Budget Variance and Project Schedules (A, B, and C)

September 12, 2023Pages 79–813 sections

Consolidated budget variance tables and project status lists for non-core and capital works.

1 CALL TO ORDER- Mayor Tobias called the meeting to order at 3:30 p.m.
Total Capital project budget: $6,663,270Actual Capital expenditure YTD: $605,294Six Mile Rd roundabout budget: $2,385,000

Schedule A – 2023 Consolidated Budget Variance

Revenue

Category 2023 YTD 2023 Total Budget Variance Variance % Prior YTD Prior Year Total Budget
Taxation $ 11,316,271 $ 11,318,193 $ 1,922 0% under budget $10,207,973 $ 10,208,319
User fees 703,338 3,065,159 2,361,821 77% under budget 640,245 2,979,060
Sales of services 1,142,023 918,800 (223,223) 24% over budget 1,139,612 846,695
Penalties and fines 77,443 76,000 (1,443) 2% over budget 100,420 60,000
Investment income 576,795 115,000 (461,795) 402% over budget (112,162) 115,000
Other revenue 236,119 298,950 62,831 21% under budget 1,161,299 247,635
Government grants and transfers 6,397,616 8,079,172 1,681,556 21% under budget 2,398,907 2,666,440
Contributions from developers and others 176,250 1,059,090 882,840 83% under budget 1,379,540 95,000
Development cost charges - 681,255 681,255 100% under budget - 496,503
Transfers from reserves - 1,736,820 1,736,820 100% under budget - 1,346,427
Transfers from reserve accounts - 5,702,556 5,702,556 100% under budget - 3,653,336
Transfers from accumulated surplus - 266,150 266,150 100% under budget - 450,538
Transfers from equity in capital assets - 3,200,270 3,200,270 100% under budget 77,418 3,143,400
Internal cost allocations 544,295 544,295 - 0% under budget - 533,626
Revenue Total $ 21,170,150 $ 37,061,710 $ 15,891,560 43% under budget $16,993,253 $ 26,841,979

Expense

Category 2023 YTD 2023 Total Budget Variance Variance % Prior YTD Prior Year Total Budget
General government services $ 1,834,390 $ 3,574,654 $ 1,740,264 49% budget remaining $ 1,933,638 $ 2,917,318
Protective services 2,512,333 6,035,421 3,523,088 58% budget remaining 3,340,000 6,322,713
Transportation services 1,381,611 6,330,553 4,948,942 78% budget remaining 2,524,664 3,891,755
Environmental health services 2,225,718 3,456,314 1,230,596 36% budget remaining 2,134,871 3,169,444
Development services 363,835 753,608 389,773 52% budget remaining 442,659 623,439
Parks services 628,471 2,321,212 1,692,741 73% budget remaining 638,167 1,699,218
Recreation and culture services 1,024,082 1,372,072 347,990 25% budget remaining 1,051,168 1,386,083
Interest on debt 108,556 217,112 108,556 50% budget remaining 217,112 217,112
Principal payment on debt 184,364 315,615 131,251 42% budget remaining 315,615 315,615
Amortization - 3,200,270 3,200,270 100% budget remaining 77,418 3,143,400
Internal cost allocations 544,295 544,295 - 0% budget remaining - 533,626
Transfers to reserves 5,528,250 6,392,000 863,750 14% budget remaining 1,148,000 606,300
Transfers to reserve accounts 1,349,805 2,548,584 1,198,779 47% budget remaining 1,769,388 2,015,956
Expense Total 17,685,711 37,061,710 19,375,999 52% budget remaining 15,592,700 26,841,979
Grand Total $3,484,439 $0 ($3,484,439) $1,400,553 $0
Page 79–81

