible by displacing the weight of machinery and foot traffic. This can be achieved by one of the following methods:
- Installing a layer of hog fuel or coarse wood chips at least 20 cm in depth and maintaining it in good condition until construction is complete.
- Placing medium weight geotextile cloth over the area to be used and installing a layer of crushed rock to a depth of 15 cm over top.
- Placing two layers of 19mm plywood.
- Placing steel plates.
Demolition of the Existing Buildings: The demolition of the existing houses, driveways, and any services that must be removed or abandoned, must take the critical root zone of the trees to be retained into account. If any excavation or machine access is required within the critical root zones of trees to be retained, it must be completed under the supervision and direction of the project arborist. If temporarily removed for demolition, barrier fencing must be erected immediately after the supervised demolition.
Paved Surfaces Above Tree Roots:
If the new paved surfaces within the CRZ of tree to be retained require excavation down to bearing soil and roots are encountered in this area, this could impact their health and structural stability. If tree retention is desired, a raised and permeable paved surface should be constructed in the areas within the critical root zone of the trees. The “paved surfaces above root systems” diagram and specifications is attached.
The objective is to avoid root loss and to instead raise the paved surface and its base layer above the roots. This may result in the grade of the paved surface being raised above the existing grade (the amount depending on how close roots are to the surface and the depth of the paving material and base layers). Final grading plans should take this potential change into account. This may also result in soils which are high in organic content being left intact below the paved area.
To allow water to drain into the root systems below, we also recommend that the surface be made of a permeable material (instead of conventional asphalt or concrete) such as permeable asphalt, paving stones, or other porous paving materials and designs such as those utilized by Grasspave, Gravelpave, Grasscrete and open-grid systems.
Mulching: Mulching can be an important proactive step in maintaining the health of trees and mitigating construction related impacts and overall stress. Mulch should be made from a natural material such as wood chips or bark pieces and be 5-8cm deep. No mulch should be touching the trunk of the tree. See “methods to avoid soil compaction” if the area is to have heavy traffic.
Blasting: Care must be taken to ensure that the area of blasting does not extend beyond the necessary footprints and into the critical root zones of surrounding trees. The use of small low-concussion charges and multiple small charges designed to pre-shear the rock face will reduce fracturing, ground vibration, and overall impact on the surrounding environment. Only explosives of low phytotoxicity and techniques that minimize tree damage should be used. Provisions must be made to ensure that blasted rock and debris are stored away from the critical root zones of trees.
Scaffolding: This assessment has not included impacts from potential scaffolding including canopy clearance pruning requirements. If scaffolding is necessary and this will require clearance pruning of retained trees, the project arborist should be consulted. Depending on the extent of pruning required, the project arborist may recommend that alternatives to full scaffolding be considered such as hydraulic lifts, ladders or platforms. Methods to avoid soil compaction may also be recommended (see “Minimizing Soil Compaction” section).
Landscaping and Irrigation Systems: The planting of new trees and shrubs should not damage the roots of retained trees. The installation of any in-ground irrigation system must take into account the critical root zones of the trees to be retained. Prior to installation, we recommend the irrigation technician consult with the project arborist about the most suitable locations for the irrigation lines and how best to mitigate the impacts on the trees to be retained. This may require the project arborist supervise the excavations associated with installing the irrigation system. Excessive frequent irrigation and irrigation which wets the trunks of trees can have a detrimental impact on tree health and can lead to root and trunk decay.
Windthrow: Where forest edge trees are proposed to be removed, we recommend that trees that may experience an increase in wind exposure be re-examined, once tree clearing has taken place, to ensure that they are structurally stable, and suitable for retention as leading-edge trees.
Arborist Role: It is the responsibility of the client or his/her representative to contact the project arborist for the purpose of:
- Locating the barrier fencing
- Reviewing the report with the project foreman or site supervisor
- Locating work zones, where required
- Supervising any excavation within the critical root zones of trees to be retained
- Reviewing and advising of any pruning requirements for machine clearances
Review and site meeting: Once the project receives approval, it is important that the project arborist meet with the principals involved in the project to review the information contained herein. It is also important that the arborist meet with the site foreman or supervisor before any site clearing, tree removal, demolition, or other construction activity occurs and to confirm the locations of the tree protection barrier fencing.
9. DISCLOSURE STATEMENT
This arboricultural field review report was prepared by Talbot Mackenzie & Associates for the exclusive use of the Client and may not be reproduced, used or relied upon, in whole or in part, by a party other than the Client without the prior written consent of Talbot Mackenzie & Associates. Any unauthorized use of this report, or any part hereof, by a third party, or any reliance on or decisions to be made based on it, are at the sole risk of such third parties. Talbot Mackenzie & Associates accepts no responsibility for damages, if any, suffered by any third party as a result of decisions made or actions based on this report, in whole or in part.
