Committee of the Whole/Documents/Schedule B – 2022 Non-core Projects
Appendix

Schedule B – 2022 Non-core Projects

January 10, 2023Page 421 section

A tracking table for 2022 non-core projects showing estimated completion dates and budget variances.

3 MINUTES OF PREVIOUS MEETINGS, ADOPTION OF
Total non-core project budget: $716,340Total actual costs: $336,536

Schedule B – 2022 Non-core Projects

Report to Committee of the Whole

Re: Budget Variance and Projects Update Report to December 31 Meeting Date: January 10, 2023

Row Labels CC Code Est. Completion Project budget Project actual Project variance Variance %
General Government Services
Admin Buildings
Energy audit of municipal buildings-Town Hall 510-04 Dec 2022 $15,000 $0 $15,000 100% budget remaining
Administration
Truth and Reconciliation awareness 140-11 Dec 2022 10,000 0 10,000 100% budget remaining
Finance
Long-term financial plan and sustainability review 150-02 Sep 2022 45,500 44,188 1,313 3% budget remaining
Information Technology
Digital signature certificate service 160-05 Oct 2023 5,000 0 5,000 100% budget remaining
Information security mgmt system-business continuity 160-07 Dec 2023 15,000 0 15,000 100% budget remaining
Information security mgmt system-IT asset inventory so 160-09 Dec 2023 5,000 0 5,000 100% budget remaining
Information security mgmt system-IT disaster recovery 160-06 Jan 2023 20,000 2,000 18,000 90% budget remaining
Information security mgmt system-multi-factor authent 160-08 Dec 2022 10,000 0 10,000 100% budget remaining
Public Relations
Online citizen budget engagement 120-03 Apr 2022 6,000 6,322 (322) 5% over budget
Protective Services
Emergency Program
Emergency Response and Recovery Plan 230-04 Mar 2024 20,000 0 20,000 100% budget remaining
EOC supplies 230-02 Mar 2023 7,000 1,335 5,665 81% budget remaining
Hazard risk vulnerability assessment 230-03 Mar 2023 15,000 0 15,000 100% budget remaining
Fire Building
Energy audit of municipal buildings-PSB 510-29 Dec 2022 15,000 0 15,000 100% budget remaining
Public Safety Building public art 215-02 May 2022 15,000 9,134 5,866 39% budget remaining
Fire General
Community Wildfire Protection Plan 210-03 Dec 2022 33,000 0 33,000 100% budget remaining
Protective Inspections
Energy Step Code implementation 241-01 Dec 2022 12,000 19,137 (7,137) 59% over budget
RCMP
Additional RCMP members* 800-06 Dec 2022 23,200 0 23,200 100% budget remaining
Transportation Services
Transportation-General
Active Transportation Plan 310-08 Dec 2022 145,000 74,759 70,241 48% budget remaining
Development Services
Planning and Development Services
Community Climate Action Plan 510-27 May 2022 25,000 12,091 12,909 52% budget remaining
OCP review 510-02 Jul 2022 94,640 89,719 4,921 5% budget remaining
Parks Services
Centennial Park
Helmcken Centennial Park Master Plan 722-03 Dec 2022 55,000 0 55,000 100% budget remaining
Park Trees
Replacement tree water bags 730-02 Dec 2022 5,000 4,713 288 6% budget remaining
Resident tree planting program 730-01 Dec 2022 10,000 0 10,000 100% budget remaining
Parks, Rec & Culture-General
Public art acquisition 710-01 Jul 2023 35,000 5,661 29,340 84% budget remaining
Small Parks & Greenspaces
Greater Victoria Green Team program expansion 720-02 Dec 2022 7,000 0 7,000 100% budget remaining
Recreation & Culture Services
Recreation Services
WSPR skatepark contribution 750-01 Oct 2022 68,000 67,480 520 1% budget remaining
Grand Total $716,340 $336,536 $379,804 53% budget remaining

* Personnel costs are not individually tracked in the financial system; actual costs will be reported as $0 for the purposes of this report

Page 42