Committee of the Whole/Documents/Staff Report: Capital Project Update
Staff Report

Staff Report: Capital Project Update

June 8, 2021Pages 192–1933 sections

Report from the Manager of Accounting providing current status and expenditure data for 2021 capital projects.

2 APPROVAL OF AGENDA
Approved capital expenditures: $2,609,526Expenditures tracked to May 31, 2021Atkins Rd sidewalk project budget: $843,225

TOWN OF VIEW ROYAL

Page 192–193

Finance and Administration Report

TO: Committee of the Whole
DATE: June 3, 2021
FROM: S. Vella, Manager of Accounting
MEETING: June 8, 2021

Capital Project Update

RECOMMENDATION:

THAT the Committee receive the June 3, 2021 Capital Project Update Report for information.

CHIEF ADMINISTRATIVE OFFICER’S COMMENTS:

I concur with the recommendation.

PURPOSE OF REPORT:

To provide Council with information regarding Capital Project expenditures and projected completion dates.

INFORMATION:

For 2021, the Town has approved capital expenditures of $2,609,526. The attached report outlines budgeted and actual expenditures to May 31, 2021 and current projected completion dates. Due to timing differences between internal reporting timelines and invoices from vendors, there may exist variances between reported costs and actual costs of some projects. As invoices are processed, a more complete calculation of actual variances will be made.

RECOMMENDATION:

THAT the Committee receive the June 3, 2021 Capital Project Update Report for information.

SUBMITTED BY:

S. Vella, Manager of Accounting

REVIEWED BY:

D. Christenson, Director of Finance


Page 192–193

Town of View Royal Capital Project Update Report

For period ending May 31, 2021

Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
Transportation
Sidewalk Projects
11101 Sidewalks 1234 Atkins Rd sidewalk - Anya Crt to Langford border - 843,225 843,225 0% December
Street Lighting Projects
11103 Street Lighting 1236 Pedestrian lighting improvements - 45,000 45,000 0% October
Road Projects
11105 Road Projects 1168 Six Mile Rd improvements 6,206 289,250 283,044 2% September
SUB-TOTAL 6,206 1,177,475 1,171,269
Sewer
Collection System Projects
11701 Collection Systems 1237 Sewer gravity main upgrade - Fort Victoria 1,400 32,000 30,600 4% November
11701 Collection Systems 1238 Sewer gravity main upgrade - Pheasant Lane - 32,000 32,000 0% November
Lift Station Projects
11702 Lift Stations 1211 Helmcken Bay pump station upgrade 2,370 32,000 29,630 7% November
11702 Lift Stations 1162 Thetis Cove pump station upgrade 159,549 190,000 30,451 84% Complete
SUB-TOTAL 163,319 286,000 122,681
Parks
Park Improvement Projects
11302 Park Improvements 0901 Development of road ends Crane Place beach access - 20,000 20,000 0% June
11302 Park Improvements 1175 Parks signage and branding - 10,000 10,000 0% TBD
Park Development Projects
11303 Park Development 1028 View Royal Park - 158,000 158,000 0% November
11303 Park Development 3400 Hart Rd Lime Kiln restoration - 209,471 209,471 0% Deferred
Park Vehicle Projects
11304 Park Vehicles 1067 1996 Kubota tractor/backhoe (2019/2020 c/f) - 81,600 81,600 0% October
11304 Park Vehicles 1221 Small trailer with cargo rack (2020 c/f) - 10,000 10,000 0% July
11304 Park Vehicles 1230 2007 John Deere (2020 c/f) 44,415 56,400 11,985 79% June
11304 Park Vehicles 1235 2006 John Deere (2020 c/f) - 40,000 40,000 0% August
SUB-TOTAL 44,415 585,471 541,056
Building Improvements
Buidling Improvement Projects
11401 Building Improvements 1232 Town Hall lunchroom renovation - 50,000 50,000 0% September
SUB-TOTAL - 50,000 50,000
Fire Services
Fire Vehicle Projects
12102 Fire - Vehicles 0845 Fire apparatus Ladder 35 upgrades - 75,000 75,000 0% October
12102 Fire - Vehicles 1033 2020 Rescue Truck additions - 27,000 27,000 0% September
12102 Fire - Vehicles 1209 Rescue 36 equipment 7,184 8,000 816 90% Complete
12102 Fire - Vehicles 1239 Marine 34 overhaul and upgrade - 50,000 50,000 0% November
Fire Furniture and Equipment Projects
12103 Fire - Furniture and Equip 1227 Public Safety Building - Public art (2019/2020 c/f) 26,603 52,000 25,397 51% September
SUB-TOTAL 33,787 212,000 178,213
Emergency Services
Emergency Program Equipment Projects
12202 Emerg Prog Equipment 0849 ESS equipment and supplies - 23,500 23,500 0% November
12202 Emerg Prog Equipment 0850 EOC equipment and supplies - 19,500 19,500 0% November
SUB-TOTAL - 43,000 43,000
Police Services
Police Machinery and Equipment Projects
12301 Police Services 1103 RCMP building renovation - 20,000 20,000 0% Ongoing
12301 Police Services 1152 RCMP capital projects - 26,880 26,880 0% Ongoing
SUB-TOTAL - 46,880 46,880
Administration / General Government
Information Technology Hardware Projects
13103 Information Tech - Hardware 1044 IT infrastructure hardware replacements (Server replacement) - 18,700 18,700 0% December
13103 Information Tech - Hardware 1070 IT workstation evergreening 18,477 40,000 21,523 46% December
Land Acquisition Projects
13201 Land Acquisitions 1054 Land Acquisitions - Legal (2019 c/f) 7,743 150,000 142,257 5% Complete
SUB-TOTAL 26,219 208,700 182,481
Total 2021 Capital Projects 273,946 2,609,526 2,335,580