Arborists are professionals who examine trees and use their training, knowledge, and experience to recommend techniques and procedures that will improve a tree’s health and structure or to mitigate associated risks. Trees are living organisms whose health and structure change and are influenced by age, continued growth, climate, weather conditions, and insect and disease pathogens. Indicators of structural weakness and disease are often hidden within the tree structure or beneath the ground. The arborist’s review is limited to a visual examination of tree health and structural condition, without excavation, probing, resistance drilling, increment coring, or aerial examination. There are inherent limitations to this type of investigation, including, without limitation, that some tree conditions will inadvertently go undetected. The arborist’s review followed the standard of care expected of arborists undertaking similar work in British Columbia under similar conditions. No warranties, either express or implied, are made as to the services provided and included in this report.
The findings and opinions expressed in this report are based on the conditions that were observed on the noted date of the field review only. The Client recognizes that passage of time, natural occurrences, and direct or indirect human intervention at or near the trees may substantially alter discovered conditions and that Talbot Mackenzie & Associates cannot report on, or accurately predict, events that may change the condition of trees after the described investigation was completed.
It is not possible for an Arborist to identify every flaw or condition that could result in failure nor can he/she guarantee that the tree will remain healthy and free of risk. The only way to eliminate tree risk entirely is to remove the entire tree. All trees retained should be monitored on a regular basis. Remedial care and mitigation measures recommended are based on the visible and detectable indicators present at the time of the examination and cannot be guaranteed to alleviate all symptoms or to mitigate all risk posed.
Immediately following land clearing, grade changes or severe weather events, all trees retained should be reviewed for any evidence of soil heaving, cracking, lifting or other indicators of root plate instability. If new information is discovered in the future during such events or other activities, Talbot Mackenzie & Associates should be requested to re-evaluate the conclusions of this report and to provide amendments as required prior to any reliance upon the information presented herein.
10. IN CLOSING
We trust that this report meets your needs. Should there be any questions regarding the information within this report, please do not hesitate to contact the undersigned.
Yours truly,
Talbot Mackenzie & Associates
Prepared by:
Noah Talbot, BA ISA Certified Arborist PN – 6822A Tree Risk Assessment Qualification Email: tmtreehelp@gmail.com
11. REFERENCES
Dunster, J.A., E.T. Smiley, N. Matheny, and S. Lily. 2017. Tree Risk Assessment Manual, International Society of Arboriculture (ISA).
Town of View Royal Bylaw No. 695.
APPENDIX A - TREE MANAGEMENT PLAN (T1)

Tree Management Plan - T1 Notes (summarized from plan):
- Project: 10 Erskine Lane, View Royal, BC
- Date: October 29, 2021
- Scale: 1:500 @ 11" x 17"
- Reference DWG: Site plan by Parsi Development Ltd.
Tree Protection Notes from Plan:
- Tree protection barrier: The areas, surrounding the trees to be retained should be isolated from the construction activity by erecting protective barrier fencing. Where possible, the fencing should be erected at the perimeter of the critical root zone. The barrier fencing to be erected must be a minimum of 1200mm in height, of solid frame construction that is attached to wooden or metal posts. A solid board or rail must run between the posts at the top and the bottom of the fencing. This solid frame can then be covered with flexible snow fencing. The fencing must be erected prior to the start of any construction activity on site (i.e. demolition, excavation, construction), and remain in place through completion of the project. Signs should be posted around the protection zone to declare it off limits to all construction related activity. The project arborist must be consulted before this fencing is removed or moved for any purpose.
- Arborist supervision: All excavation occurring within the critical root zones of protected trees must be completed under the supervision of the project arborist. Any severed or severely damaged roots must be pruned back to sound tissue to reduce wound surface area and encourage rapid compartmentalization of the wound.
- Demolition: The demolition of the existing houses, driveways, and any services that must be removed or abandoned must take the critical root zone of the trees to be retained into account. If any excavation or machine access is required within the critical root zones of trees to be retained, it must be completed under the supervision of the project arborist. If temporarily removed for demolition, barrier fencing must be erected immediately after the supervised demolition.
- Methods to avoid soil compaction: In areas where construction traffic must encroach into the critical root zones of trees to be retained, efforts must be made to reduce soil compaction where possible by displacing the weight of machinery and foot traffic. This can be achieved by one of the following methods:
- Installing a layer of hog fuel or coarse wood chips at least 20cm in depth and maintaining it in good condition until construction is complete.
