Attachment 2: Conceptual Frontage and Servicing
Engineering drawings showing the proposed road frontage improvements and utility servicing for the development at 339 Island Highway.
339 Island Highway, View Royal BC - Conceptual Frontage Works




Notes
- For building information, see drawings by KWL architects.
- For landscape design information, see landscape drawings.
- For tree information including critical root zones, see report by Talbot Urban Forestry Consultants.
- For legal survey information, see drawings by McElhanney Ltd.
- For traffic impact assessment, see report by Watt Consulting Group.
- All existing on-site buildings, driveways, parking lots, retaining walls, etc. to be removed and disposed off-site (not shown).
- All existing property information was produced from a combination of field survey and record information provided by the Town of View Royal. All information to be confirmed in the field prior to construction (including installing a bench mark).
- Onsite bike parking, etc. not shown for clarity (see architect and landscape drawings).
Sight Line Note
Sight lines at Prince Robert Drive / Island Highway intersection and required extents of vegetation clearing to be confirmed during detailed design.
Map Annotations
- New traffic signal at the intersection of Island Highway and Prince Robert Drive to be determined during detailed design.
- Eradicate existing pavement markings on Island Highway within limits of construction (TYP). Extents to be confirmed during detailed design.
- Sawcut location to be confirmed during detailed design.
- Remove existing curb, extent to be confirmed during detailed design.
- Vegetation clearing to property line for sight line requirements. See sight line note.
- Prince Robert Drive future centerline alignment concept.
- Relocate existing bus stop, bus shelter and pullouts to BC Transit standards. Location to be confirmed during detailed design.
- Relocate existing catch basins as required to new gutter line. Locations, spacing and lead connections to be confirmed during detailed design.
- Remove existing curb.
- Lane taper to existing to be confirmed during detailed design.
- Island Highway future centerline alignment concept.
- Tie-in to existing curb and gutter and sidewalk. Tie-in locations to be confirmed during detailed design.
- Approximate extents of building at grade (TYP). See architectural.
- Approximate extents of parkade (TYP). See architectural.
- Project Boundary.
- Road Dedication.
Drawing Details
- Project: 339 Island Highway, View Royal BC
- Title: Conceptual Frontage Works
- Date: 2023-07-10
- Scale: Horiz: 1:300; Vert: NTS
- Project No.: 22-149
- Drawing No.: 22-149-CSP-2
339 Island Highway, View Royal BC - Conceptual Servicing Plan
Sheet Notes
| No. | Description |
|---|---|
| 1 | Existing water service to be capped and abandoned by CRD forces at developer's expense. |
| 2 | Remove existing fire hydrant and valve and cap existing tee by CRD forces at developer's expense. |
| 3 | New fire hydrant by CRD forces at developer's expense. |
| 4 | New water service c/w meter at property line by CRD forces at developer's expense. Size to be confirmed during detailed design. |
| 5 | Existing connection to CRD water main #2 to be capped and abandoned by CRD forces at developer's expense. |
| 6 | Connection to existing water main by CRD forces at developer's expense. |
| 7 | New 150ø domestic water service connection c/w 100ø water meter and 150ø fire water service connection c/w check valve by CRD forces at developer's expense. Sizes to be confirmed during detailed design. |
| 8 | Cap and abandon existing sanitary service at property line. |
| 9 | New 200ø sanitary service connection c/w inspection chamber at property line and 1200ø manhole at existing main by Town of View Royal forces at developer's expense. Sizes to be confirmed during detailed design. |
| 10 | New 200ø storm service connection c/w inspection chamber at property line and 1200ø manhole at existing main by Town of View Royal forces at developer's expense. Sizes to be confirmed during detailed design. |
| 11 | Raise or replace existing fire hydrant by CRD forces at developer's expense. |
Storm Water Management Note
Storm water storage volume required = 35 cu. m. Storm water storage will be provided via on site rain gardens (see landscape drawings). Stormwater storage volume to be confirmed during detailed design.
Notes
- For building information, see drawings by KWL architects.
- For landscape design information, see landscape drawings.
- For tree information including critical root zones, see report by Talbot Urban Forestry Consultants.
- For legal survey information, see drawings by McElhanney Ltd.
- All existing on-site buildings, driveways, parking lots, retaining walls, etc. to be removed and disposed off-site (not shown).
- All existing property information was produced from a combination of field survey and record information provided by the Town of View Royal. All information to be confirmed in the field prior to construction (including installing a bench mark).
- Onsite bike parking, etc. not shown for clarity (see architect and landscape drawings).
Map Annotations
- Replace existing sanitary main if required to be determined during detailed design.
- Caution: Gas Crossing.
- For frontage works, see DWG. 22-149-CSP-2.
- New 200ø D.I. water main. Alignment location to be confirmed during detailed design.
- Proposed West Building (See Architectural).
- Proposed East Building (See Architectural).
- Approximate extents of building at grade (TYP). See architectural.
- Approximate extents of parkade (TYP). See architectural.
- Project Boundary.
- Remove existing drain and appurtenances (approx. 50m long). To be confirmed during detailed design.
- Proposed Trees, TYP (See Landscape).
- Existing Trees, TYP (See Arborist Report).
Drawing Details
- Project: 339 Island Highway, View Royal BC
- Title: Conceptual Servicing Plan
- Date: 2023-07-10
- Scale: Horiz: 1:250; Vert: NTS
- Project No.: 22-149
- Drawing No.: 22-149-CSP-1
Document Images
(230)
Fragment showing building edge and adjacent sidewalk

Fragment showing green-shaded boulevard landscaping

Fragment of landscaped area along the property frontage

Fragment of green-shaded area near the site entrance







































































































Detail of the new 200ø D.I. water main alignment

Detail of the sanitary service connection showing the inspection chamber