Committee of the Whole/Documents/Report dated September 8, 2020 from the Manager of Accounting Re: Capital Project Update
Staff Report

Report dated September 8, 2020 from the Manager of Accounting Re: Capital Project Update

September 15, 2020Pages 52–532 sections

A financial report providing updates on the status and spending of ongoing capital projects in the town.

September 8, 2020Manager of Accounting

Finance and Administration Report

TO: Council DATE: September 8, 2020 FROM: Steven Vella, Manager of Accounting MEETING: September 15, 2020

Capital Project Update

RECOMMENDATION: THAT the Committee receive the September 15, 2020 Capital Project Update Report for information.

CHIEF ADMINISTRATIVE OFFICER’S COMMENTS: I concur with the recommendation.

PURPOSE OF REPORT: To provide Council with information regarding Capital Project expenditures and projected completion dates.

INFORMATION: For 2020, the Town has approved capital expenditures of $3,578,125. The attached report outlines budgeted and actual expenditures to August 31, 2020 and current projected completion dates. Due to timing differences between internal reporting timelines and invoices from vendors, there may exist variances between reported costs and actual costs of some projects. As invoices are processed, a more complete calculation of actual variances will be made.

RECOMMENDATION: THAT the Committee receive the September 15, 2020 Capital Project Update Report for information.

SUBMITTED BY: S. Vella, Manager of Accounting

REVIEWED BY: D. Christenson, Director of Finance


Page 52–53

Capital Project Update Report

For period ending August 31, 2020

Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
Transportation
Sidewalk Projects
11101 Sidewalks 1205 Watkiss Way sidewalk - Eagle Creek to Stoneridge Drive - 25,000 25,000 0% Deferred
11101 Sidewalks 1231 Eltham Rd sidewalk 10,439 10,000 (439) 104% Complete
Street Lighting Projects
11103 Street Lighting 1194 Island Hwy LED lighting upgrade Yr 2 - 45,000 45,000 0% Complete
Road Projects
11105 Road Projects 1168 Six Mile Rd improvements - 96,000 96,000 0% Nov-20
11105 Road Projects 1192 Island Hwy upgrades - Hart Rd. to Wilfert Rd. (2019 c/f) - 200,000 200,000 0% Deferred (partial)
Other Transportation Projects
11106 Other Transportation Projects 1203 Ready Step Roll program - 25,000 25,000 0% Complete
Signal Projects
SUB-TOTAL 10,439 401,000 390,561
Sewer
Lift Station Projects
11702 Lift Stations 1162 Thetis Cove pump station upgrade 31,913 453,000 421,087 7% 2021
SUB-TOTAL 31,913 453,000 421,087
Parks
Park Improvement Projects
11302 Park Improvements 0901 Development of road ends - 20,000 20,000 0% Deferred
11302 Park Improvements 1127 MacLennan Trail improvements - guard rails and paving (2019 c/f) 20,000 20,000 - 100% Complete
11302 Park Improvements 1165 Beaumont access improvements (2019 c/f) 10,887 17,290 6,403 63% Sep-20
11302 Park Improvements 1177 Playground replacement program - Marler Park (2019 c/f) 11,619 10,615 (1,004) 109% Complete
11302 Park Improvements 1215 Portage Park West staircase 60,612 60,000 (612) 101% Complete
11302 Park Improvements 1216 Portage Park toilets - 4,500 4,500 0% Deferred
11302 Park Improvements 1217 Centennial Park toilets - 4,500 4,500 0% Deferred
11302 Park Improvements 1219 View Royal Park water fountain - 13,000 13,000 0% Deferred
11302 Park Improvements 1220 View Royal Park swing set replacement - 25,000 25,000 0% Deferred
11302 Park Improvements 2022 Playground replacement program - Knollwood Park 231 85,000 84,769 0% 2021
Park Vehicle Projects
11304 Park Vehicles 1067 Kubota tractor/backhoe (2019 c/f) - 81,600 81,600 0% Oct-20
11304 Park Vehicles 1132 1/2 ton pickup replacement (2019 c/f) 2,337 3,500 1,163 67% Complete
11304 Park Vehicles 1221 Small trailer with cargo rack - 10,000 10,000 0% Deferred
11304 Park Vehicles 1229 Parks vehicle replacement - 2004 Ford Ranger - 45,000 45,000 Sep-20
11304 Park Vehicles 1230 Parks vehicle replacement - 2007 John Deere - 56,400 56,400 Nov-20
SUB-TOTAL 105,686 456,405 350,719
Building Improvements
Building Improvement Projects
11401 Building Improvements 1226 Ergonomic workstation replacement - 93,600 93,600 0% Deferred
11401 Building Improvements 1232 Town Hall lunchroom renovation - 50,000 50,000 0% Deferred
SUB-TOTAL - 143,600 143,600
Fire Services
Fire Building Projects
12101 Fire - Buildings 1207 Firefighter decontamination room - 15,500 15,500 0% 2021
Fire Vehicle Projects
12102 Fire - Vehicles 0845 Fire apparatus Ladder 35 upgrades - 65,000 65,000 0% Deferred
12102 Fire - Vehicles 1033 Rescue Truck (2019 c/f) - 520,000 520,000 0% Dec-20
12102 Fire - Vehicles 1209 Rescue 36 equipment 16,084 150,000 133,916 11% Dec-20
Fire Furniture and Equipment Projects
12103 Fire - Furniture and Equip 1227 Public Safety Building - Public art (2019 c/f) 16,000 35,000 19,000 46% Mar-21
12103 Fire - Furniture and Equip 1181 Fire dispatch - mobile terminal Yr 3 9,895 14,000 4,105 71% Dec-20
SUB-TOTAL 41,979 799,500 757,521
Emergency Services
Emergency Program Equipment Projects
12202 Emerg Prog Equipment 0849 ESS equipment and supplies 10,699 20,000 9,301 53% Dec-20
12202 Emerg Prog Equipment 0850 EOC equipment and supplies 13,281 12,000 (1,281) 111% Complete
SUB-TOTAL 23,980 32,000 8,020
Police Services
Police Machinery and Equipment Projects
12301 Police Services 1103 RCMP building renovation - 20,000 20,000 0% Ongoing
12301 Police Services 1152 RCMP capital projects - 41,920 41,920 0% Ongoing
SUB-TOTAL - 61,920 61,920
Administration / General Government
Administration Projects
13101 Administration - Software 1038 Records information management system - 165,000 165,000 0% Deferred
13101 Administration - Software 1225 Council meeting webcasting 34,574 - (34,574) Sep-20
Information Technology Hardware Projects
13103 Information Tech - Hardware 1044 IT infrastructure hardware replacements (server/switches) 1,400 3,000 1,600 47% Dec-20
13103 Information Tech - Hardware 1070 IT workstation evergreening 16,886 40,000 23,114 42% Dec-20
Information Technology Software Projects
13103 Information Tech - Software 1039 Microsoft Office Productivity Suite upgrade - 68,000 68,000 0% 2021
13103 Information Tech - Software 1186 Secondary suites online renewal - 25,000 25,000 0% Deferred
13103 Information Tech - Software 4858 Vadim iCity Online upgrade - 29,700 29,700 0% Dec-20
Land Acquisition Projects
13201 Land Acquisitions 1054 Land Acquisitions - Legal (2019 c/f) - 150,000 150,000 0% Ongoing
13201 Land Acquisitions 1233 Little Rd parkland acquisition 751,358 750,000 (1,358) 100% Complete
SUB-TOTAL 804,218 1,230,700 426,482
Total 2020 Capital Projects 1,018,215 3,578,125 2,559,910
Page 52–53