- Placing medium weight geotextile cloth over the area to be used and installing a layer of crushed rock to a depth of 15cm over top.
- Placing two layers of 19mm plywood.
- Placing steel plates.
- Mulching: Mulching can be an important proactive step in maintaining the health of trees and mitigating construction related impacts and overall stress. Mulch should be made from a natural material such as wood chips or bark pieces and be 5-8cm deep. No mulch should be touching the trunk of the tree. See "methods to avoid soil compaction" if the area is to have heavy traffic.
- Pruning: We recommend that any pruning of bylaw-protected trees be performed to ANSI A300 standards and Best Management Practices.
- Paved surfaces above tree roots: Where paved areas cannot avoid encroachment within critical root zones of trees to be retained, construction techniques, such as floating permeable paving, may be required. The "paved surfaces above tree roots" detail above offers a compromise to full depth excavation (which could impact the health or structural stability of the tree). The objective is to avoid root loss and to instead raise the paved surface above the existing grade (the amount depending on how close roots are to the surface and the depth of the paving material and base layers). Final grading plans should take this potential change into account. This may also result in soils which are high in organic content being left intact below the paved area. To allow water to drain into the root systems below, we also recommend that the surface be made of a permeable material (instead of conventional asphalt or concrete) such as permeable asphalt, paving stones, or other porous paving materials and designs such as those utilized by Grasspave, Gravelpave, Grasscrete and open-grid systems.
- Blasting and rock removal: Care must be taken to ensure that the area of blasting does not extend beyond the necessary footprints and into the critical root zones of surrounding trees. The use of small low-concussion charges and multiple small charges designed to pre-shear the rock face will reduce fracturing, ground vibrations and overall impact to the surrounding environment. Only explosives of low phytotoxicity and techniques that minimize tree damage should be used. Provisions must be made to ensure that blasted rock and debris are stored away from the critical root zones of trees.
- Scaffolding: This assessment has not included impacts from potential scaffolding including canopy clearance pruning requirements. If scaffolding is necessary and this will require clearance pruning of retained trees, the project arborist should be consulted. Depending on the extent of pruning required, the project arborist may recommend that alternatives to full scaffolding be considered such as hydraulic lifts, ladders or platforms. Methods to avoid soil compaction may also be recommended (see "Minimizing Soil Compaction" section).
- Landscaping and irrigation systems: The planting of new trees and shrubs should not damage the roots of retained trees. The installation of any in-ground irrigation system must take into account the critical root zones of the trees to be retained. Prior to installation, we recommend the irrigation technician consult with the project arborist about the most suitable locations for the irrigation lines and how best to mitigate the impacts on the trees to be retained. This may require the project arborist supervise the excavations associated with installing the irrigation system. Excessive frequent irrigation and irrigation which wets the trunks of trees can have a detrimental impact on the tree health and can lead to root and trunk decay.
- Arborists role: It is the responsibility of the client or his/her representative to contact the project arborist for the purpose of:
- Locating the barrier fencing.
- Reviewing the report with the project foreman or site supervisor.
- Locating work zones and machine access corridors where required.
- Supervising excavation for any areas within the critical root zones of trees to be retained including any proposed retaining wall footings and review any proposed fill areas near trees to be retained.
APPENDIX B – HARD SURFACE ABOVE TREE ROOTS DETAIL

Hard Surface Above Tree Roots Notes:
- Maintain as large a setback between the fill encroachment and the root collar of the tree as possible.
- Review any canopy clearance pruning requirements to accommodate vehicle or pedestrian clearances (Pruning to be performed to ANSI A300 standards).
- Excavate the new footprint of the driveway or sidewalk under the supervision of the project arborist. Excavation will be limited to the removal of the existing sod layer. Excavation around root structures must be performed by hand, airspade, or hydroexcavation.
- Install a two-dimensional (such as Combigrid 3030) or Three-dimensional geogrid reinforcement.
- Install a 150mm depth layer of clear crushed gravel (no fines) using 20mm and/or 75mm diameter material or approved equivalent. *Note - the depth may be less than 150mm in some situations (dependant on grading constraints).
- Install medium weight geotextile fabric (such as Nilex 4535 or similar) over the clear crushed gravel layer to prevent fine particles of sand from infiltrating this layer.
- The bedding or base layer and new driveway or sidewalk surface can be installed directly on top of the felted filter fabric.
- Fill slopes - where possible install loose stacked boulders to reduce the footprint of the fill slopes that encroach within the critical root zone. Fill slope materials must be permeable to air and water. Do not pile fill material directly against the trunk of a tree.