Schedule B – 2023 Non-core Projects

Project CC Code Est. Completion Project budget Project actual Project variance Variance %
General Government Services
Admin Buildings
Energy audit - Town Hall 510-04 Dec 2023 $ 8,310 $ 3,063 $ 5,248 63% budget remaining
Administration
Accessible BC Act implementation 140-15 Dec 2023 5,100 - 5,100 100% budget remaining
Truth and Reconciliation awareness 140-11 Dec 2023 10,000 - 10,000 100% budget remaining
Finance
Strategic Asset Management Plan 150-03 Dec 2023 20,000 - 20,000 100% budget remaining
Sustainable Infrastructure Replacement Plan 150-02 Dec 2023 20,300 - 20,300 100% budget remaining
Information Technology
Cyber security policies and process 160-11 Nov 2023 10,000 - 10,000 100% budget remaining
Information security strategic plan 160-10 Oct 2023 8,500 - 8,500 100% budget remaining
Information Technology Coordinator 160-14 Jul 2023 46,725 - 46,725 100% budget remaining
IT asset inventory solution 160-09 Dec 2023 8,500 - 8,500 100% budget remaining
IT disaster recovery plan 160-06 Jan 2023 10,000 2,846 7,154 72% budget remaining
Multi-factor authentication 160-08 Dec 2023 10,000 3,242 6,758 68% budget remaining
Public Relations
Volunteer community improvement program 120-05 Dec 2023 2,500 - 2,500 100% budget remaining
Protective Services
Emergency Program
EOC training and education 230-02 May 2023 5,500 3,000 2,500 45% budget remaining
Extreme heat risk reduction study 230-06 Oct 2023 30,000 - 30,000 100% budget remaining
Fire Building
Energy audit - Public Safety Building 510-29 Dec 2023 5,550 2,063 3,488 63% budget remaining
Fire General
Community wildfire protection plan update 210-03 Dec 2023 33,000 - 33,000 100% budget remaining
Wildfire fuel management 210-04 Dec 2023 25,000 - 25,000 100% budget remaining
Fire Volunteers
Volunteer firefighter qualifications compensation 211-03 May 2023 24,000 - 24,000 100% budget remaining
Transportation Services
Traffic Calming
Stormont Road traffic calming 323-01 Dec 2023 8,000 - 8,000 100% budget remaining
Transportation-General
Active Transportation Network Plan 310-08 May 2023 57,428 48,404 9,024 16% budget remaining
Development Services
Planning and Development Services
Coastal Adaptation Plan 510-28 Dec 2023 60,000 - 60,000 100% budget remaining
Community engagement strategy 510-22 Dec 2023 80,000 - 80,000 100% budget remaining
Official Community Plan review 510-02 Dec 2023 41,000 5,502 35,498 87% budget remaining
Off-street parking review 510-32 Dec 2023 35,000 - 35,000 100% budget remaining
Parks Services
Parks, Rec & Culture-General
Public art acquisition-mural 710-01 Dec 2023 35,000 10,000 25,000 71% budget remaining
Urban forestry strategy 310-14 Dec 2023 82,500 - 82,500 100% budget remaining
Grand Total $ 681,913 $ 78,120 $603,793 89% budget remaining
Page 79–81

