Committee of the Whole/Documents/Tree Protection inventory Table and Fencing Detail
Appendix

Tree Protection inventory Table and Fencing Detail

May 11, 2021Page 1822 sections

A detailed tree inventory table and diagram for the 221 Atkins Road property, including tree management recommendations and fencing specifications.

2. APPROVAL OF AGENDA (motion to approve)
221 Atkins RoadProject Arborist: Gye & AssociatesProject No. 20-005

Tree Management Plan

Project: 221 Atkins Rd, View Royal, BC Title: Tree Management Plan for Sub-division & Site Servicing Project No: 20-005 Date: April 27, 2020 Scale: 1:250 Drawn By: JG Sheet No: T-1 Company: Gye & Associates Ltd.

Tree Protection Fencing Detail

Modular steel panel fencing is recommended in order to reduce land-fill waste post-construction. Fencing panels shall be secured to the ground with rebar wired to panel frame.

16 x 24” all-weather signage will be attached with the following wording:

  • For protected trees: DO NOT ENTER – Tree Protection Zone
  • For replacement/landscape tree planting sites: DO NOT ENTER – Future Tree Planting Zone

In cases where steel-panel fencing is not practical or available, fencing shall be constructed with a wooden 2x4 frame (side, top and bottom rails) and back-bracing supports as required to ensure robust placement. Snow-fencing will then be affixed to the frame using battens, zip-ties, staples, wire or nails.

Photo of modular steel panel tree protection fencing installed on-site
Photo of modular steel panel tree protection fencing installed on-site
Close-up photo showing the base of the tree protection fencing secured to the ground with rebar
Close-up photo showing the base of the tree protection fencing secured to the ground with rebar

TREE PROTECTION FENCING SIGNAGE

(Signs shall be 16x24” and made to sustain all weather conditions)

DO NOT ENTER Tree Protection Zone [Diagram showing three icons: NO DUMPING, NO STORAGE, and NO DIGGING] Project Arborist: Gye and Associates Ltd, 250.883.4533


TREE INVENTORY TABLE

G&A Tree ID Common Name DBH (cm) PRZ Radius (m) Crown Radius (m) Health Structural Condition Bylaw Tree? Action Notes
295 Big-leaf maple 57 7 9w Good Good Yes Retain & Protect
296 Big-leaf maple 56 7 9w Good Fair Yes Retain & Protect
297 Big-leaf maple 74 9 9w Good Good Yes Retain & Protect
298 Big-leaf maple 54 7 12sw Good Fair Yes Retain & Protect
299 Douglas-fir 22 3 3 Fair Poor Yes Remove
300 Douglas-fir 38 5 3 Poor Poor Yes Remove
301 Douglas-fir 52 6 3 Poor Poor Yes Remove
302 Grand fir 27 4 3 Fair Fair Yes Remove
303 Douglas-fir 21 3 3 Poor Poor Yes Remove
304 Douglas-fir 94 12 11 Good Fair Yes Retain & Protect
305 Grand fir 20 3 3 Poor Fair Yes Remove
306 Grand fir 35 4 3 Poor Poor Yes Remove
307 Black locust 45 4 10w Good Poor Yes Remove
308 Grand fir 50 7 5 Fair Poor-Fair Yes Retain & Protect
309 Grand fir 55 6 6 Fair Poor-Fair Yes Remove
310 Douglas-fir 50 6 6s Good Good Yes Retain & Protect
311 Lawson cypress 30 3 4 Good Good Yes Retain & Protect
312 Lawson cypress 51 5 12s Good Good Yes Retain & Protect
313 Lawson cypress 53 5 6 Good Fair Yes Retain & Protect
314 Western Red cedar 58 13 8nw Fair Poor-Fair Yes Retain & Protect
315 Western Red cedar 115 17 9 Fair Good Yes Retain & Protect
316 Big-leaf maple 78 10 12 Good Fair Yes Retain & Protect Anticipated removal for lot buildout
317 English holly 52 6 4 Good Fair Yes Retain & Protect Anticipated removal for lot buildout
318 Big-leaf maple 57 7 8 Good Fair Yes Retain & Protect Anticipated removal for lot buildout
319 Big-leaf maple 52 7 7 Good Fair Yes Retain & Protect
320 Big-leaf maple 52 7 6 Good Fair Yes Retain & Protect
321 Big-leaf maple 31 4 3 Fair Poor Yes Retain & Protect
322 Big-leaf maple 45 5 1 Fair Fair Yes Retain & Protect
323 Pacific dogwood 47 6 5sw Good Fair Yes Retain & Protect
324 Big-leaf maple 56 7 10 Good Good Yes Retain & Protect
325 Western Red cedar 65 8 7sw Good Good Yes Retain & Protect
326 Western Red cedar 70 9 14 Good Good Yes Retain & Protect
327 Western Red cedar 75 11 7se Fair Fair-Good Yes Retain & Protect
328 Big-leaf maple 80 13 9 Poor Fair-Good Yes Retain & Protect
328(u) Big-leaf maple 55 7 9 Fair-Good Fair-Good Yes Retain & Protect
329 Big-leaf maple 70 9 9 Good Good Yes Retain & Protect
330 Western Red cedar 50 7 5 Good Good Yes Retain & Protect
331 Western Red cedar 100 14 8 Fair Fair Yes Retain & Protect Anticipated removal for lot buildout
332 Western Red cedar 110 15 6s Fair Fair Yes Retain & Protect Anticipated removal for lot buildout
333 Grand fir 56 10 4 Fair Fair Yes Retain & Protect Anticipated removal for lot buildout
334 Douglas-fir 56 10 10 Fair Fair Yes Retain & Protect Anticipated removal for lot buildout
335 Douglas-fir 50 7 6 Good Fair Yes Retain & Protect Anticipated removal for lot buildout
336 Douglas-fir 140 19 10 Fair Fair Yes Retain & Protect Anticipated removal for lot buildout
337 Western Red cedar 47 7 5sw Fair Poor-Fair Yes Retain & Protect Anticipated removal for lot buildout
338 Western Red cedar 74 10 11s Good Good Yes Retain & Protect Anticipated removal for lot buildout
339 Western Red cedar 27 4 4 Fair Fair Yes Retain & Protect Anticipated removal for lot buildout
340 Western Red cedar 74 10 10 Fair Fair Yes Retain & Protect
341 Douglas-fir 85 12 9sw Fair Fair Yes Retain & Protect
342 Douglas-fir 85 12 10 Good Good Yes Retain & Protect
343 Douglas-fir 125 16 10n Good Good Yes Retain & Protect
344 Douglas-fir 40 5 4 Good Good Yes Retain & Protect

