Committee of the Whole/Documents/Schedule C – 2022 Capital Projects
Appendix

Schedule C – 2022 Capital Projects

January 10, 2023Page 432 sections

A detailed tracking table for 2022 capital projects, including building improvements, fire vehicles, and road projects.

3 MINUTES OF PREVIOUS MEETINGS, ADOPTION OF
Total capital project budget: $3,888,140Total actual costs: $612,675

Report to Committee of the Whole

Re: Budget Variance and Projects Update Report to December 31

Meeting Date: January 10, 2023

Page 43

Schedule C – 2022 Capital Projects

Project Category / Description CC Code Est. Completion Project budget Project actual Project variance Variance %
General Government Services
Building Improvements
Council Chambers modifications 1138 Jan 2023 $50,000 $58,487 ($8,487) 17% over budget
Ergonomic workstation replacement 1226 Aug 2023 135,000 0 135,000 100% budget remaining
Information Technology
IT infrastructure hardware replacements 1044 Aug 2022 24,280 19,171 5,109 21% budget remaining
IT workstation ever-greening 1070 Dec 2022 45,000 25,445 19,555 43% budget remaining
Protective Services
Emerg Prog Equipment
Emergency Operations Centre equipment 0850 Feb 2023 18,000 0 18,000 100% budget remaining
Fire - Buildings
Firefighter decontamination room 1207 Oct 2022 15,500 12,350 3,150 20% budget remaining
Fire - Vehicles
Fire services vehicle replacement plan-1992 Superior E-One 1240 Jan 2024 1,120,000 0 1,120,000 100% budget remaining
Fire services vehicle replacement-Ladder 35 upgrade 0845 Sep 2022 47,000 42,915 4,085 9% budget remaining
Fire services vehicle replacement-Marine 34 overhaul and upgrade 1239 Jan 2022 49,000 47,763 1,237 3% budget remaining
Fire services vehicle replacement-Rescue 36 1033 Jun 2022 12,000 14,969 (2,969) 25% over budget
Police Services
RCMP building capital projects 1152 Dec 2022 30,960 8,577 22,383 72% budget remaining
Transportation Services
Equipment
Parks/PW Yard storage container 1249 Dec 2022 25,000 22,420 2,580 10% budget remaining
Riding mower replacement 1250 Jan 2023 25,000 0 25,000 100% budget remaining
Other Transportation Projects
Traffic patrol pullout bay 1251 Dec 2022 50,000 0 50,000 100% budget remaining
Road Projects
Island Hwy paving-Colwood interchange to Six Mile Rd 1248 Dec 2022 325,000 0 325,000 100% budget remaining
Island Hwy upgrades-Helmcken Rd to Beaumont Ave 1111 Jan 2023 100,000 0 100,000 100% budget remaining
Six Mile Rd improvements-hydro coordination 1260 Jan 2023 100,000 0 100,000 100% budget remaining
Six Mile Rd improvements-roundabout 1252 Jan 2023 15,000 3,444 11,556 77% budget remaining
Street Lighting
LED lighting upgrade 1194 Jan 2023 30,000 0 30,000 100% budget remaining
Pedestrian lighting improvements 1236 Jan 2023 99,000 1,425 97,575 99% budget remaining
Environmental Services
Collection Systems
Sewer gravity main upgrade-Fort Victoria to Pheasant Ln 1237 Dec 2022 42,000 31,796 10,204 24% budget remaining
Lift Stations
Helmcken Bay pump station upgrade 1211 Feb 2023 670,000 200,828 469,172 70% budget remaining
Packers pump station upgrade 1163 Dec 2022 35,000 9,169 25,831 74% budget remaining
SCADA/Communication
SCADA software upgrade 1019 Dec 2022 12,000 12,823 (823) 7% over budget
Parks Services
Park Development
View Royal Park development-design 1028 Apr 2022 38,500 24,624 13,876 36% budget remaining
View Royal Park development-landscaping 1258 Apr 2023 232,800 0 232,800 100% budget remaining
Watkiss Way Community Park site preparation 1241 Dec 2022 150,000 15,868 134,132 89% budget remaining
Park Improvements
Development of road ends-Polly Place 1243 Dec 2022 40,000 15,805 24,195 60% budget remaining
Parks signage and wayfinding 1175 Dec 2022 35,000 0 35,000 100% budget remaining
Playground replacement program-Knollwood Park playground 1199 Feb 2023 100,000 0 100,000 100% budget remaining
Portage Park toilets 1216 Dec 2022 5,500 8,081 (2,581) 47% over budget
View Royal Park swing set replacement 1220 Sep 2022 35,000 36,716 (1,716) 5% over budget
Park Vehicles
Parks vehicle replacement plan-1996 Kubota replacement 1067 Jan 2023 81,600 0 81,600 100% budget remaining
Parks vehicle replacement plan-2006 Ford F350 replacement 1253 Jan 2023 85,000 0 85,000 100% budget remaining
Small trailer with cargo rack 1221 Feb 2023 10,000 0 10,000 100% budget remaining
Grand Total $3,888,140 $ 612,675 $ 3,275,465 84% budget remaining
Page 43