Schedule C – 2023 Capital Projects

Project CC Code Est. Completion Project budget Project actual Project variance Variance %
General Government Services
Administration
Records information management system 1038 Dec 2023 $ 168,000 $ 1,050 $ 166,950 99% budget remaining
Building Improvements
Council Chambers modifications 1138 Jan 2023 34,200 38,353 (4,153) 12% over budget
Ergonomic workstation replacement 1226 Dec 2023 145,000 - 145,000 100% budget remaining
Town Hall HVAC replacements 1272 Aug 2023 110,000 - 110,000 100% budget remaining
Information Technology
IT infrastructure hardware replacements 1044 Oct 2023 96,700 12,306 84,394 87% budget remaining
IT workstation ever-greening 1070 Oct 2023 42,500 11,284 31,216 73% budget remaining
Phone service replacement 1037 Oct 2023 35,000 - 35,000 100% budget remaining
Protective Services
Emerg Prog Equipment
Emergency Operations Centre equipment 0850 Apr 2023 5,000 4,776 224 4% budget remaining
Fire - Buildings
Fire training ground improvements 1149 Dec 2023 50,000 13,321 36,679 73% budget remaining
Public Safety Building envelope repairs 1032 Oct 2023 100,000 - 100,000 100% budget remaining
Public Safety Building landscaping 1208 Jul 2023 35,000 - 35,000 100% budget remaining
Public Safety Building security gate 1264 Sep 2023 25,000 - 25,000 100% budget remaining
Fire - Furniture and Equipment
Firefighting hose replacement 1150 Jun 2023 25,000 - 25,000 100% budget remaining
SCBA cylinder and battery replacements 1101 Jun 2023 35,000 26,232 8,768 25% budget remaining
Police Services
RCMP building capital projects 1152 Dec 2023 20,000 4,705 15,295 76% budget remaining
RCMP building design validation 1266 Dec 2023 186,720 - 186,720 100% budget remaining
Transportation Services
Bus Shelters
Bus shelter installation program 0058 Dec 2023 45,000 - 45,000 100% budget remaining
Other Transportation Projects
Intersection safety improvements at trail crossings 1265 Dec 2023 20,000 - 20,000 100% budget remaining
Road Projects
Intersection improvements-Helmcken Rd at Watkiss Way 1085 Dec 2023 60,000 - 60,000 100% budget remaining
Island Hwy upgrades-Helmcken Rd to Beaumont Ave 1111 Dec 2023 100,000 - 100,000 100% budget remaining
Six Mile Rd hydro works 1260 Dec 2023 300,000 1,000 299,000 100% budget remaining
Six Mile Rd roundabout 1252 Dec 2023 2,385,000 51,562 2,333,438 98% budget remaining
Six Mile Road cross-section review 1168 Dec 2023 5,000 5,273 (273) 5% over budget
Sidewalks
Atkins Road sidewalk-Anya Court to Langford border 1234 Dec 2023 30,000 - 30,000 100% budget remaining
Curb & sidewalk replacement-Eagle Creek Village to Helmcken/Burnside 1189 Dec 2023 100,000 2,650 97,350 97% budget remaining
Jedburgh Rd sidewalk 1204 Dec 2023 28,000 - 28,000 100% budget remaining
Signals
Traffic signal upgrades-collector road intersections 1270 Dec 2023 16,700 - 16,700 100% budget remaining
Traffic signal upgrades-Island Hwy 1261 Dec 2023 68,000 - 68,000 100% budget remaining
Street Lighting
LED lighting upgrade 1194 Dec 2023 30,000 - 30,000 100% budget remaining
Pedestrian lighting improvements 1236 Dec 2023 22,700 - 22,700 100% budget remaining
St. Giles Street lighting improvements 1269 Dec 2023 20,000 - 20,000 100% budget remaining
Environmental Services
Lift Stations
Helmcken Bay pump station upgrade 1211 Apr 2023 301,500 301,497 3 0% budget remaining
Packers pump station upgrade 1163 Dec 2023 670,000 1,978 668,022 100% budget remaining
Parks Services
Park Development
View Royal Park-design 1028 Dec 2023 13,875 9,612 4,263 31% budget remaining
View Royal Park-fencing & garbage receptacles 1268 Dec 2023 78,700 - 78,700 100% budget remaining
View Royal Park-saltwater marsh/wetland 1267 Dec 2023 272,625 - 272,625 100% budget remaining
View Royal Park-soft landscaping 1258 Dec 2023 232,800 - 232,800 100% budget remaining
Watkiss Way Community Park development 1241 Dec 2023 15,000 - 15,000 100% budget remaining
Park Improvements
Centennial Park diamond #4 fencing improvement 1218 Dec 2023 40,250 - 40,250 100% budget remaining
Chancellor Park playground replacement 1254 Dec 2023 300,000 - 300,000 100% budget remaining
Knollwood Park playground replacement 1199 Dec 2023 100,000 - 100,000 100% budget remaining
Stillwater Road waterfront access 1245 Dec 2023 40,000 - 40,000 100% budget remaining
Thomas Road waterfront access 1244 Dec 2023 40,000 1,966 38,034 95% budget remaining
Park Vehicles
1996 Kubota replacement 1067 Apr 2023 33,000 32,779 221 1% budget remaining
2006 Ford F350 replacement 1253 May 2023 62,000 60,922 1,078 2% budget remaining
2007 Chev 1-ton pickup replacement 1271 Dec 2023 85,000 - 85,000 100% budget remaining
Riding mower replacement 1250 Apr 2023 25,000 24,028 972 4% budget remaining
Small trailer with cargo rack 1221 Dec 2023 10,000 - 10,000 100% budget remaining
Grand Total $6,663,270 $ 605,294 $6,057,976 91% budget remaining