Note: Tree tag numbers in bold italics have been approximately located on plan by arborist. Trees along edge of creek beyond toe of slope are not shown on this plan.


CATEGORY - # OF TREES

CATEGORY # OF TREES
Total number of trees indicated on Tree Management Plan 51
(On-site Bylaw-Protected Trees) 21
(Boulevard Trees) 24
(Adjacent Off-site Trees) 6
(Boundary Trees) 0
On-site Tree Removals for Site Servicing 10
Boulevard Tree Removals for Site Servicing 0
Anticipated On-site Tree Removals for Lot Build-out 11
Replacement Trees Required by Tree Bylaw 0

TREE PRESERVATION MEASURES

Page 182
  1. Pre-construction meeting: Before demolition or site servicing begins, the contractor will meet with the arborist to review the placement of fencing and other tree protection measures which include:
    • a) The Project Arborist shall clearly mark the boundaries of all TPAs to be fenced and protected.
    • b) Access routes and areas for parking and materials storage will be identified with the contractor.
  2. Tree Fencing:
    • a) Protective tree fencing shall be installed to the Town of View Royal standards at the locations indicated on this drawing prior to demolition or site servicing permits being issued (see fencing detail on plan).
    • b) Tree protection fencing and armouring shall be maintained in good condition throughout construction and may only be moved under arborist supervision. Any breach in tree fencing must be reviewed by the project arborist for approval.
  3. Tree Management Plan posting:
    • a) At least one (1) large format copy of this tree plan shall be posted in plain sight on the site office.
    • b) The general contractor shall ensure that all relevant sub-trades are aware of the location and intent of TPAs.
  4. Site servicing and excavations: The project arborist shall be present to oversee excavations for site servicing and/or any other site grading or blasting within, or adjacent to, the tree protection areas (TPAs).
  5. Root & branch pruning and protection:
    • a) Any tree roots or branches damaged during site work shall be pruned back to undamaged tissue by the arborist.
    • b) The vertical face of excavated cuts adjacent to the TPAs shall be lined with heavy plastic or geotextile fabric by the project arborist to prevent soil desiccation and erosion.
  6. Mulch & irrigation: Trees impacted by excavation for site servicing shall have the TPAs mulched with 3-4" of wood chips or composted bark mulch and receive adequate irrigation every two weeks during the dry summer period (May to mid-October) to a depth of 12" within the TPAs.
  7. Temporary access: If temporary access is required within a tree protection zone (TPA), the contractor shall notify the project arborist in advance and review the access requirements and any additional soil protection measures required.
  8. Soil armouring: If it is not possible to fence the entire PRZ, the exposed portion of the PRZ shall be protected with 3/4" plywood or a temporary cover of geotextile and 200mm of road-base, woodchips, or mulch, as specified by the arborist based on recommended soil armouring details.
  9. Materials storage: No equipment, materials or excavated soil shall be placed or stored within the TPA.
  10. Blasting and rock removal near root zones:
    • a) The general contractor will convene a meeting with the arborist and blasting contractor to review the blasting work plan that minimizes rock removal impacts to protected trees.
    • b) Where considered necessary by the arborist, alternate rock removal techniques, such as hoe-ramming, shall be used in place of blasting.
    • c) Blasting vibrations in the vicinity of the Tree Protection Areas are not to exceed a measured peak particle velocity of 25 mm/sec.
      • i) Seismometer records will be kept of all blasting within a 30m radius of any tree protection areas for review by the project arborist.
      • ii) Seismometers shall be placed at the outer boundary of the tree protection area nearest the blast.
    • d) Use DYNAMEE as the explosive product, no fertilizer-based explosive is permitted, due to its toxicity to tree roots.
    • e) The contractor will erect shielding to protect trees from rock debris from the blast site from entering the TPAs.

LEGEND

Symbol Description
[Green circle with black outline] CONIFER
[Hollow circle with central dot] DECIDUOUS
[Solid line circle] TREE CANOPY
[Central dot] TREE CENTRE
[Shaded green area] PROTECTED ROOT ZONE
[Solid green circle] Trees to be retained
[Red X over tree symbol] Trees to be removed
RT REPLACEMENT TREE
20 TREE TAG #
X REMOVE TREE SYMBOL
[Hollow red circle] Remove at Site Servicing
[Solid green circle] Anticipated Removal at Building Permit

REVISION TABLE

REV NO DESCRIPTION DATE
1 FOR SUBDIVISION Dec. 14, 2020
2 FOR SUBDIVISION Jan. 14, 2021
3 FOR CONSTRUCTION July 7, 2021
4 FOR CONSTRUCTION Aug. 31, 2021
Page 182

Document Images

(34)
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Extracted from: 2021 05 11 Committee of the Whole Agenda - Agenda - Pdf