Committee of the Whole/Documents/Schedule C – 2022 Capital Projects
Appendix

Schedule C – 2022 Capital Projects

February 14, 2023Page 1402 sections

Capital project status report including infrastructure upgrades and vehicle replacements.

3 MINUTES OF PREVIOUS MEETINGS, ADOPTION OF
Total Capital Budget: $3,888,140Actual spend to date: $1,014,485Helmcken Bay pump station upgrade budget: $670,000

Report to Committee of the Whole

Re: Budget Variance and Projects Update Report to January 31, 2023 Meeting Date: February 14, 2023

Page 140

Schedule C – 2022 Capital Projects

Row Labels CC Code Est. Completion Project budget Project actual Project variance Variance %
General Government Services
Building Improvements
Council Chambers modifications 1138 Jan 2023 $50,000 $58,946 ($8,946) 18% over budget
Ergonomic workstation replacement 1226 Aug 2023 135,000 0 135,000 100% budget remaining
Information Technology
IT infrastructure hardware replacements 1044 Aug 2022 24,280 19,171 5,109 21% budget remaining
IT workstation ever-greening 1070 Dec 2022 45,000 38,626 6,374 14% budget remaining
Protective Services
Emerg Prog Equipment
Emergency Operations Centre equipment 0850 Feb 2023 18,000 12,655 5,345 30% budget remaining
Fire - Buildings
Firefighter decontamination room 1207 Oct 2022 15,500 12,350 3,150 20% budget remaining
Fire - Vehicles
Fire services vehicle replacement plan-1992 Superior E-One 1240 Jan 2024 1,120,000 3,083 1,116,917 100% budget remaining
Fire services vehicle replacement-Ladder 35 upgrade 0845 Sep 2022 47,000 42,915 4,085 9% budget remaining
Fire services vehicle replacement-Marine 34 overhaul and upgrade 1239 Jan 2022 49,000 47,763 1,237 3% budget remaining
Fire services vehicle replacement-Rescue 36 1033 Jun 2022 12,000 14,969 (2,969) 25% over budget
Police Services
RCMP building capital projects 1152 Dec 2022 30,960 32,726 (1,766) 6% over budget
Transportation Services
Equipment
Parks/PW Yard storage container 1249 Dec 2022 25,000 24,486 514 2% budget remaining
Riding mower replacement 1250 Jan 2023 25,000 0 25,000 100% budget remaining
Other Transportation Projects
Traffic patrol pullout bay 1251 Dec 2022 50,000 0 50,000 100% budget remaining
Road Projects
Island Hwy paving-Colwood interchange to Six Mile Rd 1248 Dec 2022 325,000 0 325,000 100% budget remaining
Island Hwy upgrades-Helmcken Rd to Beaumont Ave 1111 Jan 2023 100,000 0 100,000 100% budget remaining
Six Mile Rd improvements-hydro coordination 1260 Jan 2023 100,000 0 100,000 100% budget remaining
Six Mile Rd improvements-roundabout 1252 Jan 2023 15,000 7,984 7,016 47% budget remaining
Street Lighting
LED lighting upgrade 1194 Jan 2023 30,000 29,590 410 1% budget remaining
Pedestrian lighting improvements 1236 Jan 2023 99,000 101,000 (2,000) 2% over budget
Environmental Services
Collection Systems
Sewer gravity main upgrade-Fort Victoria to Pheasant Ln 1237 Dec 2022 42,000 44,478 (2,478) 6% over budget
Lift Stations
Helmcken Bay pump station upgrade 1211 Feb 2023 670,000 349,782 320,218 48% budget remaining
Packers pump station upgrade 1163 Dec 2022 35,000 15,985 19,015 54% budget remaining
SCADA/Communication
SCADA software upgrade 1019 Dec 2022 12,000 12,823 (823) 7% over budget
Parks Services
Park Development
View Royal Park development-design 1028 Apr 2022 38,500 24,624 13,876 36% budget remaining
View Royal Park development-landscaping 1258 Apr 2023 232,800 0 232,800 100% budget remaining
Watkiss Way Community Park site preparation 1241 Dec 2022 150,000 83,814 66,186 44% budget remaining
Park Improvements
Development of road ends-Polly Place 1243 Dec 2022 40,000 0 40,000 100% budget remaining
Parks signage and wayfinding 1175 Dec 2022 35,000 0 35,000 100% budget remaining
Playground replacement program-Knollwood Park playground 1199 Feb 2023 100,000 0 100,000 100% budget remaining
Portage Park toilets 1216 Dec 2022 5,500 0 5,500 100% budget remaining
View Royal Park swing set replacement 1220 Sep 2022 35,000 36,716 (1,716) 5% over budget
Park Vehicles
Parks vehicle replacement plan-1996 Kubota replacement 1067 Jan 2023 81,600 0 81,600 100% budget remaining
Parks vehicle replacement plan-2006 Ford F350 replacement 1253 Jan 2023 85,000 0 85,000 100% budget remaining
Small trailer with cargo rack 1221 Feb 2023 10,000 0 10,000 100% budget remaining
Grand Total $3,888,140 $1,014,485 $2,873,655 74% budget remaining